Constructing detours unit price, Texas
Low bidders on TxDOT contracts carried a median of $89.78 per SY for item 508-7001, constructing detours, over the 24 months to 19 NOV 2026, across 161 low bids. Half of all 975 bids fell between $75.00 and $150.00.
- Owner
- Texas DOT
- Item
- 508-7001
- Unit
- SY
- Latest letting
- 04 NOV 2026
By year of letting
| Year | Contracts | Low bids | Low-bid median | All bids | Median, all bids |
|---|---|---|---|---|---|
| 2024 | 5 | 5 | $129.70 | 34 | $108.06 |
| 2025 | 79 | 78 | $83.50 | 433 | $110.00 |
| 2026 | 81 | 81 | $90.00 | 527 | $100.00 |
Bid prices as published, not adjusted for inflation.
By district
| District | Low bids | Low-bid median | All bids | Median, all bids |
|---|---|---|---|---|
| Dallas District | 21 | $110.00 | 144 | $115.00 |
| San Antonio District | 15 | $71.92 | 98 | $83.45 |
| Fort Worth District | 16 | $99.50 | 98 | $107.76 |
| Houston District | 8 | $123.03 | 76 | $125.00 |
| Austin District | 10 | $74.75 | 70 | $112.02 |
| Bryan District | 9 | $125.00 | 60 | $114.00 |
| Corpus Christi District | 8 | $121.50 | 57 | $130.00 |
| Pharr District | 12 | $45.00 | 57 | $55.00 |
| Tyler District | 7 | $87.75 | 46 | $119.00 |
| Laredo District | 7 | $77.14 | 43 | $85.00 |
| Abilene District | 5 | $70.00 | 38 | $115.89 |
| Lufkin District | 4 | $150.86 | 29 | $155.00 |
Districts with at least three low bids, over the last 24 months.
By quantity
| Quantity (SY) | Low bids | Low-bid median |
|---|---|---|
| 33 to 678 | 40 | $125.00 |
| 687 to 2,480 | 40 | $88.00 |
| 2,500 to 10,796 | 40 | $74.50 |
| 11,519 to 92,955 | 41 | $80.99 |
The low bids split into four bands of equal count by the quantity on the contract. Larger quantities usually carry lower unit prices.
Latest contracts with this item
| Let | Contract | District | Quantity | Low bidder's price | Median | Estimate | Bids | Low bidder | Source |
|---|---|---|---|---|---|---|---|---|---|
| 04 NOV 2026 | A00193521 | Corpus Christi District | 14,413 | $59.00 | $65.00 | $125.00 | 5 | J E CONSTRUCTION SERVICES, LLC | TxDOT |
| 04 NOV 2026 | A00124162 | Bryan District | 5,819 | $83.00 | $82.50 | $90.00 | 12 | FLUOR ENTERPRISES, INC. | TxDOT |
| 04 NOV 2026 | A00212892 | Dallas District | 56,603 | $95.00 | $94.80 | $85.00 | 6 | INDUS ROAD & BRIDGE, INC. | TxDOT |
| 04 NOV 2026 | A00129572 | Dallas District | 25,823 | $60.00 | $65.50 | $80.00 | 4 | MARIO SINACOLA & SONS EXCAVATING, INC. | TxDOT |
| 07 OCT 2026 | A00064192 | San Antonio District | 38,516 | $83.90 | $82.95 | $80.00 | 8 | HUNTER INDUSTRIES, LTD. | TxDOT |
| 06 OCT 2026 | A00186301 | Waco District | 28,268 | $58.00 | $51.00 | $93.00 | 6 | BIG CREEK CONSTRUCTION, LTD. | TxDOT |
| 06 OCT 2026 | A00134683 | Houston District | 444 | $120.00 | $170.00 | n/a | 9 | GARRET SHIELDS INFRASTRUCTURE | TxDOT |
| 03 SEP 2026 | A00061184 | Austin District | 333 | $34.56 | $34.56 | $80.00 | 7 | HUNTER INDUSTRIES, LTD. | TxDOT |
| 03 SEP 2026 | A00207389 | Childress District | 978 | $55.50 | $80.00 | $55.00 | 7 | COPPELL CONSTRUCTION CO., INC. | TxDOT |
| 02 SEP 2026 | A00121174 | Pharr District | 3,007 | $35.00 | $50.93 | $60.00 | 7 | IOC COMPANY LLC | TxDOT |
| 02 SEP 2026 | A00193937 | Dallas District | 378 | $38.35 | $105.00 | $150.00 | 7 | AUSTIN BRIDGE & ROAD SERVICES, LP | TxDOT |
| 06 AUG 2026 | A00197439 | Austin District | 2,045 | $67.25 | $69.69 | $80.00 | 7 | STX CIVIL | TxDOT |
| 06 AUG 2026 | A00192187 | Beaumont District | 286 | $40.00 | $219.87 | $150.00 | 6 | CASTILLO ARANDA LLC | TxDOT |
| 06 AUG 2026 | A00049653 | Tyler District | 15,901 | $63.50 | $68.00 | $100.00 | 5 | LONGVIEW BRIDGE AND ROAD, LTD. | TxDOT |
| 06 AUG 2026 | A00209034 | Corpus Christi District | 46 | $275.00 | $290.80 | $130.00 | 8 | STX CIVIL | TxDOT |
Filter this item by your own quantity, district and period, or check your price against it, in the TxDOT explorer.
How these prices were read
TxDOT Bid Tabulations open-data export (data.texas.gov) from September 2024, read 21 November 2026, and TxDOT's legacy Tabulation of Bids pages for January 2020 to August 2024. The legacy pages are a large sample, not every contract: their file names were reused from year to year. Their district is the one TxDOT gives the county. Bids that did not match their published total are left out.
- Statistics leave out bids over three times the low bid, zero or negative prices and token prices under 5% of the median.
- Item codes and units are TxDOT's own: this item is compared with TxDOT contracts only.
- Prices are bid prices, not paid prices, and are not adjusted for inflation. Use them as a reference range, never as a quote.
Your own bid history, read the same way