Temporary sediment tube 12IN unit price, Tennessee
Low bidders on TDOT contracts carried a median of $5.55 per LF for item 740-11.02, temporary sediment tube 12in, over the 24 months to 02 OCT 2026, across 40 low bids. Half of all 127 bids fell between $3.87 and $7.72.
- Owner
- Tennessee DOT
- Item
- 740-11.02
- Unit
- LF
- Latest letting
- 02 OCT 2026
By year of letting
| Year | Contracts | Low bids | Low-bid median | All bids | Median, all bids |
|---|---|---|---|---|---|
| 2018 | 4 | 4 | $5.15 | 13 | $4.32 |
| 2020 | 1 | 1 | $4.00 | 4 | $4.00 |
| 2023 | 3 | 3 | $3.50 | 11 | $4.00 |
| 2024 | 19 | 19 | $4.63 | 62 | $5.20 |
| 2025 | 24 | 24 | $5.17 | 76 | $4.60 |
| 2026 | 9 | 9 | $5.25 | 35 | $5.00 |
Bid prices as published, not adjusted for inflation.
By quantity
| Quantity (LF) | Low bids | Low-bid median |
|---|---|---|
| 20 to 425 | 10 | $5.42 |
| 447 to 1,223 | 10 | $6.80 |
| 1,250 to 2,544 | 10 | $5.30 |
| 2,823 to 213,640 | 10 | $4.40 |
The low bids split into four bands of equal count by the quantity on the contract. Larger quantities usually carry lower unit prices.
Latest contracts with this item
| Let | Contract | County | Quantity | Low bidder's price | Median | Bids | Low bidder | Source |
|---|---|---|---|---|---|---|---|---|
| 02 OCT 2026 | CN262064 | Bradley County | 40 | $5.00 | $7.50 | 2 | Davis H. Elliot Construction Company, Inc. | TDOT |
| 02 OCT 2026 | CN261079 | Hawkins County | 2,823 | $10.00 | $5.00 | 3 | Southern Constructors, Inc. | TDOT |
| 14 AUG 2026 | CN262056 | Grundy County | 1,250 | $3.50 | $3.75 | 5 | Mack Construction, LLC | TDOT |
| 26 JUN 2026 | CN262050 | Mcminn County | 20 | $5.25 | $5.25 | 1 | Rogers Group, Inc. | TDOT |
| 26 JUN 2026 | CN261044 | Monroe County | 17,435 | $3.68 | $3.68 | 6 | Charles Blalock & Sons, Inc. | TDOT |
| 08 MAY 2026 | CN264039 | Henderson County | 812 | $6.00 | $6.00 | 3 | Jones Bros. Contractors, LLC | TDOT |
| 20 MAR 2026 | CN261015 | Anderson County | 1,426 | $3.85 | $4.50 | 5 | Whaley Construction, LLC | TDOT |
| 20 MAR 2026 | CN264026 | Shelby County | 4,700 | $6.00 | $5.50 | 6 | Thomson & Thomson, Inc. | TDOT |
| 20 MAR 2026 | CN261026 | Sullivan County | 1,165 | $7.00 | $9.57 | 4 | Southern Constructors, Inc. | TDOT |
| 05 DEC 2025 | CNZ276 | Sullivan County | 775 | $5.50 | $4.99 | 2 | Nicholas Overbay DBA East Tennessee Turf and Landscape | TDOT |
| 03 OCT 2025 | CNZ902 | White County | 1,080 | $4.23 | $4.25 | 5 | Rogers Group, Inc. | TDOT |
| 03 OCT 2025 | CNZ269 | Counties Benton, Carroll, Decatur, Dickson, Fayette, Haywood, Henderson, Humphreys, And Madison | 1,140 | $6.60 | $4.40 | 3 | Shelby Electric Company, Inc. | TDOT |
| 03 OCT 2025 | CNZ273 | Counties Dyer, Giles, Marshall, And Roane | 300 | $4.30 | $10.00 | 2 | Stansell Electric Company, Inc. | TDOT |
| 03 OCT 2025 | CNZ267 | Hamilton County | 1,616 | $4.85 | $5.15 | 2 | Dement Construction Group, LLC | TDOT |
| 03 OCT 2025 | CNZ253 | Scott County | 80 | $7.50 | $9.75 | 2 | Rogers Group, Inc. | TDOT |
Filter this item by your own quantity, county and period, or check your price against it, in the TDOT explorer.
How these prices were read
TDOT Summary of Bids PDFs: every letting posted for February 2024 to October 2026, and nine lettings of 2018 to 2023 recovered from archived copies of the tn.gov files. Cost-plus-time bids, and bids that did not match their published total, are left out.
- Statistics leave out bids over three times the low bid, zero or negative prices and token prices under 5% of the median.
- Item codes and units are TDOT's own: this item is compared with TDOT contracts only.
- Prices are bid prices, not paid prices, and are not adjusted for inflation. Use them as a reference range, never as a quote.
Your own bid history, read the same way