Sodding (new sod) unit price, Tennessee
Low bidders on TDOT contracts carried a median of $6.48 per SY for item 803-01, sodding (new sod), over the 24 months to 02 OCT 2026, across 89 low bids. Half of all 293 bids fell between $5.50 and $8.00.
- Owner
- Tennessee DOT
- Item
- 803-01
- Unit
- SY
- Latest letting
- 02 OCT 2026
By year of letting
| Year | Contracts | Low bids | Low-bid median | All bids | Median, all bids |
|---|---|---|---|---|---|
| 2018 | 13 | 13 | $4.40 | 43 | $4.15 |
| 2020 | 10 | 10 | $4.88 | 35 | $4.75 |
| 2023 | 3 | 3 | $9.50 | 10 | $9.43 |
| 2024 | 43 | 43 | $6.70 | 133 | $6.50 |
| 2025 | 36 | 36 | $6.83 | 120 | $6.97 |
| 2026 | 31 | 31 | $6.30 | 108 | $6.35 |
Bid prices as published, not adjusted for inflation.
By county
| County | Low bids | Low-bid median | All bids | Median, all bids |
|---|---|---|---|---|
| Shelby County | 7 | $9.00 | 19 | $9.45 |
| Rutherford County | 4 | $5.85 | 18 | $5.98 |
| Sumner County | 3 | $5.98 | 16 | $6.32 |
| Williamson County | 3 | $7.03 | 14 | $7.00 |
| Cumberland County | 3 | $6.30 | 14 | $6.53 |
| Coffee County | 3 | $6.70 | 13 | $6.70 |
| Bradley County | 3 | $6.70 | 12 | $7.04 |
| Gibson County | 3 | $4.50 | 10 | $8.25 |
| Hawkins County | 3 | $12.00 | 9 | $12.00 |
| Chester County | 3 | $4.00 | 8 | $4.00 |
Countys with at least three low bids, over the last 24 months.
By quantity
| Quantity (SY) | Low bids | Low-bid median |
|---|---|---|
| 1 to 547 | 22 | $11.25 |
| 584 to 3,504 | 22 | $7.50 |
| 4,166 to 15,593 | 22 | $6.00 |
| 16,980.80 to 164,646 | 23 | $5.00 |
The low bids split into four bands of equal count by the quantity on the contract. Larger quantities usually carry lower unit prices.
Latest contracts with this item
| Let | Contract | County | Quantity | Low bidder's price | Median | Bids | Low bidder | Source |
|---|---|---|---|---|---|---|---|---|
| 02 OCT 2026 | CN263064 | Bedford County | 521 | $10.00 | $10.50 | 6 | Jones Bros. Contractors, LLC | TDOT |
| 02 OCT 2026 | CN264057 | Hardin County | 26,640 | $3.75 | $3.94 | 5 | Delta Contracting Company, LLC | TDOT |
| 02 OCT 2026 | CN261079 | Hawkins County | 277 | $25.00 | $20.00 | 3 | Southern Constructors, Inc. | TDOT |
| 02 OCT 2026 | CN261064 | Sullivan County | 19,930 | $7.03 | $7.03 | 1 | Summers-Taylor, Inc. | TDOT |
| 14 AUG 2026 | CN262059 | Coffee County | 1,720 | $7.10 | $6.84 | 5 | Jones Bros. Contractors, LLC | TDOT |
| 14 AUG 2026 | CN262058 | Cumberland County | 90,102 | $6.30 | $6.40 | 6 | Charles Blalock & Sons, Inc. | TDOT |
| 14 AUG 2026 | CN264048 | Dyer County | 29,630 | $3.50 | $3.50 | 1 | Ford Construction Company | TDOT |
| 14 AUG 2026 | CN262056 | Grundy County | 11,090 | $6.50 | $6.75 | 5 | Mack Construction, LLC | TDOT |
| 14 AUG 2026 | CN261061 | Knox County | 6,142 | $6.30 | $6.72 | 4 | Charles Blalock & Sons, Inc. | TDOT |
| 14 AUG 2026 | CN264054 | Shelby County | 14,091 | $5.00 | $5.25 | 2 | Dement Construction Group, LLC | TDOT |
| 14 AUG 2026 | CN264052 | Tipton County | 15,593 | $3.50 | $3.50 | 2 | Delta Contracting Company, LLC | TDOT |
| 14 AUG 2026 | CN263061 | Humphreys County | 300 | $7.50 | $7.50 | 1 | Dement Construction Group, LLC | TDOT |
| 26 JUN 2026 | CN264041 | Chester County | 2,756 | $4.00 | $4.00 | 2 | Delta Contracting Company, LLC | TDOT |
| 26 JUN 2026 | CN264049 | Dyer County | 455 | $4.50 | $4.50 | 3 | Ford Construction Company | TDOT |
| 26 JUN 2026 | CN261057 | Hawkins County | 2,407 | $8.30 | $7.90 | 4 | Whaley Construction, LLC | TDOT |
Filter this item by your own quantity, county and period, or check your price against it, in the TDOT explorer.
How these prices were read
TDOT Summary of Bids PDFs: every letting posted for February 2024 to October 2026, and nine lettings of 2018 to 2023 recovered from archived copies of the tn.gov files. Cost-plus-time bids, and bids that did not match their published total, are left out.
- Statistics leave out bids over three times the low bid, zero or negative prices and token prices under 5% of the median.
- Item codes and units are TDOT's own: this item is compared with TDOT contracts only.
- Prices are bid prices, not paid prices, and are not adjusted for inflation. Use them as a reference range, never as a quote.
Your own bid history, read the same way