Granular structure backfill unit price, Oregon

Low bidders on ODOT contracts carried a median of $122.81 per CY for item 0510-0108000A, granular structure backfill, over the 24 months to 13 AUG 2026, across 17 low bids. Half of all 97 bids fell between $90.00 and $234.38.

Owner
Oregon DOT
Item
0510-0108000A
Unit
CY
Latest letting
13 AUG 2026
$122.81Low bidder's median, per CY
$136.36Median of all bids, per CY
15Contracts in the window

By year of letting

Granular structure backfill, ODOT: unit prices by year
YearContractsLow bidsLow-bid medianAll bidsMedian, all bids
20211222$122.7175$121.95
2022910$235.7139$114.29
2023918$120.7541$174.78
20241114$89.7470$89.83
202578$196.9043$175.44
202645$119.5830$149.48
Granular structure backfill, ODOT: unit prices by year

Bid prices as published, not adjusted for inflation.

By region

Granular structure backfill, ODOT: unit prices by region, last 24 months
RegionLow bidsLow-bid medianAll bidsMedian, all bids
Region 57$119.5848$127.19
Region 25$205.5723$140.91
Region 33$172.4115$104.50
Granular structure backfill, ODOT: unit prices by region, last 24 months

Regions with at least three low bids, over the last 24 months.

By quantity

Granular structure backfill, ODOT: low bidder's median by quantity band
Quantity (CY)Low bidsLow-bid median
2 to 224$371.00
32 to 66.904$121.19
150 to 5004$136.21
622 to 1,4005$64.31
Granular structure backfill, ODOT: low bidder's median by quantity band

The low bids split into four bands of equal count by the quantity on the contract. Larger quantities usually carry lower unit prices.

Latest contracts with this item

Latest ODOT contracts carrying Granular structure backfill
LetContractRegionQuantityLow bidder's priceMedianBidsSource
13 AUG 202615679Region 3622$64.31$88.426ODOT
25 JUN 202615674Region 3203$172.41$124.386ODOT
11 JUN 202615670Region 566.90$119.58$179.516ODOT
11 JUN 202615670Region 566.90$119.58$224.226ODOT
08 JAN 202615638Region 132$781.25$412.506ODOT
11 DEC 202515632Region 557$122.81$175.447ODOT
30 OCT 202515616Region 5170$188.24$150.746ODOT
22 MAY 202515601Region 34$425.00$875.003ODOT
03 APR 202515595Region 222$136.36$136.366ODOT
27 MAR 202515592Region 214$317.00$426.364ODOT
27 MAR 202515592Region 22$535.50$567.754ODOT
30 JAN 202515580Region 2772$205.57$116.585ODOT
30 JAN 202515579Region 5150$100.00$131.678ODOT
12 DEC 202415567Region 2647$85.78$93.124ODOT
31 OCT 202415550Region 11,206$61.77$67.995ODOT
Latest ODOT contracts carrying Granular structure backfill

Filter this item by your own quantity, region and period, or check your price against it, in the ODOT explorer.

How these prices were read

ODOT Bid Data Program yearly workbooks. ODOT publishes rank and unit price only: no bidder names and no bid totals, so these bids cannot be checked against a total and Oregon is left out of the competitor views.

  • Statistics leave out bids over three times the low bid, zero or negative prices and token prices under 5% of the median.
  • Item codes and units are ODOT's own: this item is compared with ODOT contracts only.
  • Prices are bid prices, not paid prices, and are not adjusted for inflation. Use them as a reference range, never as a quote.

Your own bid history, read the same way

Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.

We use your email to reply to you and, now and then, to tell you about Mirage. You can opt out at any time. Privacy policy