Construction perimeter fence unit price, Texas
Low bidders on TxDOT contracts carried a median of $5.00 per LF for item 5066034005, construction perimeter fence, from 05 NOV 2020 to 01 AUG 2024, across 46 low bids. Half of all 208 bids fell between $3.75 and $10.00.
- Owner
- Texas DOT
- Item
- 5066034005
- Unit
- LF
- Latest letting
- 01 AUG 2024
By year of letting
| Year | Contracts | Low bids | Low-bid median | All bids | Median, all bids |
|---|---|---|---|---|---|
| 2020 | 1 | 1 | $2.50 | 8 | $2.48 |
| 2021 | 15 | 15 | $5.00 | 84 | $5.12 |
| 2022 | 5 | 5 | $4.00 | 27 | $5.00 |
| 2023 | 13 | 13 | $5.00 | 53 | $5.50 |
| 2024 | 12 | 12 | $6.12 | 36 | $6.47 |
Bid prices as published, not adjusted for inflation.
By district
| District | Low bids | Low-bid median | All bids | Median, all bids |
|---|---|---|---|---|
| Lufkin District | 11 | $4.95 | 43 | $5.00 |
| Austin District | 5 | $2.75 | 34 | $2.79 |
| Houston District | 6 | $7.57 | 30 | $8.11 |
| San Antonio District | 5 | $4.50 | 25 | $4.50 |
| Bryan District | 3 | $5.00 | 13 | $5.00 |
| Yoakum District | 3 | $1.50 | 8 | $4.38 |
Districts with at least three low bids, over all lettings.
By quantity
| Quantity (LF) | Low bids | Low-bid median |
|---|---|---|
| 35 to 250 | 11 | $6.00 |
| 275 to 700 | 12 | $5.00 |
| 900 to 1,499 | 11 | $3.80 |
| 2,000 to 51,147 | 12 | $4.78 |
The low bids split into four bands of equal count by the quantity on the contract. Larger quantities usually carry lower unit prices.
Latest contracts with this item
| Let | Contract | District | Quantity | Low bidder's price | Median | Estimate | Bids | Low bidder | Source |
|---|---|---|---|---|---|---|---|---|---|
| 01 AUG 2024 | 08243001 | Houston District | 3,618 | $9.13 | $9.57 | $3.90 | 2 | WEBBER, LLC | TxDOT |
| 10 JUL 2024 | 07243213 | Lufkin District | 250 | $5.50 | $27.75 | $10.00 | 2 | PINTO CONSTRUCTION CO., INC. | TxDOT |
| 09 JUL 2024 | 07243002 | El Paso District | 2,000 | $6.25 | $8.20 | $6.27 | 2 | SUNDT CONSTRUCTION, INC. | TxDOT |
| 06 JUN 2024 | 06243201 | San Antonio District | 80 | $4.50 | $4.85 | $9.10 | 5 | WEBBER, LLC | TxDOT |
| 06 JUN 2024 | 06243204 | Abilene District | 9,569 | $4.60 | $4.63 | $6.00 | 2 | WEBBER, LLC | TxDOT |
| 05 JUN 2024 | 06243003 | Pharr District | 275 | $6.00 | $6.75 | $5.05 | 2 | IOC COMPANY LLC | TxDOT |
| 03 MAY 2024 | 05243201 | Yoakum District | 3,435 | $1.50 | $1.50 | $5.00 | 3 | PULICE CONSTRUCTION, INC. | TxDOT |
| 03 MAY 2024 | 05243215 | San Antonio District | 1,368 | $18.00 | $4.25 | $3.52 | 7 | RELMCO, INC. | TxDOT |
| 03 MAY 2024 | 05243221 | Lufkin District | 419 | $20.00 | $7.75 | $5.00 | 4 | DCC CONSTRUCTION AND SERVICES, L.L.C. | TxDOT |
| 04 APR 2024 | 04243007 | Lufkin District | 430 | $1.00 | $13.00 | $5.00 | 2 | HODGES AND SON CONSTRUCTION COMPANY, INC. | TxDOT |
| 01 FEB 2024 | 02243002 | Lubbock District | 290 | $9.10 | $17.05 | $20.00 | 2 | DUININCK, INC. | TxDOT |
| 05 JAN 2024 | 01243205 | Lufkin District | 180 | $11.00 | $10.72 | $5.00 | 3 | A. L. HELMCAMP, INC. | TxDOT |
| 06 DEC 2023 | 12233201 | Yoakum District | 1,399 | $1.00 | $3.75 | $6.00 | 3 | WILLIAMS BROTHERS CONSTRUCTION CO., INC. | TxDOT |
| 07 SEP 2023 | 09233225 | Houston District | 100 | $6.00 | $10.50 | $5.00 | 2 | JOHN REED AND COMPANY, LLC | TxDOT |
| 03 AUG 2023 | 08233213 | Childress District | 2,508 | $20.00 | $8.00 | $25.00 | 5 | HODGES AND SON CONSTRUCTION COMPANY, INC. | TxDOT |
Filter this item by your own quantity, district and period, or check your price against it, in the TxDOT explorer.
How these prices were read
TxDOT Bid Tabulations open-data export (data.texas.gov) from September 2024, read 21 November 2026, and TxDOT's legacy Tabulation of Bids pages for January 2020 to August 2024. The legacy pages are a large sample, not every contract: their file names were reused from year to year. Their district is the one TxDOT gives the county. Bids that did not match their published total are left out.
- Statistics leave out bids over three times the low bid, zero or negative prices and token prices under 5% of the median.
- Item codes and units are TxDOT's own: this item is compared with TxDOT contracts only.
- Prices are bid prices, not paid prices, and are not adjusted for inflation. Use them as a reference range, never as a quote.