Low bidders on TxDOT contracts carried a median of $14.41 per LF for item 5296011, conc curb (dowel), from 10 JAN 2020 to 02 AUG 2024, across 75 low bids. Half of all 316 bids fell between $10.00 and $26.14.
- Owner
- Texas DOT
- Item
- 5296011
- Unit
- LF
- Latest letting
- 02 AUG 2024
By year of letting
| Year | Contracts | Low bids | Low-bid median | All bids | Median, all bids |
|---|---|---|---|---|---|
| 2020 | 16 | 16 | $14.50 | 85 | $18.18 |
| 2021 | 20 | 20 | $12.59 | 73 | $15.00 |
| 2022 | 18 | 18 | $17.50 | 81 | $14.41 |
| 2023 | 16 | 16 | $15.05 | 59 | $14.24 |
| 2024 | 5 | 5 | $25.37 | 18 | $21.91 |
Bid prices as published, not adjusted for inflation.
By district
| District | Low bids | Low-bid median | All bids | Median, all bids |
|---|---|---|---|---|
| Houston District | 57 | $13.00 | 242 | $14.59 |
| Dallas District | 6 | $19.37 | 27 | $16.00 |
| San Antonio District | 4 | $12.94 | 14 | $13.35 |
Districts with at least three low bids, over all lettings.
By quantity
| Quantity (LF) | Low bids | Low-bid median |
|---|---|---|
| 7 to 128 | 18 | $23.86 |
| 150 to 581 | 19 | $18.18 |
| 627 to 3,278 | 19 | $15.00 |
| 3,353 to 151,246 | 19 | $7.95 |
The low bids split into four bands of equal count by the quantity on the contract. Larger quantities usually carry lower unit prices.
Latest contracts with this item
| Let | Contract | District | Quantity | Low bidder's price | Median | Estimate | Bids | Low bidder | Source |
|---|---|---|---|---|---|---|---|---|---|
| 02 AUG 2024 | 08243202 | Houston District | 562 | $12.59 | $11.29 | $14.00 | 4 | JAMES CONSTRUCTION GROUP, LLC | TxDOT |
| 01 AUG 2024 | 08243001 | Houston District | 2,197 | $25.37 | $17.96 | $13.00 | 2 | WEBBER, LLC | TxDOT |
| 10 JUL 2024 | 07243220 | Houston District | 250 | $37.00 | $42.26 | $12.00 | 4 | STATEWIDE TRAFFIC SIGNAL COMPANY | TxDOT |
| 09 JUL 2024 | 07243014 | Houston District | 470 | $36.00 | $35.50 | $11.00 | 2 | STATEWIDE TRAFFIC SIGNAL COMPANY | TxDOT |
| 06 JUN 2024 | 06243231 | Houston District | 3,353 | $6.80 | $14.50 | $28.73 | 6 | SER CONSTRUCTION PARTNERS, LLC | TxDOT |
| 06 DEC 2023 | 12233212 | Houston District | 7,830 | $13.20 | $15.10 | $11.95 | 6 | RAGLE CONSTRUCTION, INC. | TxDOT |
| 02 NOV 2023 | 11233201 | Odessa District | 3,273 | $20.00 | $19.47 | $15.00 | 5 | SUNDT CONSTRUCTION, INC. | TxDOT |
| 01 NOV 2023 | 11233014 | Houston District | 655 | $10.00 | $12.25 | $10.00 | 4 | MAIN LANE INDUSTRIES LTD. | TxDOT |
| 03 AUG 2023 | 08233207 | Houston District | 8,315 | $5.20 | $7.47 | $9.00 | 4 | SER CONSTRUCTION PARTNERS, LLC | TxDOT |
| 03 AUG 2023 | 08233246 | Houston District | 1,821 | $18.00 | $18.00 | $10.53 | 1 | MAIN LANE INDUSTRIES LTD. | TxDOT |
| 02 AUG 2023 | 08233045 | Houston District | 779 | $71.00 | $71.00 | $20.00 | 1 | TEXAS MATERIALS GROUP, INC. | TxDOT |
| 02 AUG 2023 | 08233053 | Houston District | 105 | $30.00 | $30.00 | $10.53 | 1 | MAIN LANE INDUSTRIES LTD. | TxDOT |
| 28 JUN 2023 | 06233601 | Dallas District | 1,125 | $9.00 | $17.90 | $8.00 | 5 | WILLIAMS BROTHERS CONSTRUCTION CO., INC. | TxDOT |
| 28 JUN 2023 | 06233633 | Houston District | 18 | $35.15 | $47.00 | $19.38 | 4 | TRAF-TEX, INC. | TxDOT |
| 27 JUN 2023 | 06233404 | Houston District | 565 | $6.50 | $8.10 | $8.50 | 5 | BALFOUR BEATTY INFRASTRUCTURE, INC. | TxDOT |
Filter this item by your own quantity, district and period, or check your price against it, in the TxDOT explorer.
How these prices were read
TxDOT Bid Tabulations open-data export (data.texas.gov) from September 2024, read 21 November 2026, and TxDOT's legacy Tabulation of Bids pages for January 2020 to August 2024. The legacy pages are a large sample, not every contract: their file names were reused from year to year. Their district is the one TxDOT gives the county. Bids that did not match their published total are left out.
- Statistics leave out bids over three times the low bid, zero or negative prices and token prices under 5% of the median.
- Item codes and units are TxDOT's own: this item is compared with TxDOT contracts only.
- Prices are bid prices, not paid prices, and are not adjusted for inflation. Use them as a reference range, never as a quote.
Your own bid history, read the same way
Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.