Removal of signal equipment unit price, Tennessee
Low bidders on TDOT contracts carried a median of $3,157.89 per EACH for item 730-01.02, removal of signal equipment, over the 24 months to 02 OCT 2026, across 27 low bids. Half of all 93 bids fell between $2,255.32 and $8,000.00.
- Owner
- Tennessee DOT
- Item
- 730-01.02
- Unit
- EACH
- Latest letting
- 02 OCT 2026
By year of letting
| Year | Contracts | Low bids | Low-bid median | All bids | Median, all bids |
|---|---|---|---|---|---|
| 2018 | 3 | 3 | $1,098.30 | 10 | $1,040.00 |
| 2020 | 3 | 3 | $3,186.00 | 7 | $3,186.00 |
| 2023 | 1 | 1 | $3,500.00 | 5 | $13,154 |
| 2024 | 16 | 16 | $3,883.11 | 54 | $4,138.11 |
| 2025 | 8 | 8 | $3,835.00 | 27 | $4,258.10 |
| 2026 | 10 | 10 | $2,110.00 | 32 | $3,660.00 |
Bid prices as published, not adjusted for inflation.
By county
| County | Low bids | Low-bid median | All bids | Median, all bids |
|---|---|---|---|---|
| Sumner County | 3 | $3,825.00 | 16 | $4,072.39 |
| Rutherford County | 3 | $2,500.00 | 13 | $2,750.00 |
| Shelby County | 3 | $8,480.00 | 8 | $8,577.24 |
Countys with at least three low bids, over the last 24 months.
By quantity
| Quantity (EACH) | Low bids | Low-bid median |
|---|---|---|
| 1 to 1 | 6 | $3,004.00 |
| 1 to 1 | 7 | $10,200 |
| 1 to 2 | 7 | $3,825.00 |
| 2 to 31 | 7 | $1,720.00 |
The low bids split into four bands of equal count by the quantity on the contract. Larger quantities usually carry lower unit prices.
Latest contracts with this item
| Let | Contract | County | Quantity | Low bidder's price | Median | Bids | Low bidder | Source |
|---|---|---|---|---|---|---|---|---|
| 02 OCT 2026 | CN262064 | Bradley County | 1 | $6,000.00 | $4,750.00 | 2 | Davis H. Elliot Construction Company, Inc. | TDOT |
| 02 OCT 2026 | CN262062 | Counties Franklin, Hamilton, Jackson, Mcminn, Putnam, Rhea, And White | 1 | $1,500.00 | $1,016.00 | 2 | Davis H. Elliot Construction Company, Inc. | TDOT |
| 26 JUN 2026 | CN261057 | Hawkins County | 2 | $1,050.00 | $2,909.45 | 4 | Whaley Construction, LLC | TDOT |
| 26 JUN 2026 | CN263052 | Maury County | 1 | $2,500.00 | $3,722.50 | 8 | Eubank Asphalt Paving & Sealing, LLC | TDOT |
| 26 JUN 2026 | CN262050 | Mcminn County | 1 | $1,055.00 | $1,055.00 | 1 | Rogers Group, Inc. | TDOT |
| 26 JUN 2026 | CN261044 | Monroe County | 1 | $11,183 | $10,916 | 6 | Charles Blalock & Sons, Inc. | TDOT |
| 26 JUN 2026 | CN263057 | Rutherford County | 4 | $1,720.00 | $2,770.00 | 4 | Civil Constructors, LLC | TDOT |
| 08 MAY 2026 | CN263043 | Davidson County | 31 | $640.00 | $2,820.00 | 2 | Stansell Electric Company, Inc. | TDOT |
| 08 MAY 2026 | CN261036 | Greene County | 1 | $15,000 | $10,115 | 2 | Davis H. Elliot Construction Company, Inc. | TDOT |
| 06 FEB 2026 | CN261011 | Sevier County | 1 | $13,125 | $13,125 | 1 | Charles Blalock & Sons, Inc. | TDOT |
| 05 DEC 2025 | CNZ276 | Sullivan County | 4 | $10,000 | $7,635.35 | 2 | Nicholas Overbay DBA East Tennessee Turf and Landscape | TDOT |
| 15 AUG 2025 | CNZ221 | Sumner County | 2 | $3,825.00 | $4,193.33 | 6 | Scotty's Contracting & Stone, LLC | TDOT |
| 27 JUN 2025 | CNZ193 | Rutherford County | 2 | $3,845.00 | $7,169.73 | 4 | Capital City Construction Services, LLC | TDOT |
| 09 MAY 2025 | CNZ153 | Wilson County | 2 | $1,500.00 | $1,000.00 | 5 | Sessions Paving Company | TDOT |
| 21 MAR 2025 | CNZ082 | Gibson County | 1 | $3,000.00 | $3,835.00 | 3 | Wade Electric Company, Inc. | TDOT |
Filter this item by your own quantity, county and period, or check your price against it, in the TDOT explorer.
How these prices were read
TDOT Summary of Bids PDFs: every letting posted for February 2024 to October 2026, and nine lettings of 2018 to 2023 recovered from archived copies of the tn.gov files. Cost-plus-time bids, and bids that did not match their published total, are left out.
- Statistics leave out bids over three times the low bid, zero or negative prices and token prices under 5% of the median.
- Item codes and units are TDOT's own: this item is compared with TDOT contracts only.
- Prices are bid prices, not paid prices, and are not adjusted for inflation. Use them as a reference range, never as a quote.
Your own bid history, read the same way