Removal of surfacings for curb ramp construction unit price, Oregon

Low bidders on ODOT contracts carried a median of $35.34 per SY for item 0310-0106101J, removal of surfacings for curb ramp construction, over the 24 months to 13 AUG 2026, across 30 low bids. Half of all 174 bids fell between $30.00 and $55.00.

Owner
Oregon DOT
Item
0310-0106101J
Unit
SY
Latest letting
30 JUL 2026
$35.34Low bidder's median, per SY
$40.00Median of all bids, per SY
30Contracts in the window

By year of letting

Removal of surfacings for curb ramp construction, ODOT: unit prices by year
YearContractsLow bidsLow-bid medianAll bidsMedian, all bids
202311$40.006$40.00
20241414$42.5075$45.00
20251919$33.00113$40.00
202677$36.0039$38.00
Removal of surfacings for curb ramp construction, ODOT: unit prices by year

Bid prices as published, not adjusted for inflation.

By region

Removal of surfacings for curb ramp construction, ODOT: unit prices by region, last 24 months
RegionLow bidsLow-bid medianAll bidsMedian, all bids
Region 111$34.0077$38.00
Region 27$27.0040$39.00
Region 54$42.5025$46.00
Region 35$45.0019$46.90
Region 43$35.6713$36.00
Removal of surfacings for curb ramp construction, ODOT: unit prices by region, last 24 months

Regions with at least three low bids, over the last 24 months.

By quantity

Removal of surfacings for curb ramp construction, ODOT: low bidder's median by quantity band
Quantity (SY)Low bidsLow-bid median
320 to 2,5457$40.00
3,050 to 6,0008$34.70
6,153 to 9,1007$33.00
9,700 to 25,7208$34.84
Removal of surfacings for curb ramp construction, ODOT: low bidder's median by quantity band

The low bids split into four bands of equal count by the quantity on the contract. Larger quantities usually carry lower unit prices.

Latest contracts with this item

Latest ODOT contracts carrying Removal of surfacings for curb ramp construction
LetContractRegionQuantityLow bidder's priceMedianBidsSource
30 JUL 202615676Region 23,050$40.00$48.756ODOT
23 JUL 202615668Region 219,130$30.00$32.003ODOT
25 JUN 202615673Region 16,000$38.00$65.003ODOT
11 JUN 202615671Region 113,000$36.00$28.756ODOT
11 JUN 202615672Region 56,401$44.00$44.506ODOT
07 MAY 202615664Region 21,004$10.00$20.009ODOT
02 APR 202615650Region 425,720$35.67$34.696ODOT
18 DEC 202515633Region 13,605$31.40$37.5010ODOT
18 DEC 202515607Region 212,687$27.00$27.506ODOT
11 DEC 202515626Region 316,684$50.00$47.006ODOT
30 OCT 202515618Region 19,700$4.50$38.507ODOT
30 OCT 202515624Region 56,743$43.00$45.386ODOT
18 SEP 202515612Region 18,600$33.00$29.009ODOT
11 SEP 202515610Region 21,675$19.00$65.005ODOT
11 SEP 202515614Region 25,537$27.00$45.005ODOT
Latest ODOT contracts carrying Removal of surfacings for curb ramp construction

Filter this item by your own quantity, region and period, or check your price against it, in the ODOT explorer.

How these prices were read

ODOT Bid Data Program yearly workbooks. ODOT publishes rank and unit price only: no bidder names and no bid totals, so these bids cannot be checked against a total and Oregon is left out of the competitor views.

  • Statistics leave out bids over three times the low bid, zero or negative prices and token prices under 5% of the median.
  • Item codes and units are ODOT's own: this item is compared with ODOT contracts only.
  • Prices are bid prices, not paid prices, and are not adjusted for inflation. Use them as a reference range, never as a quote.

Your own bid history, read the same way

Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.

We use your email to reply to you and, now and then, to tell you about Mirage. You can opt out at any time. Privacy policy