Debris removal (cntr medians/mainlanes) unit price, Texas
Low bidders on TxDOT contracts carried a median of $1,819.84 per CYC for item 7356001, debris removal (cntr medians/mainlanes), from 10 JAN 2020 to 01 AUG 2024, across 48 low bids. Half of all 182 bids fell between $1,000.00 and $2,800.00.
- Owner
- Texas DOT
- Item
- 7356001
- Unit
- CYC
- Latest letting
- 01 AUG 2024
By year of letting
| Year | Contracts | Low bids | Low-bid median | All bids | Median, all bids |
|---|---|---|---|---|---|
| 2020 | 4 | 4 | $1,664.30 | 21 | $1,279.85 |
| 2021 | 13 | 12 | $1,150.00 | 42 | $1,162.19 |
| 2022 | 8 | 8 | $746.79 | 28 | $2,000.00 |
| 2023 | 15 | 15 | $2,201.83 | 58 | $2,450.00 |
| 2024 | 9 | 9 | $2,415.00 | 33 | $2,083.02 |
Bid prices as published, not adjusted for inflation.
By district
| District | Low bids | Low-bid median | All bids | Median, all bids |
|---|---|---|---|---|
| Houston District | 19 | $1,767.68 | 82 | $1,758.84 |
| Dallas District | 9 | $1,250.00 | 35 | $1,800.00 |
| San Antonio District | 4 | $1,500.00 | 21 | $1,300.00 |
| Yoakum District | 5 | $3,200.00 | 14 | $3,400.00 |
Districts with at least three low bids, over all lettings.
By quantity
| Quantity (CYC) | Low bids | Low-bid median |
|---|---|---|
| 2 to 12 | 12 | $1,936.00 |
| 12 to 34 | 12 | $1,178.15 |
| 36 to 53 | 12 | $2,350.00 |
| 54 to 416 | 12 | $809.99 |
The low bids split into four bands of equal count by the quantity on the contract. Larger quantities usually carry lower unit prices.
Latest contracts with this item
| Let | Contract | District | Quantity | Low bidder's price | Median | Estimate | Bids | Low bidder | Source |
|---|---|---|---|---|---|---|---|---|---|
| 01 AUG 2024 | 08243001 | Houston District | 53 | $2,500.00 | $3,500.00 | $2,808.00 | 2 | WEBBER, LLC | TxDOT |
| 10 JUL 2024 | 07243201 | Dallas District | 34 | $1,000.00 | $2,250.00 | $2,000.00 | 2 | AUSTIN BRIDGE & ROAD SERVICES, LP | TxDOT |
| 06 JUN 2024 | 06243201 | San Antonio District | 45 | $2,895.58 | $2,083.02 | $2,000.00 | 5 | WEBBER, LLC | TxDOT |
| 03 MAY 2024 | 05243201 | Yoakum District | 56 | $6,798.11 | $4,300.00 | $3,000.00 | 3 | PULICE CONSTRUCTION, INC. | TxDOT |
| 03 MAY 2024 | 05243215 | San Antonio District | 16 | $2,000.00 | $1,165.98 | $183.82 | 7 | RELMCO, INC. | TxDOT |
| 02 MAY 2024 | 05243001 | Beaumont District | 48 | $4,200.00 | $4,200.00 | $2,450.00 | 1 | WILLIAMS BROTHERS CONSTRUCTION CO., INC. | TxDOT |
| 06 MAR 2024 | 03243201 | Odessa District | 44 | $2,200.00 | $2,200.00 | $8,700.00 | 3 | SUNDT CONSTRUCTION, INC. | TxDOT |
| 05 MAR 2024 | 03243002 | Houston District | 23 | $2,415.00 | $2,359.77 | $1,875.00 | 4 | SER CONSTRUCTION PARTNERS, LLC | TxDOT |
| 05 MAR 2024 | 03243017 | San Antonio District | 38 | $1,000.00 | $1,213.00 | $1,400.00 | 6 | J3 COMPANY, LLC | TxDOT |
| 06 DEC 2023 | 12233201 | Yoakum District | 54 | $4,300.00 | $4,300.00 | $1,500.00 | 3 | WILLIAMS BROTHERS CONSTRUCTION CO., INC. | TxDOT |
| 06 DEC 2023 | 12233212 | Houston District | 6 | $250.00 | $1,625.00 | $2,490.00 | 6 | RAGLE CONSTRUCTION, INC. | TxDOT |
| 02 NOV 2023 | 11233201 | Odessa District | 53 | $1,100.00 | $3,000.00 | $2,000.00 | 5 | SUNDT CONSTRUCTION, INC. | TxDOT |
| 07 SEP 2023 | 09233224 | Houston District | 2 | $3,500.00 | $3,500.00 | $1,500.00 | 3 | FORDE CONSTRUCTION COMPANY, INC. | TxDOT |
| 03 AUG 2023 | 08233203 | Dallas District | 8 | $1,872.00 | $6,186.00 | $900.00 | 2 | WEBBER, LLC | TxDOT |
| 03 AUG 2023 | 08233204 | Yoakum District | 16 | $2,250.00 | $2,250.00 | $2,500.00 | 1 | HUNTER INDUSTRIES, LTD. | TxDOT |
Filter this item by your own quantity, district and period, or check your price against it, in the TxDOT explorer.
How these prices were read
TxDOT Bid Tabulations open-data export (data.texas.gov) from September 2024, read 21 November 2026, and TxDOT's legacy Tabulation of Bids pages for January 2020 to August 2024. The legacy pages are a large sample, not every contract: their file names were reused from year to year. Their district is the one TxDOT gives the county. Bids that did not match their published total are left out.
- Statistics leave out bids over three times the low bid, zero or negative prices and token prices under 5% of the median.
- Item codes and units are TxDOT's own: this item is compared with TxDOT contracts only.
- Prices are bid prices, not paid prices, and are not adjusted for inflation. Use them as a reference range, never as a quote.
Your own bid history, read the same way
Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.