Cut & restore asph paving unit price, Texas
Low bidders on TxDOT contracts carried a median of $184.67 per SY for item 400-7008, cut & restore asph paving, over the 24 months to 19 NOV 2026, across 103 low bids. Half of all 646 bids fell between $110.00 and $250.00.
- Owner
- Texas DOT
- Item
- 400-7008
- Unit
- SY
- Latest letting
- 10 NOV 2026
By year of letting
| Year | Contracts | Low bids | Low-bid median | All bids | Median, all bids |
|---|---|---|---|---|---|
| 2024 | 3 | 3 | $389.50 | 22 | $222.50 |
| 2025 | 50 | 49 | $200.00 | 300 | $200.00 |
| 2026 | 54 | 54 | $162.00 | 346 | $154.50 |
Bid prices as published, not adjusted for inflation.
By district
| District | Low bids | Low-bid median | All bids | Median, all bids |
|---|---|---|---|---|
| Atlanta District | 9 | $150.00 | 64 | $157.50 |
| Austin District | 7 | $188.04 | 58 | $180.00 |
| Fort Worth District | 9 | $262.00 | 56 | $200.00 |
| Pharr District | 9 | $80.00 | 55 | $85.00 |
| Paris District | 10 | $225.00 | 49 | $175.50 |
| Dallas District | 7 | $170.00 | 48 | $200.00 |
| Tyler District | 6 | $237.50 | 44 | $208.00 |
| San Antonio District | 6 | $128.75 | 34 | $150.00 |
| Yoakum District | 5 | $275.92 | 34 | $181.80 |
| Lufkin District | 5 | $180.00 | 33 | $191.65 |
| Wichita Falls District | 4 | $192.33 | 29 | $200.00 |
| Waco District | 5 | $200.00 | 27 | $190.00 |
Districts with at least three low bids, over the last 24 months.
By quantity
| Quantity (SY) | Low bids | Low-bid median |
|---|---|---|
| 3 to 40 | 25 | $210.02 |
| 42 to 140 | 26 | $200.00 |
| 149 to 446 | 26 | $155.50 |
| 456 to 5,619 | 26 | $148.81 |
The low bids split into four bands of equal count by the quantity on the contract. Larger quantities usually carry lower unit prices.
Latest contracts with this item
| Let | Contract | District | Quantity | Low bidder's price | Median | Estimate | Bids | Low bidder | Source |
|---|---|---|---|---|---|---|---|---|---|
| 10 NOV 2026 | A00219095 | Odessa District | 10 | $1,000.00 | $980.00 | $525.00 | 3 | SCR CIVIL CONSTRUCTION, LLC | TxDOT |
| 04 NOV 2026 | A00206631 | Bryan District | 138 | $240.00 | $100.00 | $140.00 | 7 | BIG CREEK CONSTRUCTION, LTD. | TxDOT |
| 03 NOV 2026 | A00184974 | Austin District | 5,619 | $147.63 | $178.33 | $91.00 | 6 | AUSTIN BRIDGE & ROAD SERVICES, LP | TxDOT |
| 13 OCT 2026 | A00223040 | Tyler District | 48 | $350.00 | $350.00 | $250.00 | 7 | ICOS MANAGEMENT, LLC | TxDOT |
| 06 OCT 2026 | A00207643 | Paris District | 381 | $250.00 | $100.00 | $195.60 | 7 | HIGHWAY 19 CONSTRUCTION LLC | TxDOT |
| 03 SEP 2026 | A00123454 | Pharr District | 262 | $81.75 | $95.00 | $100.00 | 5 | REIM CONSTRUCTION, INC. | TxDOT |
| 03 SEP 2026 | A00191741 | Houston District | 1,263 | $130.00 | $130.00 | $150.00 | 7 | CASTILLO ARANDA LLC | TxDOT |
| 03 SEP 2026 | A00061184 | Austin District | 12 | $210.02 | $203.70 | $125.00 | 8 | HUNTER INDUSTRIES, LTD. | TxDOT |
| 03 SEP 2026 | A00207181 | Yoakum District | 101 | $275.92 | $140.00 | $180.00 | 7 | 3LW CIVIL LLC | TxDOT |
| 06 AUG 2026 | A00196275 | Atlanta District | 6 | $195.00 | $350.00 | $300.00 | 5 | MADDEN CONTRACTING COMPANY, LLC. | TxDOT |
| 06 AUG 2026 | A00049653 | Tyler District | 173 | $161.00 | $161.00 | $135.00 | 5 | LONGVIEW BRIDGE AND ROAD, LTD. | TxDOT |
| 06 AUG 2026 | A00062075 | Fort Worth District | 40 | $525.00 | $400.00 | $450.00 | 7 | INDUS ROAD & BRIDGE, INC. | TxDOT |
| 06 AUG 2026 | A00219498 | Wichita Falls District | 213 | $120.00 | $150.00 | $200.00 | 3 | GARRET SHIELDS INFRASTRUCTURE | TxDOT |
| 05 AUG 2026 | A00007222 | Fort Worth District | 1,879 | $262.00 | $125.00 | $13.00 | 11 | INDUS ROAD & BRIDGE, INC. | TxDOT |
| 05 AUG 2026 | A00068611 | Houston District | 88 | $331.70 | $233.56 | $180.00 | 7 | SER CONSTRUCTION PARTNERS, LLC | TxDOT |
Filter this item by your own quantity, district and period, or check your price against it, in the TxDOT explorer.
How these prices were read
TxDOT Bid Tabulations open-data export (data.texas.gov) from September 2024, read 21 November 2026, and TxDOT's legacy Tabulation of Bids pages for January 2020 to August 2024. The legacy pages are a large sample, not every contract: their file names were reused from year to year. Their district is the one TxDOT gives the county. Bids that did not match their published total are left out.
- Statistics leave out bids over three times the low bid, zero or negative prices and token prices under 5% of the median.
- Item codes and units are TxDOT's own: this item is compared with TxDOT contracts only.
- Prices are bid prices, not paid prices, and are not adjusted for inflation. Use them as a reference range, never as a quote.