Aggr (ty-pd gr-3 or ty-pl gr-3) unit price, Texas
Low bidders on TxDOT contracts carried a median of $150.00 per CY for item 3166407002, aggr (ty-pd gr-3 or ty-pl gr-3), from 07 FEB 2020 to 10 JUL 2024, across 50 low bids. Half of all 225 bids fell between $130.00 and $230.00.
- Owner
- Texas DOT
- Item
- 3166407002
- Unit
- CY
- Latest letting
- 10 JUL 2024
By year of letting
| Year | Contracts | Low bids | Low-bid median | All bids | Median, all bids |
|---|---|---|---|---|---|
| 2020 | 9 | 9 | $115.00 | 31 | $130.00 |
| 2021 | 12 | 12 | $136.22 | 75 | $140.00 |
| 2022 | 12 | 12 | $147.50 | 49 | $150.00 |
| 2023 | 12 | 12 | $186.50 | 43 | $225.00 |
| 2024 | 5 | 5 | $288.00 | 27 | $288.00 |
Bid prices as published, not adjusted for inflation.
By district
| District | Low bids | Low-bid median | All bids | Median, all bids |
|---|---|---|---|---|
| Tyler District | 44 | $155.00 | 202 | $160.00 |
| Waco District | 5 | $104.35 | 15 | $105.00 |
Districts with at least three low bids, over all lettings.
By quantity
| Quantity (CY) | Low bids | Low-bid median |
|---|---|---|
| 15 to 187 | 12 | $342.50 |
| 193 to 1,169 | 13 | $176.15 |
| 1,250 to 3,600 | 12 | $146.00 |
| 4,352 to 40,145 | 13 | $110.00 |
The low bids split into four bands of equal count by the quantity on the contract. Larger quantities usually carry lower unit prices.
Latest contracts with this item
| Let | Contract | District | Quantity | Low bidder's price | Median | Estimate | Bids | Low bidder | Source |
|---|---|---|---|---|---|---|---|---|---|
| 10 JUL 2024 | 07243208 | San Antonio District | 310 | $347.00 | $280.39 | $311.50 | 8 | ACME BRIDGE COMPANY, INC. | TxDOT |
| 03 MAY 2024 | 05243207 | Tyler District | 44 | $335.00 | $342.50 | $170.00 | 4 | BAKER & COMPANY CONSTRUCTION, LLC | TxDOT |
| 06 MAR 2024 | 03243227 | Tyler District | 76 | $288.00 | $412.50 | $500.00 | 4 | REYNOLDS & KAY, LTD. | TxDOT |
| 01 FEB 2024 | 02243016 | Tyler District | 1,933 | $180.00 | $180.00 | $200.00 | 5 | REYNOLDS & KAY, LTD. | TxDOT |
| 04 JAN 2024 | 01243027 | Tyler District | 775 | $190.00 | $202.50 | $200.00 | 6 | MADDEN CONTRACTING COMPANY, LLC. | TxDOT |
| 06 DEC 2023 | 12233202 | Tyler District | 16,745 | $149.94 | $145.00 | $165.00 | 5 | RONALD R. WAGNER & CO., LP | TxDOT |
| 07 SEP 2023 | 09233206 | Tyler District | 1,169 | $200.00 | $235.00 | $380.00 | 3 | REYNOLDS & KAY, LTD. | TxDOT |
| 06 SEP 2023 | 09233010 | Waco District | 15,115 | $130.00 | $137.72 | $130.00 | 2 | COX PAVING OF TEXAS, INC. | TxDOT |
| 03 AUG 2023 | 08233261 | Tyler District | 65 | $350.00 | $379.50 | $110.00 | 2 | FNH CONSTRUCTION, LLC | TxDOT |
| 02 AUG 2023 | 08233009 | Tyler District | 922 | $180.00 | $180.00 | $190.00 | 3 | HIGHWAY 19 CONSTRUCTION LLC | TxDOT |
| 27 JUN 2023 | 06233422 | Tyler District | 165 | $460.00 | $350.00 | $280.00 | 3 | REYNOLDS & KAY, LTD. | TxDOT |
| 02 JUN 2023 | 06233203 | Tyler District | 1,370 | $190.00 | $190.00 | $180.00 | 3 | L. S. EQUIPMENT CO., INC. | TxDOT |
| 01 JUN 2023 | 06233005 | Tyler District | 1,933 | $183.00 | $150.00 | $220.00 | 3 | MADDEN CONTRACTING COMPANY, LLC. | TxDOT |
| 05 MAY 2023 | 05233230 | Tyler District | 40 | $375.00 | $352.50 | $140.00 | 4 | TRUE ROADS CONSTRUCTION, LLC | TxDOT |
| 08 MAR 2023 | 03233221 | Tyler District | 540 | $175.00 | $205.00 | $185.00 | 4 | MADDEN CONTRACTING COMPANY, LLC. | TxDOT |
Filter this item by your own quantity, district and period, or check your price against it, in the TxDOT explorer.
How these prices were read
TxDOT Bid Tabulations open-data export (data.texas.gov) from September 2024, read 21 November 2026, and TxDOT's legacy Tabulation of Bids pages for January 2020 to August 2024. The legacy pages are a large sample, not every contract: their file names were reused from year to year. Their district is the one TxDOT gives the county. Bids that did not match their published total are left out.
- Statistics leave out bids over three times the low bid, zero or negative prices and token prices under 5% of the median.
- Item codes and units are TxDOT's own: this item is compared with TxDOT contracts only.
- Prices are bid prices, not paid prices, and are not adjusted for inflation. Use them as a reference range, never as a quote.
Your own bid history, read the same way