Conc box culv (5 ft x 5 ft) unit price, Texas

Low bidders on TxDOT contracts carried a median of $550.00 per LF for item 4626009002, conc box culv (5 ft x 5 ft), from 09 JAN 2020 to 01 AUG 2024, across 43 low bids. Half of all 196 bids fell between $400.75 and $700.00.

Owner
Texas DOT
Item
4626009002
Unit
LF
Latest letting
01 AUG 2024
$550.00Low bidder's median, per LF
$550.00Median of all bids, per LF
43Contracts in the window
$475.00Engineer's estimate, median per LF

By year of letting

Conc box culv (5 ft x 5 ft), TxDOT: unit prices by year
YearContractsLow bidsLow-bid medianAll bidsMedian, all bids
20201111$535.0064$517.50
20211111$375.0052$425.36
202233$439.8513$500.00
202377$600.0033$680.00
20241111$673.2634$655.11
Conc box culv (5 ft x 5 ft), TxDOT: unit prices by year

Bid prices as published, not adjusted for inflation.

By district

Conc box culv (5 ft x 5 ft), TxDOT: unit prices by district, all lettings
DistrictLow bidsLow-bid medianAll bidsMedian, all bids
Dallas District6$469.9334$475.50
Houston District7$350.1025$350.10
Yoakum District5$757.3022$637.50
Fort Worth District3$600.0017$625.63
San Antonio District3$651.4117$651.41
Beaumont District4$651.638$651.63
Conc box culv (5 ft x 5 ft), TxDOT: unit prices by district, all lettings

Districts with at least three low bids, over all lettings.

By quantity

Conc box culv (5 ft x 5 ft), TxDOT: low bidder's median by quantity band
Quantity (LF)Low bidsLow-bid median
5 to 8110$660.50
87 to 15411$550.00
162 to 41511$450.00
415 to 2,38911$489.85
Conc box culv (5 ft x 5 ft), TxDOT: low bidder's median by quantity band

The low bids split into four bands of equal count by the quantity on the contract. Larger quantities usually carry lower unit prices.

Latest contracts with this item

Latest TxDOT contracts carrying Conc box culv (5 ft x 5 ft)
LetContractDistrictQuantityLow bidder's priceMedianEstimateBidsLow bidderSource
01 AUG 202408243001Houston District1,108$489.85$536.65$664.002WEBBER, LLCTxDOT
10 JUL 202407243201Dallas District1,194$500.00$518.00$750.002AUSTIN BRIDGE & ROAD SERVICES, LPTxDOT
03 MAY 202405243201Yoakum District162$757.30$537.10$660.003PULICE CONSTRUCTION, INC.TxDOT
02 MAY 202405243001Beaumont District2,389$673.26$673.26$400.001WILLIAMS BROTHERS CONSTRUCTION CO., INC.TxDOT
02 MAY 202405243002Laredo District489$506.00$507.88$700.002WEBBER, LLCTxDOT
02 MAY 202405243003Waco District56$700.00$541.12$450.004BIG CREEK CONSTRUCTION, LTD.TxDOT
04 APR 202404243010Beaumont District122$630.00$630.00$555.001TEXAS MATERIALS GROUP, INC.TxDOT
05 MAR 202403243008Yoakum District162$783.56$783.56$540.003HUNTER INDUSTRIES, LTD.TxDOT
02 FEB 202402243208Corpus Christi District116$850.00$850.00$650.005CK NEWBERRY, LLCTxDOT
05 JAN 202401243201Yoakum District928$660.22$625.00$550.007HUNTER INDUSTRIES, LTD.TxDOT
04 JAN 202401243002Yoakum District77$815.38$857.69$760.004HUNTER INDUSTRIES, LTD.TxDOT
06 SEP 202309233001Beaumont District387$555.40$561.93$700.004PULICE CONSTRUCTION, INC.TxDOT
28 JUN 202306233601Dallas District415$515.02$515.02$440.005WILLIAMS BROTHERS CONSTRUCTION CO., INC.TxDOT
27 JUN 202306233419San Antonio District135$651.41$824.00$800.005HUNTER INDUSTRIES, LTD.TxDOT
02 JUN 202306233209Waco District276$450.00$575.00$690.003BIG CREEK CONSTRUCTION, LTD.TxDOT
Latest TxDOT contracts carrying Conc box culv (5 ft x 5 ft)

Filter this item by your own quantity, district and period, or check your price against it, in the TxDOT explorer.

How these prices were read

TxDOT Bid Tabulations open-data export (data.texas.gov) from September 2024, read 21 November 2026, and TxDOT's legacy Tabulation of Bids pages for January 2020 to August 2024. The legacy pages are a large sample, not every contract: their file names were reused from year to year. Their district is the one TxDOT gives the county. Bids that did not match their published total are left out.

  • Statistics leave out bids over three times the low bid, zero or negative prices and token prices under 5% of the median.
  • Item codes and units are TxDOT's own: this item is compared with TxDOT contracts only.
  • Prices are bid prices, not paid prices, and are not adjusted for inflation. Use them as a reference range, never as a quote.

Your own bid history, read the same way

Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.

We use your email to reply to you and, now and then, to tell you about Mirage. You can opt out at any time. Privacy policy