Level 4, 1/2 inch acp unit price, Oregon

Low bidders on ODOT contracts carried a median of $145.00 per TON for item 0745-0402000M, level 4, 1/2 inch acp, over the 24 months to 13 AUG 2026, across 11 low bids. Half of all 58 bids fell between $135.00 and $180.00.

Owner
Oregon DOT
Item
0745-0402000M
Unit
TON
Latest letting
13 AUG 2026
$145.00Low bidder's median, per TON
$150.00Median of all bids, per TON
11Contracts in the window

By year of letting

Level 4, 1/2 inch acp, ODOT: unit prices by year
YearContractsLow bidsLow-bid medianAll bidsMedian, all bids
20211010$83.5036$90.00
20221414$130.5034$130.00
20231010$118.7529$132.00
202499$135.0033$135.00
202511$140.005$143.00
202666$155.0041$150.00
Level 4, 1/2 inch acp, ODOT: unit prices by year

Bid prices as published, not adjusted for inflation.

By region

Level 4, 1/2 inch acp, ODOT: unit prices by region, last 24 months
RegionLow bidsLow-bid medianAll bidsMedian, all bids
Region 14$145.0021$170.00
Region 34$155.0021$150.00
Region 23$135.0016$100.25
Level 4, 1/2 inch acp, ODOT: unit prices by region, last 24 months

Regions with at least three low bids, over the last 24 months.

Latest contracts with this item

Latest ODOT contracts carrying Level 4, 1/2 inch acp
LetContractRegionQuantityLow bidder's priceMedianBidsSource
13 AUG 202615679Region 3703$155.00$149.006ODOT
25 JUN 202615674Region 31,350$155.00$149.006ODOT
30 APR 202615643Region 12,364$145.00$175.005ODOT
19 FEB 202615647Region 26,385$99.00$99.0011ODOT
12 FEB 202615637Region 1216$195.00$205.006ODOT
15 JAN 202615640Region 3436$185.00$184.007ODOT
09 JAN 202515571Region 17,906$140.00$143.005ODOT
17 DEC 202415568Region 119,581$145.00$169.005ODOT
31 OCT 202415562Region 327,710$87.43$111.222ODOT
24 SEP 202415438Region 213,500$135.00$135.001ODOT
12 SEP 202415543Region 21,905$137.00$153.004ODOT
23 MAY 202415475Region 230,000$99.00$99.005ODOT
28 MAR 202415512Region 329,007$142.00$142.001ODOT
07 MAR 202415509Region 2220$190.00$195.006ODOT
29 FEB 202415502Region 295,600$88.00$86.502ODOT
Latest ODOT contracts carrying Level 4, 1/2 inch acp

Filter this item by your own quantity, region and period, or check your price against it, in the ODOT explorer.

How these prices were read

ODOT Bid Data Program yearly workbooks. ODOT publishes rank and unit price only: no bidder names and no bid totals, so these bids cannot be checked against a total and Oregon is left out of the competitor views.

  • Statistics leave out bids over three times the low bid, zero or negative prices and token prices under 5% of the median.
  • Item codes and units are ODOT's own: this item is compared with ODOT contracts only.
  • Prices are bid prices, not paid prices, and are not adjusted for inflation. Use them as a reference range, never as a quote.

Your own bid history, read the same way