Removable pavement marking (stop line) unit price, Tennessee
Low bidders on TDOT contracts carried a median of $27.00 per LF for item 712-09.04, removable pavement marking (stop line), over the 24 months to 02 OCT 2026, across 44 low bids. Half of all 143 bids fell between $22.35 and $31.91.
- Owner
- Tennessee DOT
- Item
- 712-09.04
- Unit
- LF
- Latest letting
- 02 OCT 2026
By year of letting
| Year | Contracts | Low bids | Low-bid median | All bids | Median, all bids |
|---|---|---|---|---|---|
| 2018 | 9 | 9 | $24.04 | 36 | $22.20 |
| 2020 | 3 | 3 | $34.00 | 11 | $35.00 |
| 2023 | 5 | 5 | $33.60 | 14 | $28.50 |
| 2024 | 26 | 26 | $27.00 | 78 | $28.00 |
| 2025 | 18 | 18 | $27.43 | 57 | $25.00 |
| 2026 | 17 | 17 | $26.40 | 65 | $26.40 |
Bid prices as published, not adjusted for inflation.
By quantity
| Quantity (LF) | Low bids | Low-bid median |
|---|---|---|
| 13 to 24 | 11 | $26.40 |
| 24 to 48 | 11 | $30.00 |
| 48 to 60 | 11 | $25.00 |
| 70 to 427 | 11 | $28.00 |
The low bids split into four bands of equal count by the quantity on the contract. Larger quantities usually carry lower unit prices.
Latest contracts with this item
| Let | Contract | County | Quantity | Low bidder's price | Median | Bids | Low bidder | Source |
|---|---|---|---|---|---|---|---|---|
| 02 OCT 2026 | CN261067 | Carter County | 22 | $27.00 | $29.41 | 4 | Eclipse Companies,LLC | TDOT |
| 02 OCT 2026 | CN261074 | Claiborne County | 24 | $15.00 | $28.00 | 5 | Southern Constructors, Inc. | TDOT |
| 02 OCT 2026 | CN261079 | Hawkins County | 48 | $30.00 | $30.00 | 3 | Southern Constructors, Inc. | TDOT |
| 02 OCT 2026 | CN261072 | Johnson County | 94 | $31.83 | $31.83 | 1 | Baker's Construction Services, Inc. | TDOT |
| 14 AUG 2026 | CN262059 | Coffee County | 24 | $9.00 | $26.00 | 5 | Jones Bros. Contractors, LLC | TDOT |
| 14 AUG 2026 | CN261061 | Knox County | 107 | $15.75 | $17.16 | 4 | Charles Blalock & Sons, Inc. | TDOT |
| 14 AUG 2026 | CN262060 | Meigs County | 48 | $23.06 | $24.00 | 5 | Mid-State Construction Company, Inc. | TDOT |
| 26 JUN 2026 | CN264044 | Hardin County | 48 | $39.49 | $35.50 | 8 | Louis-Company, LLC | TDOT |
| 26 JUN 2026 | CN261901 | Johnson County | 24 | $25.00 | $31.00 | 2 | Southern Constructors, Inc. | TDOT |
| 26 JUN 2026 | CN264037 | Lake County | 108 | $30.00 | $30.00 | 1 | Ford Construction Company | TDOT |
| 26 JUN 2026 | CN261044 | Monroe County | 225 | $21.00 | $21.00 | 6 | Charles Blalock & Sons, Inc. | TDOT |
| 26 JUN 2026 | CN261902 | Roane County | 48 | $27.00 | $28.50 | 4 | Mid-State Construction Company, Inc. | TDOT |
| 08 MAY 2026 | CN261051 | Anderson County | 22 | $33.55 | $27.77 | 4 | J. Hill Excavating, LLC | TDOT |
| 08 MAY 2026 | CN262041 | Cumberland County | 48 | $30.00 | $30.00 | 5 | Capital City Construction Services, LLC | TDOT |
| 20 MAR 2026 | CN261015 | Anderson County | 21 | $26.40 | $26.40 | 5 | Whaley Construction, LLC | TDOT |
Filter this item by your own quantity, county and period, or check your price against it, in the TDOT explorer.
How these prices were read
TDOT Summary of Bids PDFs: every letting posted for February 2024 to October 2026, and nine lettings of 2018 to 2023 recovered from archived copies of the tn.gov files. Cost-plus-time bids, and bids that did not match their published total, are left out.
- Statistics leave out bids over three times the low bid, zero or negative prices and token prices under 5% of the median.
- Item codes and units are TDOT's own: this item is compared with TDOT contracts only.
- Prices are bid prices, not paid prices, and are not adjusted for inflation. Use them as a reference range, never as a quote.
Your own bid history, read the same way