Backplate w/refl brdr(5 sec)alum unit price, Texas
Low bidders on TxDOT contracts carried a median of $217.50 per EACH for item 6826053, backplate w/refl brdr(5 sec)alum, from 03 SEP 2020 to 10 JUL 2024, across 40 low bids. Half of all 136 bids fell between $150.08 and $260.00.
- Owner
- Texas DOT
- Item
- 6826053
- Unit
- EACH
- Latest letting
- 10 JUL 2024
By year of letting
| Year | Contracts | Low bids | Low-bid median | All bids | Median, all bids |
|---|---|---|---|---|---|
| 2020 | 5 | 5 | $192.00 | 20 | $152.22 |
| 2021 | 11 | 11 | $160.00 | 56 | $162.70 |
| 2022 | 8 | 8 | $225.26 | 20 | $225.26 |
| 2023 | 7 | 7 | $239.00 | 12 | $239.50 |
| 2024 | 9 | 9 | $263.00 | 28 | $296.68 |
Bid prices as published, not adjusted for inflation.
By district
| District | Low bids | Low-bid median | All bids | Median, all bids |
|---|---|---|---|---|
| Dallas District | 20 | $242.50 | 80 | $207.57 |
| Austin District | 6 | $148.50 | 15 | $150.00 |
| Odessa District | 3 | $160.00 | 10 | $212.50 |
Districts with at least three low bids, over all lettings.
By quantity
| Quantity (EACH) | Low bids | Low-bid median |
|---|---|---|
| 1 to 2 | 10 | $167.50 |
| 2 to 4 | 10 | $225.26 |
| 4 to 10 | 10 | $260.00 |
| 11 to 170 | 10 | $180.00 |
The low bids split into four bands of equal count by the quantity on the contract. Larger quantities usually carry lower unit prices.
Latest contracts with this item
| Let | Contract | District | Quantity | Low bidder's price | Median | Estimate | Bids | Low bidder | Source |
|---|---|---|---|---|---|---|---|---|---|
| 10 JUL 2024 | 07243201 | Dallas District | 3 | $270.00 | $270.00 | $350.00 | 2 | AUSTIN BRIDGE & ROAD SERVICES, LP | TxDOT |
| 06 JUN 2024 | 06243222 | Dallas District | 10 | $235.00 | $281.05 | $350.00 | 4 | DURABLE SPECIALTIES, INC. | TxDOT |
| 06 JUN 2024 | 06243239 | El Paso District | 22 | $215.00 | $366.25 | $1,021.00 | 2 | TRI STATE ELECTRIC, LTD. | TxDOT |
| 02 MAY 2024 | 05243001 | Beaumont District | 11 | $263.00 | $263.00 | $180.00 | 1 | WILLIAMS BROTHERS CONSTRUCTION CO., INC. | TxDOT |
| 04 APR 2024 | 04243020 | Dallas District | 10 | $266.30 | $300.00 | $370.00 | 5 | YUNEX LLC | TxDOT |
| 05 MAR 2024 | 03243004 | Dallas District | 4 | $335.00 | $299.76 | $211.20 | 7 | INDUS ROAD & BRIDGE, INC. | TxDOT |
| 02 FEB 2024 | 02243224 | Dallas District | 17 | $3,540.00 | $1,959.85 | $350.00 | 2 | FNH CONSTRUCTION, LLC | TxDOT |
| 02 FEB 2024 | 02243237 | Odessa District | 2 | $150.00 | $187.50 | $220.00 | 2 | WILLIS ELECTRIC CO., LP | TxDOT |
| 01 FEB 2024 | 02243025 | Austin District | 2 | $220.00 | $220.00 | $180.00 | 3 | AUSTIN TRAFFIC SIGNAL CONSTRUCTION CO., INC. | TxDOT |
| 03 AUG 2023 | 08233272 | Laredo District | 2 | $140.00 | $199.00 | $190.00 | 2 | TRIPLE H FIELD SERVICES, LLC | TxDOT |
| 03 AUG 2023 | 08233273 | Dallas District | 7 | $260.00 | $260.00 | $325.00 | 1 | DURABLE SPECIALTIES, INC. | TxDOT |
| 27 JUN 2023 | 06233457 | Lubbock District | 2 | $239.00 | $232.00 | $250.00 | 2 | WEBBER, LLC | TxDOT |
| 01 JUN 2023 | 06233002 | San Antonio District | 2 | $313.82 | $240.00 | $250.00 | 3 | WEBBER, LLC | TxDOT |
| 01 JUN 2023 | 06233021 | Dallas District | 10 | $350.00 | $305.00 | $300.00 | 2 | FNH CONSTRUCTION, LLC | TxDOT |
| 05 MAY 2023 | 05233223 | Dallas District | 170 | $175.00 | $175.00 | $250.00 | 1 | FNH CONSTRUCTION, LLC | TxDOT |
Filter this item by your own quantity, district and period, or check your price against it, in the TxDOT explorer.
How these prices were read
TxDOT Bid Tabulations open-data export (data.texas.gov) from September 2024, read 21 November 2026, and TxDOT's legacy Tabulation of Bids pages for January 2020 to August 2024. The legacy pages are a large sample, not every contract: their file names were reused from year to year. Their district is the one TxDOT gives the county. Bids that did not match their published total are left out.
- Statistics leave out bids over three times the low bid, zero or negative prices and token prices under 5% of the median.
- Item codes and units are TxDOT's own: this item is compared with TxDOT contracts only.
- Prices are bid prices, not paid prices, and are not adjusted for inflation. Use them as a reference range, never as a quote.
Your own bid history, read the same way
Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.