Approach slab (hpc) unit price, Texas

Low bidders on TxDOT contracts carried a median of $689.32 per CY for item 4226016, approach slab (hpc), from 09 JAN 2020 to 10 JUL 2024, across 124 low bids. Half of all 631 bids fell between $564.27 and $950.00.

Owner
Texas DOT
Item
4226016
Unit
CY
Latest letting
10 JUL 2024
$689.32Low bidder's median, per CY
$690.00Median of all bids, per CY
124Contracts in the window
$695.00Engineer's estimate, median per CY

By year of letting

Approach slab (hpc), TxDOT: unit prices by year
YearContractsLow bidsLow-bid medianAll bidsMedian, all bids
20202020$595.62145$600.00
20213030$540.23203$600.00
20222222$722.5094$755.00
20232828$854.5299$951.86
20242424$771.9590$794.62
Approach slab (hpc), TxDOT: unit prices by year

Bid prices as published, not adjusted for inflation.

By district

Approach slab (hpc), TxDOT: unit prices by district, all lettings
DistrictLow bidsLow-bid medianAll bidsMedian, all bids
Dallas District29$650.00207$625.00
Fort Worth District19$554.0599$625.00
Atlanta District15$600.0081$650.00
Abilene District12$894.2651$1,000.00
Wichita Falls District10$915.0044$750.00
Odessa District9$750.0037$752.96
Amarillo District10$921.8031$900.00
El Paso District10$750.0031$700.00
Childress District3$675.0020$962.50
Approach slab (hpc), TxDOT: unit prices by district, all lettings

Districts with at least three low bids, over all lettings.

By quantity

Approach slab (hpc), TxDOT: low bidder's median by quantity band
Quantity (CY)Low bidsLow-bid median
23.10 to 73.8031$845.00
76.40 to 128.2031$680.00
128.20 to 275.8031$650.00
283 to 4,35031$654.41
Approach slab (hpc), TxDOT: low bidder's median by quantity band

The low bids split into four bands of equal count by the quantity on the contract. Larger quantities usually carry lower unit prices.

Latest contracts with this item

Latest TxDOT contracts carrying Approach slab (hpc)
LetContractDistrictQuantityLow bidder's priceMedianEstimateBidsLow bidderSource
10 JUL 202407243201Dallas District2,628$653.93$638.96$554.002AUSTIN BRIDGE & ROAD SERVICES, LPTxDOT
10 JUL 202407243207Dallas District360$682.00$691.00$750.006HARPER BROTHERS CONSTRUCTION LLCTxDOT
09 JUL 202407243001Fort Worth District1,946.40$750.00$750.00$720.002ZACHRY CONSTRUCTION CORPORATIONTxDOT
09 JUL 202407243002El Paso District838.70$800.00$708.43$700.002SUNDT CONSTRUCTION, INC.TxDOT
09 JUL 202407243005Abilene District243$1,140.00$1,140.00$1,000.003FNF CONSTRUCTION, INC.TxDOT
06 JUN 202406243205Wichita Falls District285.50$840.00$840.00$750.003A. L. HELMCAMP, INC.TxDOT
06 JUN 202406243207Odessa District70.90$1,072.50$1,708.13$900.004JONES BROS. DIRT & PAVING CONTRACTORS, INC.TxDOT
05 JUN 202406243006Brownwood District70.60$1,662.08$1,100.00$625.004ALLEN KELLER COMPANYTxDOT
03 MAY 202405243203El Paso District1,464$700.00$700.00$650.003SUNDT CONSTRUCTION, INC.TxDOT
03 MAY 202405243236Atlanta District84.40$1,000.00$1,000.00$850.004EAST TEXAS BRIDGE, INC.TxDOT
05 APR 202404243202Wichita Falls District2,349.40$617.09$703.16$725.002AUSTIN BRIDGE & ROAD SERVICES, LP ZACHRY CONSTRUCTION CORPORATIONTxDOT
04 APR 202404243001Dallas District3,979$654.41$630.20$800.002SEMA CONSTRUCTION, INC.TxDOT
04 APR 202404243013Abilene District112.40$775.00$1,158.92$1,200.006COPPELL CONSTRUCTION CO., INC.TxDOT
04 APR 202404243017El Paso District58.10$950.00$967.73$800.004DAN WILLIAMS COMPANYTxDOT
06 MAR 202403243201Odessa District761$650.00$650.00$1,100.003SUNDT CONSTRUCTION, INC.TxDOT
Latest TxDOT contracts carrying Approach slab (hpc)

Filter this item by your own quantity, district and period, or check your price against it, in the TxDOT explorer.

How these prices were read

TxDOT Bid Tabulations open-data export (data.texas.gov) from September 2024, read 21 November 2026, and TxDOT's legacy Tabulation of Bids pages for January 2020 to August 2024. The legacy pages are a large sample, not every contract: their file names were reused from year to year. Their district is the one TxDOT gives the county. Bids that did not match their published total are left out.

  • Statistics leave out bids over three times the low bid, zero or negative prices and token prices under 5% of the median.
  • Item codes and units are TxDOT's own: this item is compared with TxDOT contracts only.
  • Prices are bid prices, not paid prices, and are not adjusted for inflation. Use them as a reference range, never as a quote.

Your own bid history, read the same way