Cabinet (eight phase base mounted) unit price, Tennessee
Low bidders on TDOT contracts carried a median of $26,750 per EACH for item 730-15.32, cabinet (eight phase base mounted), over the 24 months to 02 OCT 2026, across 18 low bids. Half of all 65 bids fell between $24,650 and $30,600.
- Owner
- Tennessee DOT
- Item
- 730-15.32
- Unit
- EACH
- Latest letting
- 26 JUN 2026
By year of letting
| Year | Contracts | Low bids | Low-bid median | All bids | Median, all bids |
|---|---|---|---|---|---|
| 2018 | 8 | 8 | $15,115 | 21 | $14,470 |
| 2020 | 5 | 5 | $14,720 | 18 | $15,699 |
| 2023 | 2 | 2 | $44,914 | 8 | $22,783 |
| 2024 | 18 | 18 | $27,425 | 58 | $27,500 |
| 2025 | 5 | 5 | $24,650 | 18 | $27,024 |
| 2026 | 3 | 3 | $28,828 | 14 | $28,828 |
Bid prices as published, not adjusted for inflation.
By quantity
| Quantity (EACH) | Low bids | Low-bid median |
|---|---|---|
| 1 to 1 | 4 | $26,750 |
| 1 to 1 | 5 | $24,137 |
| 2 to 2 | 4 | $31,225 |
| 3 to 19 | 5 | $29,000 |
The low bids split into four bands of equal count by the quantity on the contract. Larger quantities usually carry lower unit prices.
Latest contracts with this item
| Let | Contract | County | Quantity | Low bidder's price | Median | Bids | Low bidder | Source |
|---|---|---|---|---|---|---|---|---|
| 26 JUN 2026 | CN263052 | Maury County | 1 | $28,828 | $28,828 | 8 | Eubank Asphalt Paving & Sealing, LLC | TDOT |
| 26 JUN 2026 | CN263057 | Rutherford County | 7 | $29,120 | $29,710 | 4 | Civil Constructors, LLC | TDOT |
| 08 MAY 2026 | CN263043 | Davidson County | 19 | $25,600 | $26,800 | 2 | Stansell Electric Company, Inc. | TDOT |
| 05 DEC 2025 | CNZ276 | Sullivan County | 4 | $29,000 | $32,947 | 2 | Nicholas Overbay DBA East Tennessee Turf and Landscape | TDOT |
| 15 AUG 2025 | CNZ210 | Claiborne County | 1 | $29,500 | $29,500 | 1 | Southern Constructors, Inc. | TDOT |
| 15 AUG 2025 | CNZ221 | Sumner County | 5 | $24,650 | $27,024 | 6 | Scotty's Contracting & Stone, LLC | TDOT |
| 09 MAY 2025 | CNZ147 | Bedford County | 1 | $21,000 | $20,513 | 6 | Tinsley Asphalt, LLC | TDOT |
| 21 MAR 2025 | CNZ082 | Gibson County | 1 | $23,500 | $29,500 | 3 | Wade Electric Company, Inc. | TDOT |
| 06 DEC 2024 | CNY270 | Benton And Decatur Counties | 2 | $23,700 | $25,250 | 3 | Delta Contracting Company, LLC | TDOT |
| 06 DEC 2024 | CNY228 | Grainger County | 1 | $26,000 | $26,000 | 1 | Southern Constructors, Inc. | TDOT |
| 06 DEC 2024 | CNY294 | Jefferson County | 1 | $27,500 | $27,500 | 1 | Southern Constructors, Inc. | TDOT |
| 06 DEC 2024 | CNY214 | Madison County | 1 | $23,679 | $23,679 | 3 | Ford Construction Company | TDOT |
| 06 DEC 2024 | CNY215 | Williamson County | 1 | $24,137 | $20,811 | 5 | Rogers Group, Inc. | TDOT |
| 18 OCT 2024 | CNY205 | Hamblen County | 3 | $46,000 | $40,300 | 4 | Summers-Taylor, Inc. | TDOT |
| 04 OCT 2024 | CNY221 | Monroe County | 1 | $27,500 | $27,500 | 3 | Whaley Construction, LLC | TDOT |
Filter this item by your own quantity, county and period, or check your price against it, in the TDOT explorer.
How these prices were read
TDOT Summary of Bids PDFs: every letting posted for February 2024 to October 2026, and nine lettings of 2018 to 2023 recovered from archived copies of the tn.gov files. Cost-plus-time bids, and bids that did not match their published total, are left out.
- Statistics leave out bids over three times the low bid, zero or negative prices and token prices under 5% of the median.
- Item codes and units are TDOT's own: this item is compared with TDOT contracts only.
- Prices are bid prices, not paid prices, and are not adjusted for inflation. Use them as a reference range, never as a quote.
Your own bid history, read the same way
Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.