Low bidders on TxDOT contracts carried a median of $1,090.20 per CY for item 4206037, cl c conc (column), from 09 JAN 2020 to 06 JUN 2024, across 126 low bids. Half of all 676 bids fell between $990.43 and $1,604.97.
- Owner
- Texas DOT
- Item
- 4206037
- Unit
- CY
- Latest letting
- 06 JUN 2024
By year of letting
| Year | Contracts | Low bids | Low-bid median | All bids | Median, all bids |
|---|---|---|---|---|---|
| 2020 | 39 | 39 | $1,000.00 | 234 | $1,150.26 |
| 2021 | 55 | 55 | $1,019.82 | 294 | $1,149.57 |
| 2022 | 30 | 30 | $1,246.87 | 139 | $1,400.00 |
| 2023 | 1 | 1 | $2,800.00 | 5 | $2,517.29 |
| 2024 | 1 | 1 | $1,650.00 | 4 | $1,575.00 |
Bid prices as published, not adjusted for inflation.
By district
| District | Low bids | Low-bid median | All bids | Median, all bids |
|---|---|---|---|---|
| San Antonio District | 15 | $900.00 | 99 | $1,000.00 |
| Yoakum District | 19 | $1,200.00 | 89 | $1,240.00 |
| Corpus Christi District | 13 | $1,019.82 | 71 | $1,130.00 |
| Austin District | 11 | $1,088.11 | 63 | $1,200.00 |
| Houston District | 14 | $1,236.01 | 58 | $1,350.00 |
| Lufkin District | 10 | $1,155.00 | 49 | $1,200.00 |
| Odessa District | 8 | $1,201.94 | 45 | $1,300.00 |
| Waco District | 7 | $1,340.00 | 41 | $1,575.00 |
| Bryan District | 6 | $1,092.98 | 38 | $1,212.50 |
| Childress District | 4 | $1,600.00 | 24 | $1,525.00 |
| Beaumont District | 3 | $1,000.00 | 17 | $1,000.00 |
| Tyler District | 3 | $1,050.00 | 16 | $1,198.00 |
Districts with at least three low bids, over all lettings.
By quantity
| Quantity (CY) | Low bids | Low-bid median |
|---|---|---|
| 1.10 to 15.70 | 31 | $1,500.00 |
| 16.50 to 66.10 | 32 | $1,175.00 |
| 67.30 to 203.60 | 31 | $1,000.00 |
| 210 to 7,070.70 | 32 | $986.80 |
The low bids split into four bands of equal count by the quantity on the contract. Larger quantities usually carry lower unit prices.
Latest contracts with this item
| Let | Contract | District | Quantity | Low bidder's price | Median | Estimate | Bids | Low bidder | Source |
|---|---|---|---|---|---|---|---|---|---|
| 06 JUN 2024 | 06243206 | Childress District | 499.80 | $1,650.00 | $1,575.00 | $2,200.00 | 4 | MORTMARA CONSTRUCTION, INC. | TxDOT |
| 03 AUG 2023 | 08233213 | Childress District | 210.60 | $2,800.00 | $2,517.29 | $2,000.00 | 5 | HODGES AND SON CONSTRUCTION COMPANY, INC. | TxDOT |
| 03 AUG 2022 | 08223020 | Houston District | 61.20 | $1,750.00 | $2,000.00 | $1,300.00 | 3 | HARPER BROTHERS CONSTRUCTION LLC | TxDOT |
| 30 JUN 2022 | 06223617 | Yoakum District | 31.40 | $1,540.18 | $1,720.09 | $1,100.00 | 6 | SB CONTRACTORS LLC | TxDOT |
| 30 JUN 2022 | 06223637 | Yoakum District | 15.70 | $1,300.00 | $1,519.60 | $1,200.00 | 4 | TEXAS STEEL INDUSTRIAL PLACING, LLC | TxDOT |
| 29 JUN 2022 | 06223403 | Odessa District | 116.80 | $1,302.00 | $1,302.00 | $1,400.00 | 3 | JONES BROS. DIRT & PAVING CONTRACTORS, INC. | TxDOT |
| 29 JUN 2022 | 06223404 | Houston District | 127.60 | $1,600.00 | $1,766.46 | $900.00 | 8 | GRANITE CONSTRUCTION COMPANY | TxDOT |
| 29 JUN 2022 | 06223406 | Houston District | 102 | $1,702.00 | $1,881.00 | $870.42 | 5 | ISI CONTRACTING, INC. | TxDOT |
| 29 JUN 2022 | 06223414 | Yoakum District | 52.40 | $1,500.00 | $1,500.00 | $1,100.00 | 4 | JOHN REED AND COMPANY, LLC | TxDOT |
| 02 JUN 2022 | 06223201 | Lufkin District | 203.20 | $1,260.00 | $1,260.00 | $1,000.00 | 5 | LONGVIEW BRIDGE AND ROAD, LTD. | TxDOT |
| 05 MAY 2022 | 05223202 | Austin District | 1,488.70 | $1,285.26 | $1,400.00 | $1,300.00 | 5 | FLUOR HEAVY CIVIL, LLC | TxDOT |
| 07 APR 2022 | 04223202 | Lufkin District | 473.40 | $1,015.00 | $1,242.50 | $1,200.00 | 6 | A. L. HELMCAMP, INC. | TxDOT |
| 07 APR 2022 | 04223226 | Bryan District | 8.40 | $1,600.00 | $1,500.00 | $910.00 | 6 | PIERCE R & B LLC | TxDOT |
| 07 APR 2022 | 04223229 | Paris District | 55 | $1,200.00 | $1,250.00 | $850.00 | 5 | IBCTX, LLC | TxDOT |
| 06 APR 2022 | 04223022 | Bryan District | 7.40 | $985.96 | $1,500.00 | $910.00 | 8 | FUQUA CONSTRUCTION CO., INC. | TxDOT |
Filter this item by your own quantity, district and period, or check your price against it, in the TxDOT explorer.
How these prices were read
TxDOT Bid Tabulations open-data export (data.texas.gov) from September 2024, read 21 November 2026, and TxDOT's legacy Tabulation of Bids pages for January 2020 to August 2024. The legacy pages are a large sample, not every contract: their file names were reused from year to year. Their district is the one TxDOT gives the county. Bids that did not match their published total are left out.
- Statistics leave out bids over three times the low bid, zero or negative prices and token prices under 5% of the median.
- Item codes and units are TxDOT's own: this item is compared with TxDOT contracts only.
- Prices are bid prices, not paid prices, and are not adjusted for inflation. Use them as a reference range, never as a quote.