Curb ramps (ty 1) unit price, Texas
Low bidders on TxDOT contracts carried a median of $142.53 per SY for item 5316018, curb ramps (ty 1), from 07 MAY 2020 to 06 JUN 2024, across 63 low bids. Half of all 256 bids fell between $132.34 and $260.86.
- Owner
- Texas DOT
- Item
- 5316018
- Unit
- SY
- Latest letting
- 06 JUN 2024
By year of letting
| Year | Contracts | Low bids | Low-bid median | All bids | Median, all bids |
|---|---|---|---|---|---|
| 2020 | 11 | 11 | $110.00 | 49 | $160.00 |
| 2021 | 13 | 13 | $121.50 | 56 | $156.50 |
| 2022 | 18 | 18 | $162.50 | 65 | $178.00 |
| 2023 | 12 | 12 | $142.50 | 41 | $185.00 |
| 2024 | 9 | 9 | $154.56 | 45 | $203.82 |
Bid prices as published, not adjusted for inflation.
By district
| District | Low bids | Low-bid median | All bids | Median, all bids |
|---|---|---|---|---|
| Corpus Christi District | 9 | $120.00 | 49 | $225.00 |
| Yoakum District | 12 | $140.00 | 46 | $197.50 |
| Lubbock District | 11 | $125.00 | 31 | $140.00 |
| San Antonio District | 6 | $167.50 | 22 | $153.50 |
| Odessa District | 4 | $143.25 | 17 | $157.00 |
| Fort Worth District | 3 | $110.00 | 16 | $175.00 |
| Amarillo District | 4 | $142.50 | 15 | $174.00 |
| San Angelo District | 5 | $158.00 | 13 | $200.00 |
Districts with at least three low bids, over all lettings.
By quantity
| Quantity (SY) | Low bids | Low-bid median |
|---|---|---|
| 7 to 25 | 15 | $225.00 |
| 30 to 62 | 16 | $146.63 |
| 63 to 232.40 | 16 | $139.72 |
| 253 to 1,401 | 16 | $117.50 |
The low bids split into four bands of equal count by the quantity on the contract. Larger quantities usually carry lower unit prices.
Latest contracts with this item
| Let | Contract | District | Quantity | Low bidder's price | Median | Estimate | Bids | Low bidder | Source |
|---|---|---|---|---|---|---|---|---|---|
| 06 JUN 2024 | 06243225 | San Angelo District | 40 | $158.00 | $168.68 | $165.00 | 3 | RELMCO, INC. | TxDOT |
| 06 JUN 2024 | 06243226 | Amarillo District | 139 | $139.43 | $156.31 | $150.00 | 4 | TI-ZACK CONCRETE, LLC | TxDOT |
| 06 JUN 2024 | 06243245 | Corpus Christi District | 40 | $275.00 | $252.50 | $150.00 | 6 | MAKO CONTRACTING, LLC | TxDOT |
| 05 JUN 2024 | 06243026 | Tyler District | 51 | $154.56 | $250.00 | $165.00 | 9 | 3LW CIVIL LLC | TxDOT |
| 05 JUN 2024 | 06243058 | Amarillo District | 58 | $146.26 | $161.06 | $150.00 | 2 | TI-ZACK CONCRETE, LLC | TxDOT |
| 03 MAY 2024 | 05243237 | Pharr District | 99 | $165.00 | $175.09 | $165.00 | 6 | TEXAS CORDIA CONSTRUCTION, LLC | TxDOT |
| 05 APR 2024 | 04243217 | Yoakum District | 360.60 | $140.00 | $260.00 | $150.00 | 5 | VACA UNDERGROUND UTILITIES INC | TxDOT |
| 04 APR 2024 | 04243024 | Waco District | 30 | $142.53 | $244.50 | $170.00 | 6 | TI-ZACK CONCRETE, LLC | TxDOT |
| 04 JAN 2024 | 01243002 | Yoakum District | 10 | $1,295.96 | $837.98 | $153.00 | 4 | HUNTER INDUSTRIES, LTD. | TxDOT |
| 06 DEC 2023 | 12233207 | Amarillo District | 489 | $140.00 | $174.00 | $175.00 | 5 | TI-ZACK CONCRETE, INC. | TxDOT |
| 05 DEC 2023 | 12233012 | Amarillo District | 170 | $145.00 | $192.50 | $175.00 | 4 | TI-ZACK CONCRETE, INC. | TxDOT |
| 01 NOV 2023 | 11233019 | San Antonio District | 9 | $185.00 | $185.00 | $182.97 | 1 | E-Z BEL CONSTRUCTION, LLC | TxDOT |
| 01 NOV 2023 | 11233020 | Lubbock District | 253 | $95.00 | $231.22 | $244.00 | 4 | STX CIVIL | TxDOT |
| 06 SEP 2023 | 09233032 | Tyler District | 14 | $1,200.00 | $556.50 | $146.20 | 4 | WG ENGINEERING & CONSTRUCTION, LLC | TxDOT |
| 03 AUG 2023 | 08233209 | Lubbock District | 9 | $3,200.00 | $1,737.50 | $250.00 | 2 | WEBBER, LLC | TxDOT |
Filter this item by your own quantity, district and period, or check your price against it, in the TxDOT explorer.
How these prices were read
TxDOT Bid Tabulations open-data export (data.texas.gov) from September 2024, read 21 November 2026, and TxDOT's legacy Tabulation of Bids pages for January 2020 to August 2024. The legacy pages are a large sample, not every contract: their file names were reused from year to year. Their district is the one TxDOT gives the county. Bids that did not match their published total are left out.
- Statistics leave out bids over three times the low bid, zero or negative prices and token prices under 5% of the median.
- Item codes and units are TxDOT's own: this item is compared with TxDOT contracts only.
- Prices are bid prices, not paid prices, and are not adjusted for inflation. Use them as a reference range, never as a quote.
Your own bid history, read the same way
Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.