Mineral aggregate, type b base, grading (c or d) unit price, Tennessee
Low bidders on TDOT contracts carried a median of $38.50 per TON for item 303-02, mineral aggregate, type b base, grading (c or d), over the 24 months to 02 OCT 2026, across 58 low bids. Half of all 117 bids fell between $28.00 and $59.00.
- Owner
- Tennessee DOT
- Item
- 303-02
- Unit
- TON
- Latest letting
- 02 OCT 2026
By year of letting
| Year | Contracts | Low bids | Low-bid median | All bids | Median, all bids |
|---|---|---|---|---|---|
| 2018 | 9 | 9 | $34.80 | 12 | $35.40 |
| 2020 | 6 | 6 | $33.67 | 8 | $33.67 |
| 2023 | 3 | 3 | $44.00 | 7 | $43.60 |
| 2024 | 21 | 21 | $24.00 | 45 | $39.98 |
| 2025 | 28 | 28 | $40.62 | 57 | $48.00 |
| 2026 | 22 | 21 | $41.00 | 40 | $48.00 |
Bid prices as published, not adjusted for inflation.
By county
| County | Low bids | Low-bid median | All bids | Median, all bids |
|---|---|---|---|---|
| Shelby County | 6 | $79.10 | 16 | $68.65 |
| Henderson County | 3 | $5.00 | 10 | $30.00 |
| Madison County | 3 | $12.00 | 8 | $32.90 |
| Gibson County | 5 | $39.00 | 7 | $39.00 |
| Tipton County | 4 | $61.20 | 7 | $67.89 |
| Haywood County | 3 | $5.00 | 7 | $30.00 |
| Hardeman County | 4 | $58.23 | 6 | $55.00 |
| Obion County | 4 | $41.50 | 4 | $41.50 |
| Dyer County | 4 | $67.50 | 4 | $67.50 |
Countys with at least three low bids, over the last 24 months.
By quantity
| Quantity (TON) | Low bids | Low-bid median |
|---|---|---|
| 75 to 1,189 | 14 | $62.73 |
| 1,313 to 1,921 | 15 | $29.63 |
| 1,930 to 3,158 | 14 | $34.88 |
| 3,270 to 6,351 | 15 | $7.00 |
The low bids split into four bands of equal count by the quantity on the contract. Larger quantities usually carry lower unit prices.
Latest contracts with this item
| Let | Contract | County | Quantity | Low bidder's price | Median | Bids | Low bidder | Source |
|---|---|---|---|---|---|---|---|---|
| 02 OCT 2026 | CN264061 | Henry And Stewart Counties | 1,921 | $2.50 | $28.00 | 3 | Delta Contracting Company, LLC | TDOT |
| 26 JUN 2026 | CN264043 | Dyer County | 1,877 | $84.00 | $84.00 | 1 | Ford Construction Company | TDOT |
| 26 JUN 2026 | CN264045 | Haywood County | 3,779 | $4.00 | $12.00 | 2 | Delta Contracting Company, LLC | TDOT |
| 26 JUN 2026 | CN264047 | Henderson County | 7,543 | n/a | $30.00 | 1 | Delta Contracting Company, LLC | TDOT |
| 26 JUN 2026 | CN264050 | Henry County | 1,938 | $2.50 | $16.80 | 2 | Delta Contracting Company, LLC | TDOT |
| 26 JUN 2026 | CN264042 | Tipton County | 100 | $70.00 | $70.00 | 3 | Ford Construction Company | TDOT |
| 26 JUN 2026 | CN264904 | Gibson County | 99 | $39.00 | $57.00 | 2 | Delta Contracting Company, LLC | TDOT |
| 08 MAY 2026 | CN264035 | Obion County | 1,560 | $42.00 | $42.00 | 1 | Ford Construction Company | TDOT |
| 20 MAR 2026 | CN264025 | Fayette And Shelby Counties | 3,503 | $82.30 | $71.87 | 3 | APAC-Tennessee, Inc. | TDOT |
| 20 MAR 2026 | CN264019 | Hardeman County | 1,873 | $68.45 | $63.23 | 2 | Asphalt Paving Systems, Inc. | TDOT |
| 20 MAR 2026 | CN264017 | Hardeman County | 1,023 | $68.46 | $60.23 | 2 | Road Worx, Inc. | TDOT |
| 20 MAR 2026 | CN264028 | Hardin County | 3,114 | $5.00 | $45.00 | 3 | Delta Contracting Company, LLC | TDOT |
| 20 MAR 2026 | CN264024 | Haywood County | 1,314 | $5.00 | $20.00 | 2 | Delta Contracting Company, LLC | TDOT |
| 20 MAR 2026 | CN264021 | Obion County | 1,313 | $33.00 | $33.00 | 1 | Ford Construction Company | TDOT |
| 20 MAR 2026 | CN264022 | Obion County | 1,465 | $41.00 | $41.00 | 1 | Ford Construction Company | TDOT |
Filter this item by your own quantity, county and period, or check your price against it, in the TDOT explorer.
How these prices were read
TDOT Summary of Bids PDFs: every letting posted for February 2024 to October 2026, and nine lettings of 2018 to 2023 recovered from archived copies of the tn.gov files. Cost-plus-time bids, and bids that did not match their published total, are left out.
- Statistics leave out bids over three times the low bid, zero or negative prices and token prices under 5% of the median.
- Item codes and units are TDOT's own: this item is compared with TDOT contracts only.
- Prices are bid prices, not paid prices, and are not adjusted for inflation. Use them as a reference range, never as a quote.
Your own bid history, read the same way
Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.