Embank (fnl)(oc)(ty a) unit price, Texas
Low bidders on TxDOT contracts carried a median of $42.00 per CY for item 132-7001, embank (fnl)(oc)(ty a), over the 24 months to 19 NOV 2026, across 61 low bids. Half of all 346 bids fell between $35.00 and $115.08.
- Owner
- Texas DOT
- Item
- 132-7001
- Unit
- CY
- Latest letting
- 07 OCT 2026
By year of letting
| Year | Contracts | Low bids | Low-bid median | All bids | Median, all bids |
|---|---|---|---|---|---|
| 2024 | 1 | 1 | $200.00 | 4 | $650.00 |
| 2025 | 37 | 37 | $50.00 | 190 | $75.00 |
| 2026 | 25 | 24 | $40.00 | 156 | $50.00 |
Bid prices as published, not adjusted for inflation.
By district
| District | Low bids | Low-bid median | All bids | Median, all bids |
|---|---|---|---|---|
| El Paso District | 8 | $132.93 | 33 | $150.00 |
| Paris District | 3 | $33.00 | 31 | $40.00 |
| Houston District | 3 | $32.50 | 23 | $75.00 |
| San Antonio District | 4 | $30.94 | 22 | $60.00 |
| Wichita Falls District | 3 | $25.00 | 22 | $38.00 |
| Abilene District | 4 | $59.50 | 21 | $80.00 |
| San Angelo District | 3 | $56.00 | 19 | $63.95 |
| Dallas District | 4 | $85.05 | 18 | $83.35 |
| Fort Worth District | 5 | $50.00 | 18 | $77.00 |
| Laredo District | 4 | $28.00 | 17 | $35.00 |
| Odessa District | 4 | $63.50 | 13 | $100.00 |
| Pharr District | 3 | $20.00 | 11 | $50.27 |
Districts with at least three low bids, over the last 24 months.
By quantity
| Quantity (CY) | Low bids | Low-bid median |
|---|---|---|
| 1 to 30 | 15 | $128.10 |
| 46 to 173 | 15 | $88.00 |
| 186 to 728 | 15 | $40.00 |
| 760 to 64,043 | 16 | $20.50 |
The low bids split into four bands of equal count by the quantity on the contract. Larger quantities usually carry lower unit prices.
Latest contracts with this item
| Let | Contract | District | Quantity | Low bidder's price | Median | Estimate | Bids | Low bidder | Source |
|---|---|---|---|---|---|---|---|---|---|
| 07 OCT 2026 | A00196909 | Dallas District | 728 | $42.00 | $57.32 | $40.00 | 8 | XIT PAVING AND CONSTRUCTION INC. | TxDOT |
| 29 SEP 2026 | A00223850 | San Angelo District | 760 | $56.00 | $68.00 | $60.00 | 5 | MPB, INC. | TxDOT |
| 28 SEP 2026 | A00223925 | Fort Worth District | 80 | $200.00 | $175.00 | $50.00 | 2 | TEXWAY WASTEWATER SERVICES, LLC | TxDOT |
| 06 AUG 2026 | A00189724 | Laredo District | 1,356 | $10.00 | $13.04 | $21.00 | 3 | ANDERSON COLUMBIA CO., INC. | TxDOT |
| 06 AUG 2026 | A00128671 | Childress District | 573 | $31.00 | $31.00 | $100.00 | 3 | J. LEE MILLIGAN, INC. | TxDOT |
| 06 AUG 2026 | A00219498 | Wichita Falls District | 96 | $30.00 | $30.00 | $100.00 | 3 | GARRET SHIELDS INFRASTRUCTURE | TxDOT |
| 02 JUL 2026 | A00208465 | Odessa District | 9,696 | $20.00 | $25.00 | $14.00 | 2 | GILVIN-TERRILL, LTD. | TxDOT |
| 03 JUN 2026 | A00186691 | San Antonio District | 694 | $41.88 | $35.94 | n/a | 6 | STX CIVIL | TxDOT |
| 03 JUN 2026 | A00210143 | Amarillo District | 46 | $170.00 | $95.00 | $40.00 | 10 | GIBSON & ASSOCIATES, INC. | TxDOT |
| 03 JUN 2026 | A00220390 | Atlanta District | 3,004 | $20.00 | $45.00 | $258.00 | 10 | THK CONSTRUCTION LLC | TxDOT |
| 02 JUN 2026 | A00193151 | Austin District | 555 | $35.00 | $63.50 | $21.00 | 7 | GARRET SHIELDS INFRASTRUCTURE | TxDOT |
| 07 MAY 2026 | A00193351 | El Paso District | 12 | $150.00 | $150.00 | n/a | 3 | INTERNATIONAL EAGLE ENTERPRISES, INC. | TxDOT |
| 06 MAY 2026 | A00206377 | Bryan District | 186 | $40.00 | $42.75 | $30.00 | 10 | GARRET SHIELDS INFRASTRUCTURE | TxDOT |
| 16 APR 2026 | A00220064 | Paris District | 100 | $40.00 | $63.00 | $150.00 | 8 | RB CONTRACTING, LLC | TxDOT |
| 08 APR 2026 | A00211509 | Amarillo District | 121 | $50.00 | $107.50 | $40.00 | 8 | GILVIN-TERRILL, LTD. | TxDOT |
Filter this item by your own quantity, district and period, or check your price against it, in the TxDOT explorer.
How these prices were read
TxDOT Bid Tabulations open-data export (data.texas.gov) from September 2024, read 21 November 2026, and TxDOT's legacy Tabulation of Bids pages for January 2020 to August 2024. The legacy pages are a large sample, not every contract: their file names were reused from year to year. Their district is the one TxDOT gives the county. Bids that did not match their published total are left out.
- Statistics leave out bids over three times the low bid, zero or negative prices and token prices under 5% of the median.
- Item codes and units are TxDOT's own: this item is compared with TxDOT contracts only.
- Prices are bid prices, not paid prices, and are not adjusted for inflation. Use them as a reference range, never as a quote.
Your own bid history, read the same way
Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.