Condt (pvc) (sch 80) (3") (bore) unit price, Texas
Low bidders on TxDOT contracts carried a median of $32.00 per LF for item 618-7061, condt (pvc) (sch 80) (3") (bore), over the 24 months to 19 NOV 2026, across 108 low bids. Half of all 571 bids fell between $26.63 and $45.00.
- Owner
- Texas DOT
- Item
- 618-7061
- Unit
- LF
- Latest letting
- 03 NOV 2026
By year of letting
| Year | Contracts | Low bids | Low-bid median | All bids | Median, all bids |
|---|---|---|---|---|---|
| 2024 | 5 | 5 | $31.50 | 31 | $35.00 |
| 2025 | 51 | 51 | $34.00 | 228 | $36.00 |
| 2026 | 55 | 54 | $30.90 | 324 | $32.00 |
Bid prices as published, not adjusted for inflation.
By district
| District | Low bids | Low-bid median | All bids | Median, all bids |
|---|---|---|---|---|
| Houston District | 20 | $26.52 | 117 | $30.00 |
| Dallas District | 18 | $36.50 | 99 | $40.00 |
| Waco District | 14 | $28.00 | 91 | $35.00 |
| San Antonio District | 17 | $27.00 | 87 | $30.31 |
| Tyler District | 7 | $30.80 | 35 | $27.00 |
| Austin District | 6 | $32.50 | 28 | $36.25 |
| Fort Worth District | 3 | $33.00 | 22 | $34.16 |
| Odessa District | 4 | $44.38 | 17 | $41.00 |
Districts with at least three low bids, over the last 24 months.
By quantity
| Quantity (LF) | Low bids | Low-bid median |
|---|---|---|
| 10 to 335 | 27 | $36.50 |
| 340 to 1,000 | 27 | $33.76 |
| 1,035 to 2,615 | 27 | $30.00 |
| 2,620 to 48,815 | 27 | $30.00 |
The low bids split into four bands of equal count by the quantity on the contract. Larger quantities usually carry lower unit prices.
Latest contracts with this item
| Let | Contract | District | Quantity | Low bidder's price | Median | Estimate | Bids | Low bidder | Source |
|---|---|---|---|---|---|---|---|---|---|
| 03 NOV 2026 | A00206952 | Waco District | 340 | $51.42 | $30.00 | $28.00 | 9 | THE LEVY COMPANY, LLC | TxDOT |
| 07 OCT 2026 | A00064192 | San Antonio District | 950 | $24.00 | $25.50 | $25.60 | 8 | HUNTER INDUSTRIES, LTD. | TxDOT |
| 06 OCT 2026 | A00186301 | Waco District | 6,086 | $28.50 | $33.25 | $30.00 | 6 | BIG CREEK CONSTRUCTION, LTD. | TxDOT |
| 03 SEP 2026 | A00198323 | Dallas District | 50 | $40.00 | $37.58 | $35.00 | 8 | AMERICAN LIGHTING AND SIGNALIZATION, LLC | TxDOT |
| 02 SEP 2026 | A00206625 | Abilene District | 150 | $35.00 | $42.00 | $30.00 | 5 | WILLIS ELECTRIC CO., LP | TxDOT |
| 06 AUG 2026 | A00049653 | Tyler District | 1,265 | $26.65 | $23.75 | $25.00 | 5 | LONGVIEW BRIDGE AND ROAD, LTD. | TxDOT |
| 06 AUG 2026 | A00194280 | Waco District | 2,824 | $33.49 | $34.25 | $38.00 | 8 | Rucoba & Maya Construction, LLC | TxDOT |
| 06 AUG 2026 | A00216599 | Austin District | 2,140 | $31.00 | $31.00 | $33.00 | 5 | AUSTIN TRAFFIC SIGNAL CONSTRUCTION CO., LLC | TxDOT |
| 06 AUG 2026 | A00119935 | Laredo District | 1,000 | $31.54 | $22.60 | $37.00 | 4 | PULICE CONSTRUCTION, INC. | TxDOT |
| 06 AUG 2026 | A00218304 | San Antonio District | 28,095 | $11.30 | $18.20 | $25.50 | 7 | SICE, INC. | TxDOT |
| 06 AUG 2026 | A00140254 | San Angelo District | 355 | $40.00 | $42.50 | $60.00 | 6 | RAGLE CONSTRUCTION, INC. | TxDOT |
| 05 AUG 2026 | A00128458 | Amarillo District | 465 | $41.25 | $18.27 | $50.00 | 4 | J. LEE MILLIGAN, INC. | TxDOT |
| 05 AUG 2026 | A00191471 | Houston District | 6,120 | $32.50 | $34.35 | n/a | 8 | JAMES CONSTRUCTION GROUP, LLC | TxDOT |
| 05 AUG 2026 | A00184368 | Dallas District | 900 | $32.00 | $36.62 | $35.00 | 9 | WG ENGINEERING & CONSTRUCTION, LLC | TxDOT |
| 05 AUG 2026 | A00217697 | Waco District | 825 | $25.00 | $38.00 | $35.00 | 7 | VACA UNDERGROUND UTILITIES INC | TxDOT |
Filter this item by your own quantity, district and period, or check your price against it, in the TxDOT explorer.
How these prices were read
TxDOT Bid Tabulations open-data export (data.texas.gov) from September 2024, read 21 November 2026, and TxDOT's legacy Tabulation of Bids pages for January 2020 to August 2024. The legacy pages are a large sample, not every contract: their file names were reused from year to year. Their district is the one TxDOT gives the county. Bids that did not match their published total are left out.
- Statistics leave out bids over three times the low bid, zero or negative prices and token prices under 5% of the median.
- Item codes and units are TxDOT's own: this item is compared with TxDOT contracts only.
- Prices are bid prices, not paid prices, and are not adjusted for inflation. Use them as a reference range, never as a quote.