Condt (pvc) (sch 40) (4") unit price, Texas
Low bidders on TxDOT contracts carried a median of $23.80 per LF for item 6186033, condt (pvc) (sch 40) (4"), from 09 JAN 2020 to 10 JUL 2024, across 148 low bids. Half of all 561 bids fell between $17.00 and $31.00.
- Owner
- Texas DOT
- Item
- 6186033
- Unit
- LF
- Latest letting
- 10 JUL 2024
By year of letting
| Year | Contracts | Low bids | Low-bid median | All bids | Median, all bids |
|---|---|---|---|---|---|
| 2020 | 34 | 34 | $16.80 | 144 | $17.34 |
| 2021 | 33 | 33 | $20.50 | 155 | $20.11 |
| 2022 | 22 | 21 | $25.48 | 78 | $29.55 |
| 2023 | 31 | 31 | $30.00 | 94 | $30.00 |
| 2024 | 29 | 29 | $28.56 | 90 | $31.00 |
Bid prices as published, not adjusted for inflation.
By district
| District | Low bids | Low-bid median | All bids | Median, all bids |
|---|---|---|---|---|
| Dallas District | 32 | $26.67 | 157 | $24.90 |
| Pharr District | 25 | $24.00 | 93 | $26.22 |
| Fort Worth District | 19 | $25.50 | 72 | $24.00 |
| Bryan District | 10 | $18.34 | 44 | $17.50 |
| Paris District | 6 | $20.14 | 25 | $24.00 |
| Austin District | 8 | $19.16 | 25 | $22.00 |
| Atlanta District | 7 | $19.00 | 23 | $21.00 |
| Odessa District | 7 | $30.00 | 22 | $30.00 |
| Laredo District | 8 | $18.85 | 21 | $23.60 |
| Corpus Christi District | 4 | $46.50 | 16 | $32.50 |
| Yoakum District | 4 | $23.50 | 15 | $30.00 |
| Tyler District | 3 | $19.00 | 9 | $18.00 |
Districts with at least three low bids, over all lettings.
By quantity
| Quantity (LF) | Low bids | Low-bid median |
|---|---|---|
| 10 to 60 | 37 | $25.48 |
| 60 to 160 | 37 | $26.00 |
| 173 to 689 | 37 | $22.00 |
| 705 to 7,276 | 37 | $21.57 |
The low bids split into four bands of equal count by the quantity on the contract. Larger quantities usually carry lower unit prices.
Latest contracts with this item
| Let | Contract | District | Quantity | Low bidder's price | Median | Estimate | Bids | Low bidder | Source |
|---|---|---|---|---|---|---|---|---|---|
| 10 JUL 2024 | 07243227 | Fort Worth District | 600 | $44.00 | $40.50 | $38.35 | 2 | YUNEX LLC | TxDOT |
| 09 JUL 2024 | 07243001 | Fort Worth District | 50 | $54.00 | $54.00 | $29.50 | 2 | ZACHRY CONSTRUCTION CORPORATION | TxDOT |
| 09 JUL 2024 | 07243002 | El Paso District | 580 | $39.50 | $42.03 | $35.00 | 2 | SUNDT CONSTRUCTION, INC. | TxDOT |
| 09 JUL 2024 | 07243008 | Fort Worth District | 50 | $25.00 | $25.00 | $35.00 | 1 | LIGHT IT UP ELECTRIC | TxDOT |
| 09 JUL 2024 | 07243018 | Bryan District | 10 | $35.00 | $52.65 | $40.00 | 4 | LARRY YOUNG PAVING, INC. | TxDOT |
| 06 JUN 2024 | 06243239 | El Paso District | 60 | $20.00 | $22.87 | $41.00 | 2 | TRI STATE ELECTRIC, LTD. | TxDOT |
| 06 JUN 2024 | 06243241 | Pharr District | 1,575 | $34.40 | $30.00 | $29.84 | 3 | TRAF-TEX, INC. | TxDOT |
| 06 JUN 2024 | 06243254 | Yoakum District | 101 | $24.00 | $40.00 | $34.00 | 5 | STX CIVIL | TxDOT |
| 05 JUN 2024 | 06243025 | Dallas District | 50 | $26.00 | $36.75 | $35.00 | 3 | SELECT MAINTENANCE, L.L.C. | TxDOT |
| 05 JUN 2024 | 06243035 | Corpus Christi District | 230 | $106.80 | $44.44 | $40.00 | 4 | TRAF-TEX, INC. | TxDOT |
| 03 MAY 2024 | 05243202 | Fort Worth District | 850 | $25.50 | $25.38 | $25.00 | 5 | ZACHRY CONSTRUCTION CORPORATION | TxDOT |
| 03 MAY 2024 | 05243238 | Dallas District | 589 | $26.47 | $26.47 | $35.00 | 5 | FLORIDA TRAFFIC CONTROL DEVICES, INC. | TxDOT |
| 02 MAY 2024 | 05243001 | Beaumont District | 3,650 | $19.42 | $19.42 | $15.00 | 1 | WILLIAMS BROTHERS CONSTRUCTION CO., INC. | TxDOT |
| 02 MAY 2024 | 05243002 | Laredo District | 100 | $16.30 | $16.15 | $30.00 | 2 | WEBBER, LLC | TxDOT |
| 02 MAY 2024 | 05243005 | Austin District | 295 | $42.50 | $42.75 | $35.00 | 2 | HARPER BROTHERS CONSTRUCTION LLC | TxDOT |
Filter this item by your own quantity, district and period, or check your price against it, in the TxDOT explorer.
How these prices were read
TxDOT Bid Tabulations open-data export (data.texas.gov) from September 2024, read 21 November 2026, and TxDOT's legacy Tabulation of Bids pages for January 2020 to August 2024. The legacy pages are a large sample, not every contract: their file names were reused from year to year. Their district is the one TxDOT gives the county. Bids that did not match their published total are left out.
- Statistics leave out bids over three times the low bid, zero or negative prices and token prices under 5% of the median.
- Item codes and units are TxDOT's own: this item is compared with TxDOT contracts only.
- Prices are bid prices, not paid prices, and are not adjusted for inflation. Use them as a reference range, never as a quote.