Road & drainage excavation (unclassified) unit price, Tennessee
Low bidders on TDOT contracts carried a median of $33.94 per CY for item 203-01, road & drainage excavation (unclassified), over the 24 months to 02 OCT 2026, across 127 low bids. Half of all 429 bids fell between $20.25 and $60.00.
- Owner
- Tennessee DOT
- Item
- 203-01
- Unit
- CY
- Latest letting
- 02 OCT 2026
By year of letting
| Year | Contracts | Low bids | Low-bid median | All bids | Median, all bids |
|---|---|---|---|---|---|
| 2018 | 11 | 11 | $19.99 | 36 | $19.99 |
| 2020 | 16 | 16 | $19.48 | 56 | $20.60 |
| 2023 | 7 | 7 | $31.00 | 26 | $47.50 |
| 2024 | 60 | 61 | $30.00 | 196 | $37.98 |
| 2025 | 49 | 49 | $36.33 | 164 | $38.76 |
| 2026 | 47 | 47 | $28.00 | 172 | $36.20 |
Bid prices as published, not adjusted for inflation.
By county
| County | Low bids | Low-bid median | All bids | Median, all bids |
|---|---|---|---|---|
| Rutherford County | 6 | $41.38 | 24 | $42.00 |
| Sumner County | 3 | $37.95 | 16 | $47.25 |
| Anderson County | 4 | $26.62 | 16 | $41.20 |
| Williamson County | 4 | $56.97 | 16 | $45.15 |
| Cumberland County | 4 | $27.50 | 16 | $29.12 |
| Shelby County | 5 | $22.97 | 15 | $22.97 |
| Coffee County | 3 | $58.00 | 13 | $50.00 |
| Sullivan County | 5 | $50.00 | 13 | $72.00 |
| Humphreys County | 3 | $65.00 | 12 | $56.20 |
| Bradley County | 3 | $20.25 | 12 | $35.95 |
| Campbell County | 3 | $35.00 | 10 | $37.50 |
| Cocke County | 3 | $60.00 | 10 | $55.50 |
Countys with at least three low bids, over the last 24 months.
By quantity
| Quantity (CY) | Low bids | Low-bid median |
|---|---|---|
| 1.80 to 899 | 31 | $65.00 |
| 1,029 to 4,439 | 32 | $41.00 |
| 4,502 to 16,779 | 32 | $27.10 |
| 17,353 to 955,503 | 32 | $17.40 |
The low bids split into four bands of equal count by the quantity on the contract. Larger quantities usually carry lower unit prices.
Latest contracts with this item
| Let | Contract | County | Quantity | Low bidder's price | Median | Bids | Low bidder | Source |
|---|---|---|---|---|---|---|---|---|
| 02 OCT 2026 | CN261076 | Anderson County | 614 | $32.00 | $60.00 | 4 | Rogers Group, Inc. | TDOT |
| 02 OCT 2026 | CN263064 | Bedford County | 814 | $40.00 | $41.00 | 6 | Jones Bros. Contractors, LLC | TDOT |
| 02 OCT 2026 | CN261070 | Carter County | 1,184 | $43.56 | $114.00 | 3 | Baker's Construction Services, Inc. | TDOT |
| 02 OCT 2026 | CN261067 | Carter County | 824 | $113.00 | $146.00 | 4 | Eclipse Companies,LLC | TDOT |
| 02 OCT 2026 | CN261069 | Cocke County | 33 | $99.97 | $75.94 | 4 | Whaley Construction, LLC | TDOT |
| 02 OCT 2026 | CN264057 | Hardin County | 66,183 | $10.30 | $10.30 | 5 | Delta Contracting Company, LLC | TDOT |
| 02 OCT 2026 | CN261079 | Hawkins County | 8,540 | $40.00 | $40.00 | 3 | Southern Constructors, Inc. | TDOT |
| 02 OCT 2026 | CN263065 | Humphreys County | 453 | $65.00 | $64.50 | 6 | Dement Construction Group, LLC | TDOT |
| 02 OCT 2026 | CN261072 | Johnson County | 10,483 | $48.00 | $48.00 | 1 | Baker's Construction Services, Inc. | TDOT |
| 02 OCT 2026 | CN263066 | Smith County | 6,574 | $24.00 | $43.00 | 4 | Rock Supremacy, LLC | TDOT |
| 02 OCT 2026 | CN261064 | Sullivan County | 88,915 | $15.45 | $15.45 | 1 | Summers-Taylor, Inc. | TDOT |
| 14 AUG 2026 | CN261063 | Campbell County | 23,410 | $24.00 | $25.76 | 5 | Rogers Group, Inc. | TDOT |
| 14 AUG 2026 | CN262059 | Coffee County | 1,604 | $40.00 | $45.00 | 5 | Jones Bros. Contractors, LLC | TDOT |
| 14 AUG 2026 | CN262058 | Cumberland County | 955,503 | $9.84 | $11.18 | 6 | Charles Blalock & Sons, Inc. | TDOT |
| 14 AUG 2026 | CN264048 | Dyer County | 28,015 | $20.00 | $20.00 | 1 | Ford Construction Company | TDOT |
Filter this item by your own quantity, county and period, or check your price against it, in the TDOT explorer.
How these prices were read
TDOT Summary of Bids PDFs: every letting posted for February 2024 to October 2026, and nine lettings of 2018 to 2023 recovered from archived copies of the tn.gov files. Cost-plus-time bids, and bids that did not match their published total, are left out.
- Statistics leave out bids over three times the low bid, zero or negative prices and token prices under 5% of the median.
- Item codes and units are TDOT's own: this item is compared with TDOT contracts only.
- Prices are bid prices, not paid prices, and are not adjusted for inflation. Use them as a reference range, never as a quote.
Your own bid history, read the same way
Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.