Conc box culv (5 ft x 3 ft) unit price, Texas

Low bidders on TxDOT contracts carried a median of $480.00 per LF for item 462-7007, conc box culv (5 ft x 3 ft), over the 24 months to 19 NOV 2026, across 41 low bids. Half of all 259 bids fell between $417.54 and $631.00.

Owner
Texas DOT
Item
462-7007
Unit
LF
Latest letting
04 NOV 2026
$480.00Low bidder's median, per LF
$485.00Median of all bids, per LF
41Contracts in the window
$500.00Engineer's estimate, median per LF

By year of letting

Conc box culv (5 ft x 3 ft), TxDOT: unit prices by year
YearContractsLow bidsLow-bid medianAll bidsMedian, all bids
20252121$560.00110$560.65
20262020$448.04149$465.00
Conc box culv (5 ft x 3 ft), TxDOT: unit prices by year

Bid prices as published, not adjusted for inflation.

By district

Conc box culv (5 ft x 3 ft), TxDOT: unit prices by district, last 24 months
DistrictLow bidsLow-bid medianAll bidsMedian, all bids
Dallas District8$477.5056$445.75
Houston District4$386.2037$416.70
Yoakum District5$500.0030$661.51
Tyler District3$465.0022$453.50
San Antonio District3$425.0017$452.25
Fort Worth District3$600.0011$600.00
Odessa District3$610.526$528.56
Conc box culv (5 ft x 3 ft), TxDOT: unit prices by district, last 24 months

Districts with at least three low bids, over the last 24 months.

By quantity

Conc box culv (5 ft x 3 ft), TxDOT: low bidder's median by quantity band
Quantity (LF)Low bidsLow-bid median
20 to 8710$602.38
88 to 20510$492.00
215 to 46810$469.00
556 to 3,64411$413.66
Conc box culv (5 ft x 3 ft), TxDOT: low bidder's median by quantity band

The low bids split into four bands of equal count by the quantity on the contract. Larger quantities usually carry lower unit prices.

Latest contracts with this item

Latest TxDOT contracts carrying Conc box culv (5 ft x 3 ft)
LetContractDistrictQuantityLow bidder's priceMedianEstimateBidsLow bidderSource
04 NOV 2026A00212892Dallas District96$450.00$464.15$525.006INDUS ROAD & BRIDGE, INC.TxDOT
03 NOV 2026A00184974Austin District622$658.08$620.11$650.006AUSTIN BRIDGE & ROAD SERVICES, LPTxDOT
07 OCT 2026A00064192San Antonio District636$446.08$465.00$415.008HUNTER INDUSTRIES, LTD.TxDOT
06 AUG 2026A00191470Houston District3,644$323.56$385.00$430.009JAMES CONSTRUCTION GROUP, LLCTxDOT
06 AUG 2026A00124182Yoakum District318$475.00$475.00$470.003CK NEWBERRY, LLCTxDOT
05 AUG 2026A00068611Houston District456$392.40$392.40$420.007SER CONSTRUCTION PARTNERS, LLCTxDOT
05 AUG 2026A00133874Dallas District68$715.00$512.00$397.007BIG CREEK CONSTRUCTION, LTD.TxDOT
02 JUL 2026A00124174Lubbock District251$360.00$402.85$670.004WILLIAMS BROTHERS CONSTRUCTION CO., INC.TxDOT
02 JUL 2026A00027293Tyler District85$457.00$457.00$480.009BAKER & COMPANY CONSTRUCTION, LLCTxDOT
01 JUL 2026A00190685Houston District1,750$380.00$393.85$425.0011HARPER BROTHERS CONSTRUCTION LLCTxDOT
01 JUL 2026A00058522Tyler District176$465.00$450.00$468.007DRAKE COMPANIES LLCTxDOT
06 MAY 2026A00193380Yoakum District240$425.00$701.50$530.008BIG CREEK CONSTRUCTION, LTD.TxDOT
06 MAY 2026A00014162Dallas District177$499.00$357.36$340.009WEBBER, LLCTxDOT
07 APR 2026A00084334Laredo District2,374$413.66$413.66$540.007HUNTER INDUSTRIES, LTD.TxDOT
07 APR 2026A00059931San Antonio District2,588$375.00$447.51$400.004POSILLICO CIVIL, INC.TxDOT
Latest TxDOT contracts carrying Conc box culv (5 ft x 3 ft)

Filter this item by your own quantity, district and period, or check your price against it, in the TxDOT explorer.

How these prices were read

TxDOT Bid Tabulations open-data export (data.texas.gov) from September 2024, read 21 November 2026, and TxDOT's legacy Tabulation of Bids pages for January 2020 to August 2024. The legacy pages are a large sample, not every contract: their file names were reused from year to year. Their district is the one TxDOT gives the county. Bids that did not match their published total are left out.

  • Statistics leave out bids over three times the low bid, zero or negative prices and token prices under 5% of the median.
  • Item codes and units are TxDOT's own: this item is compared with TxDOT contracts only.
  • Prices are bid prices, not paid prices, and are not adjusted for inflation. Use them as a reference range, never as a quote.

Your own bid history, read the same way

Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.

We use your email to reply to you and, now and then, to tell you about Mirage. You can opt out at any time. Privacy policy