Downstream anchor terminal section unit price, Texas

Low bidders on TxDOT contracts carried a median of $1,491.35 per EACH for item 540-7015, downstream anchor terminal section, over the 24 months to 19 NOV 2026, across 348 low bids. Half of all 1,964 bids fell between $1,300.00 and $1,800.00.

Owner
Texas DOT
Item
540-7015
Unit
EACH
Latest letting
12 NOV 2026
$1,491.35Low bidder's median, per EACH
$1,500.00Median of all bids, per EACH
356Contracts in the window
$1,500.00Engineer's estimate, median per EACH

By year of letting

Downstream anchor terminal section, TxDOT: unit prices by year
YearContractsLow bidsLow-bid medianAll bidsMedian, all bids
20241212$1,344.7569$1,500.00
2025176172$1,457.09908$1,500.00
2026173169$1,500.001,012$1,500.00
Downstream anchor terminal section, TxDOT: unit prices by year

Bid prices as published, not adjusted for inflation.

By district

Downstream anchor terminal section, TxDOT: unit prices by district, last 24 months
DistrictLow bidsLow-bid medianAll bidsMedian, all bids
Houston District45$1,400.00277$1,585.00
Dallas District40$1,386.80231$1,475.00
Fort Worth District26$1,300.00180$1,390.00
San Antonio District29$1,396.00172$1,446.15
Austin District19$1,510.00136$1,500.00
Waco District14$1,410.97112$1,466.50
Pharr District17$1,665.4980$1,700.00
Beaumont District16$1,500.0078$1,692.58
Bryan District12$1,500.0068$1,525.00
Lufkin District13$1,300.0060$1,500.00
Yoakum District8$1,993.0056$1,598.78
Abilene District9$1,531.1755$1,450.00
Downstream anchor terminal section, TxDOT: unit prices by district, last 24 months

Districts with at least three low bids, over the last 24 months.

By quantity

Downstream anchor terminal section, TxDOT: low bidder's median by quantity band
Quantity (EACH)Low bidsLow-bid median
1 to 287$1,600.00
2 to 487$1,500.00
4 to 887$1,324.00
8 to 10087$1,403.42
Downstream anchor terminal section, TxDOT: low bidder's median by quantity band

The low bids split into four bands of equal count by the quantity on the contract. Larger quantities usually carry lower unit prices.

Latest contracts with this item

Latest TxDOT contracts carrying Downstream anchor terminal section
LetContractDistrictQuantityLow bidder's priceMedianEstimateBidsLow bidderSource
12 NOV 2026A00222854Amarillo District1$5,287.50$2,100.00$1,700.007TI-ZACK CONCRETE, LLCTxDOT
04 NOV 2026A00124162Bryan District7$1,314.00$1,329.50$1,700.0012FLUOR ENTERPRISES, INC.TxDOT
04 NOV 2026A00212892Dallas District4$1,250.00$1,263.24$1,400.006INDUS ROAD & BRIDGE, INC.TxDOT
04 NOV 2026A00209149Laredo District4$1,450.82$1,450.82$1,600.007STX CIVILTxDOT
04 NOV 2026A00140672Abilene District11$1,500.00$1,500.00$2,000.009LONE STAR PAVING COMPANYTxDOT
03 NOV 2026A00190779El Paso District19$2,000.00$2,192.00$1,800.006ALLEN CONCRETE, LLCTxDOT
03 NOV 2026A00184974Austin District1$1,300.00$1,321.02$1,434.006AUSTIN BRIDGE & ROAD SERVICES, LPTxDOT
07 OCT 2026A00206470Pharr District1$3,250.00$3,521.30n/a4AUSTIN TRAFFIC SIGNAL CONSTRUCTION CO., LLCTxDOT
07 OCT 2026A00064192San Antonio District3$1,906.15$1,906.15$1,428.008HUNTER INDUSTRIES, LTD.TxDOT
07 OCT 2026A00192619Dallas District15$2,019.49$1,640.00$1,500.006SICE, INC.TxDOT
07 OCT 2026A00223436Fort Worth District10$1,500.00$1,428.68$1,000.003SHORT-LINE, LLCTxDOT
06 OCT 2026A00222422Dallas District1$1,750.00$1,805.50$600.004SYNERGY SIGNS & SERVICES LLCTxDOT
29 SEP 2026A00223850San Angelo District1$1,800.00$1,932.00$1,500.005MPB, INC.TxDOT
03 SEP 2026A00206794San Antonio District2$1,350.00$1,437.50$1,210.986HUNTER INDUSTRIES, LTD.TxDOT
03 SEP 2026A00208481Dallas District1$2,968.87$1,850.00$1,400.007SICE, INC.TxDOT
Latest TxDOT contracts carrying Downstream anchor terminal section

Filter this item by your own quantity, district and period, or check your price against it, in the TxDOT explorer.

How these prices were read

TxDOT Bid Tabulations open-data export (data.texas.gov) from September 2024, read 21 November 2026, and TxDOT's legacy Tabulation of Bids pages for January 2020 to August 2024. The legacy pages are a large sample, not every contract: their file names were reused from year to year. Their district is the one TxDOT gives the county. Bids that did not match their published total are left out.

  • Statistics leave out bids over three times the low bid, zero or negative prices and token prices under 5% of the median.
  • Item codes and units are TxDOT's own: this item is compared with TxDOT contracts only.
  • Prices are bid prices, not paid prices, and are not adjusted for inflation. Use them as a reference range, never as a quote.

Your own bid history, read the same way

Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.

We use your email to reply to you and, now and then, to tell you about Mirage. You can opt out at any time. Privacy policy