Block sodding unit price, Texas
Low bidders on TxDOT contracts carried a median of $5.50 per SY for item 1626002, block sodding, from 09 JAN 2020 to 02 AUG 2024, across 588 low bids. Half of all 2,728 bids fell between $4.00 and $8.00.
- Owner
- Texas DOT
- Item
- 1626002
- Unit
- SY
- Latest letting
- 02 AUG 2024
By year of letting
| Year | Contracts | Low bids | Low-bid median | All bids | Median, all bids |
|---|---|---|---|---|---|
| 2020 | 121 | 120 | $5.00 | 722 | $5.00 |
| 2021 | 142 | 142 | $5.00 | 726 | $5.00 |
| 2022 | 116 | 116 | $5.58 | 482 | $5.70 |
| 2023 | 122 | 122 | $6.49 | 419 | $6.85 |
| 2024 | 88 | 88 | $7.00 | 379 | $7.50 |
Bid prices as published, not adjusted for inflation.
By district
| District | Low bids | Low-bid median | All bids | Median, all bids |
|---|---|---|---|---|
| Houston District | 131 | $4.50 | 646 | $4.48 |
| Dallas District | 118 | $5.38 | 589 | $5.00 |
| Fort Worth District | 48 | $8.38 | 217 | $6.00 |
| Lufkin District | 49 | $6.50 | 198 | $6.50 |
| Bryan District | 29 | $6.60 | 146 | $6.15 |
| San Antonio District | 27 | $6.25 | 146 | $6.34 |
| Paris District | 26 | $5.00 | 118 | $6.00 |
| Tyler District | 21 | $6.83 | 106 | $6.50 |
| Beaumont District | 22 | $5.50 | 89 | $6.00 |
| Austin District | 17 | $6.38 | 74 | $6.00 |
| Yoakum District | 18 | $6.00 | 71 | $7.00 |
| Waco District | 14 | $5.25 | 70 | $6.00 |
Districts with at least three low bids, over all lettings.
By quantity
| Quantity (SY) | Low bids | Low-bid median |
|---|---|---|
| 1 to 454 | 147 | $10.00 |
| 458 to 2,446 | 147 | $6.25 |
| 2,447 to 10,359 | 147 | $5.00 |
| 10,471 to 905,671 | 147 | $4.00 |
The low bids split into four bands of equal count by the quantity on the contract. Larger quantities usually carry lower unit prices.
Latest contracts with this item
| Let | Contract | District | Quantity | Low bidder's price | Median | Estimate | Bids | Low bidder | Source |
|---|---|---|---|---|---|---|---|---|---|
| 02 AUG 2024 | 08243202 | Houston District | 55,524 | $3.71 | $4.00 | $5.00 | 4 | JAMES CONSTRUCTION GROUP, LLC | TxDOT |
| 01 AUG 2024 | 08243001 | Houston District | 98,332 | $4.47 | $4.11 | $6.40 | 2 | WEBBER, LLC | TxDOT |
| 10 JUL 2024 | 07243201 | Dallas District | 437,989 | $5.15 | $4.45 | $4.50 | 2 | AUSTIN BRIDGE & ROAD SERVICES, LP | TxDOT |
| 10 JUL 2024 | 07243213 | Lufkin District | 5,673 | $6.60 | $8.30 | $6.50 | 2 | PINTO CONSTRUCTION CO., INC. | TxDOT |
| 10 JUL 2024 | 07243218 | Lufkin District | 3,988 | $6.60 | $10.00 | $10.00 | 3 | TI-ZACK CONCRETE, LLC | TxDOT |
| 10 JUL 2024 | 07243227 | Fort Worth District | 20 | $73.00 | $94.00 | $25.00 | 2 | YUNEX LLC | TxDOT |
| 09 JUL 2024 | 07243009 | Houston District | 1,737 | $4.25 | $4.31 | $5.23 | 8 | BRICE CONSTRUCTION AND DESIGN LLC | TxDOT |
| 09 JUL 2024 | 07243011 | Lufkin District | 4,053 | $12.00 | $8.67 | $10.00 | 5 | GARRET SHIELDS INFRASTRUCTURE | TxDOT |
| 09 JUL 2024 | 07243018 | Bryan District | 143 | $11.00 | $11.00 | $10.00 | 4 | LARRY YOUNG PAVING, INC. | TxDOT |
| 09 JUL 2024 | 07243032 | Dallas District | 4,141 | $4.50 | $6.75 | $4.00 | 3 | AUSTIN BRIDGE & ROAD SERVICES, LP | TxDOT |
| 06 JUN 2024 | 06243201 | San Antonio District | 7,518 | $6.99 | $6.99 | $12.15 | 5 | WEBBER, LLC | TxDOT |
| 06 JUN 2024 | 06243202 | Houston District | 58,695 | $4.25 | $4.25 | $4.00 | 3 | HARPER BROTHERS CONSTRUCTION LLC | TxDOT |
| 06 JUN 2024 | 06243203 | Houston District | 231,433 | $3.55 | $3.55 | $5.00 | 2 | JAMES CONSTRUCTION GROUP, LLC | TxDOT |
| 06 JUN 2024 | 06243204 | Abilene District | 27,106 | $5.50 | $5.69 | $10.00 | 2 | WEBBER, LLC | TxDOT |
| 06 JUN 2024 | 06243208 | Houston District | 73,197 | $4.25 | $4.50 | $8.48 | 6 | R CONSTRUCTION CIVIL, LLC | TxDOT |
Filter this item by your own quantity, district and period, or check your price against it, in the TxDOT explorer.
How these prices were read
TxDOT Bid Tabulations open-data export (data.texas.gov) from September 2024, read 21 November 2026, and TxDOT's legacy Tabulation of Bids pages for January 2020 to August 2024. The legacy pages are a large sample, not every contract: their file names were reused from year to year. Their district is the one TxDOT gives the county. Bids that did not match their published total are left out.
- Statistics leave out bids over three times the low bid, zero or negative prices and token prices under 5% of the median.
- Item codes and units are TxDOT's own: this item is compared with TxDOT contracts only.
- Prices are bid prices, not paid prices, and are not adjusted for inflation. Use them as a reference range, never as a quote.