Signs (construction) unit price, Tennessee
Low bidders on TDOT contracts carried a median of $8.00 per SF for item 712-06, signs (construction), over the 24 months to 02 OCT 2026, across 520 low bids. Half of all 1,401 bids fell between $7.25 and $9.50.
- Owner
- Tennessee DOT
- Item
- 712-06
- Unit
- SF
- Latest letting
- 02 OCT 2026
By year of letting
| Year | Contracts | Low bids | Low-bid median | All bids | Median, all bids |
|---|---|---|---|---|---|
| 2018 | 109 | 109 | $7.42 | 244 | $7.50 |
| 2019 | 1 | 1 | $14.00 | 4 | $19.50 |
| 2020 | 63 | 64 | $7.38 | 165 | $7.72 |
| 2022 | 2 | 2 | $7.25 | 4 | $7.62 |
| 2023 | 32 | 32 | $8.62 | 79 | $9.00 |
| 2024 | 216 | 217 | $8.50 | 584 | $8.75 |
| 2025 | 243 | 245 | $8.25 | 642 | $8.40 |
| 2026 | 197 | 197 | $7.35 | 548 | $7.53 |
Bid prices as published, not adjusted for inflation.
By county
| County | Low bids | Low-bid median | All bids | Median, all bids |
|---|---|---|---|---|
| Rutherford County | 16 | $7.40 | 66 | $7.67 |
| Shelby County | 21 | $7.62 | 60 | $7.67 |
| Davidson County | 19 | $8.50 | 60 | $7.57 |
| Knox County | 16 | $8.18 | 57 | $8.50 |
| Williamson County | 11 | $7.06 | 50 | $7.50 |
| Maury County | 11 | $7.50 | 43 | $7.50 |
| Cumberland County | 13 | $8.50 | 34 | $8.50 |
| Hamilton County | 14 | $8.15 | 34 | $8.83 |
| Sumner County | 9 | $9.00 | 29 | $8.16 |
| Sullivan County | 13 | $11.35 | 29 | $11.50 |
| Anderson County | 8 | $8.15 | 28 | $8.58 |
| Coffee County | 7 | $8.45 | 24 | $7.98 |
Countys with at least three low bids, over the last 24 months.
By quantity
| Quantity (SF) | Low bids | Low-bid median |
|---|---|---|
| 5 to 628 | 130 | $8.75 |
| 632 to 1,088 | 130 | $8.00 |
| 1,106 to 1,860 | 130 | $7.70 |
| 1,870 to 6,644 | 130 | $7.53 |
The low bids split into four bands of equal count by the quantity on the contract. Larger quantities usually carry lower unit prices.
Latest contracts with this item
| Let | Contract | County | Quantity | Low bidder's price | Median | Bids | Low bidder | Source |
|---|---|---|---|---|---|---|---|---|
| 02 OCT 2026 | CN261076 | Anderson County | 180 | $7.00 | $8.25 | 4 | Rogers Group, Inc. | TDOT |
| 02 OCT 2026 | CN263064 | Bedford County | 124 | $6.10 | $7.38 | 6 | Jones Bros. Contractors, LLC | TDOT |
| 02 OCT 2026 | CN262064 | Bradley County | 69 | $7.25 | $7.62 | 2 | Davis H. Elliot Construction Company, Inc. | TDOT |
| 02 OCT 2026 | CN261070 | Carter County | 601 | $9.68 | $15.00 | 3 | Baker's Construction Services, Inc. | TDOT |
| 02 OCT 2026 | CN261067 | Carter County | 363 | $8.25 | $11.05 | 4 | Eclipse Companies,LLC | TDOT |
| 02 OCT 2026 | CN261074 | Claiborne County | 761 | $15.00 | $9.00 | 5 | Southern Constructors, Inc. | TDOT |
| 02 OCT 2026 | CN261069 | Cocke County | 421 | $8.36 | $8.34 | 4 | Whaley Construction, LLC | TDOT |
| 02 OCT 2026 | CN264057 | Hardin County | 136 | $6.00 | $6.30 | 5 | Delta Contracting Company, LLC | TDOT |
| 02 OCT 2026 | CN261079 | Hawkins County | 331 | $15.00 | $10.95 | 3 | Southern Constructors, Inc. | TDOT |
| 02 OCT 2026 | CN264061 | Henry And Stewart Counties | 1,275 | $6.00 | $7.00 | 3 | Delta Contracting Company, LLC | TDOT |
| 02 OCT 2026 | CN263065 | Humphreys County | 147 | $7.00 | $7.50 | 6 | Dement Construction Group, LLC | TDOT |
| 02 OCT 2026 | CN261072 | Johnson County | 944 | $9.75 | $9.75 | 1 | Baker's Construction Services, Inc. | TDOT |
| 02 OCT 2026 | CN261073 | Knox County | 1,465 | $5.50 | $8.29 | 4 | Bluegrass Contracting Corporation | TDOT |
| 02 OCT 2026 | CN264060 | Shelby County | 568 | $7.00 | $7.00 | 3 | Thomson & Thomson, Inc. | TDOT |
| 02 OCT 2026 | CN263066 | Smith County | 659 | $7.00 | $7.92 | 4 | Rock Supremacy, LLC | TDOT |
Filter this item by your own quantity, county and period, or check your price against it, in the TDOT explorer.
How these prices were read
TDOT Summary of Bids PDFs: every letting posted for February 2024 to October 2026, and nine lettings of 2018 to 2023 recovered from archived copies of the tn.gov files. Cost-plus-time bids, and bids that did not match their published total, are left out.
- Statistics leave out bids over three times the low bid, zero or negative prices and token prices under 5% of the median.
- Item codes and units are TDOT's own: this item is compared with TDOT contracts only.
- Prices are bid prices, not paid prices, and are not adjusted for inflation. Use them as a reference range, never as a quote.