Contaminated soil disposal unit price, Oregon
Low bidders on ODOT contracts carried a median of $122.07 per TON for item 0294-0200010M, contaminated soil disposal, over the 24 months to 13 AUG 2026, across 60 low bids. Half of all 315 bids fell between $94.00 and $180.00.
- Owner
- Oregon DOT
- Item
- 0294-0200010M
- Unit
- TON
- Latest letting
- 13 AUG 2026
By year of letting
| Year | Contracts | Low bids | Low-bid median | All bids | Median, all bids |
|---|---|---|---|---|---|
| 2021 | 21 | 20 | $105.00 | 82 | $107.50 |
| 2022 | 34 | 34 | $140.75 | 108 | $150.00 |
| 2023 | 25 | 25 | $107.00 | 87 | $115.00 |
| 2024 | 35 | 35 | $105.51 | 169 | $126.00 |
| 2025 | 32 | 31 | $125.00 | 173 | $130.00 |
| 2026 | 15 | 15 | $100.00 | 75 | $123.00 |
Bid prices as published, not adjusted for inflation.
By region
| Region | Low bids | Low-bid median | All bids | Median, all bids |
|---|---|---|---|---|
| Region 1 | 26 | $125.00 | 142 | $132.00 |
| Region 2 | 17 | $124.14 | 92 | $132.00 |
| Region 3 | 10 | $122.25 | 42 | $142.50 |
| Region 5 | 4 | $66.60 | 27 | $85.00 |
| Region 4 | 3 | $180.00 | 12 | $147.50 |
Regions with at least three low bids, over the last 24 months.
By quantity
| Quantity (TON) | Low bids | Low-bid median |
|---|---|---|
| 0.75 to 35 | 15 | $225.00 |
| 40 to 122.83 | 15 | $135.00 |
| 123 to 413 | 15 | $100.00 |
| 462 to 10,180 | 15 | $96.00 |
The low bids split into four bands of equal count by the quantity on the contract. Larger quantities usually carry lower unit prices.
Latest contracts with this item
| Let | Contract | Region | Quantity | Low bidder's price | Median | Bids | Source |
|---|---|---|---|---|---|---|---|
| 13 AUG 2026 | 15681 | Region 2 | 42 | $125.00 | $175.00 | 6 | ODOT |
| 13 AUG 2026 | 15679 | Region 3 | 123 | $100.00 | $124.50 | 6 | ODOT |
| 30 JUL 2026 | 15676 | Region 2 | 100 | $140.00 | $160.00 | 6 | ODOT |
| 23 JUL 2026 | 15668 | Region 2 | 203 | $55.00 | $78.00 | 3 | ODOT |
| 23 JUL 2026 | 15675 | Region 2 | 13.50 | $375.00 | $575.00 | 4 | ODOT |
| 25 JUN 2026 | 15673 | Region 1 | 17.50 | $120.00 | $200.00 | 3 | ODOT |
| 11 JUN 2026 | 15671 | Region 1 | 500 | $80.00 | $116.00 | 6 | ODOT |
| 11 JUN 2026 | 15672 | Region 5 | 230 | $55.00 | $97.50 | 6 | ODOT |
| 21 MAY 2026 | 15667 | Region 4 | 100 | $90.00 | $100.00 | 3 | ODOT |
| 07 MAY 2026 | 15664 | Region 2 | 859 | $88.00 | $100.00 | 9 | ODOT |
| 30 APR 2026 | 15643 | Region 1 | 10,180 | $85.00 | $100.00 | 5 | ODOT |
| 02 APR 2026 | 15650 | Region 4 | 60.75 | $180.00 | $140.00 | 5 | ODOT |
| 26 MAR 2026 | 15652 | Region 1 | 8 | $320.00 | $320.00 | 1 | ODOT |
| 12 FEB 2026 | 15637 | Region 1 | 367 | $107.00 | $112.50 | 6 | ODOT |
| 08 JAN 2026 | 15638 | Region 1 | 2,792 | $73.00 | $91.00 | 6 | ODOT |
Filter this item by your own quantity, region and period, or check your price against it, in the ODOT explorer.
How these prices were read
ODOT Bid Data Program yearly workbooks. ODOT publishes rank and unit price only: no bidder names and no bid totals, so these bids cannot be checked against a total and Oregon is left out of the competitor views.
- Statistics leave out bids over three times the low bid, zero or negative prices and token prices under 5% of the median.
- Item codes and units are ODOT's own: this item is compared with ODOT contracts only.
- Prices are bid prices, not paid prices, and are not adjusted for inflation. Use them as a reference range, never as a quote.