Embankment (final)(ord comp)(ty b) unit price, Texas
Low bidders on TxDOT contracts carried a median of $25.00 per CY for item 1326003, embankment (final)(ord comp)(ty b), from 09 JAN 2020 to 02 AUG 2024, across 285 low bids. Half of all 1,437 bids fell between $16.00 and $50.00.
- Owner
- Texas DOT
- Item
- 1326003
- Unit
- CY
- Latest letting
- 02 AUG 2024
By year of letting
| Year | Contracts | Low bids | Low-bid median | All bids | Median, all bids |
|---|---|---|---|---|---|
| 2020 | 64 | 64 | $20.00 | 382 | $25.00 |
| 2021 | 70 | 70 | $21.00 | 413 | $24.00 |
| 2022 | 56 | 56 | $25.00 | 223 | $29.00 |
| 2023 | 51 | 51 | $34.00 | 213 | $40.00 |
| 2024 | 44 | 44 | $33.50 | 206 | $41.05 |
Bid prices as published, not adjusted for inflation.
By district
| District | Low bids | Low-bid median | All bids | Median, all bids |
|---|---|---|---|---|
| Austin District | 75 | $15.00 | 385 | $16.00 |
| San Antonio District | 42 | $25.00 | 250 | $27.47 |
| Paris District | 45 | $30.00 | 209 | $30.00 |
| Wichita Falls District | 25 | $28.50 | 110 | $32.00 |
| Lufkin District | 14 | $19.00 | 78 | $30.00 |
| Amarillo District | 18 | $50.00 | 71 | $58.00 |
| Waco District | 9 | $30.00 | 45 | $31.30 |
| Odessa District | 8 | $24.00 | 41 | $20.00 |
| Childress District | 7 | $35.00 | 40 | $50.00 |
| San Angelo District | 9 | $34.00 | 39 | $34.00 |
| Brownwood District | 7 | $25.00 | 35 | $30.00 |
| Abilene District | 7 | $30.00 | 28 | $40.00 |
Districts with at least three low bids, over all lettings.
By quantity
| Quantity (CY) | Low bids | Low-bid median |
|---|---|---|
| 1 to 153 | 71 | $50.00 |
| 158 to 744 | 71 | $30.00 |
| 748.70 to 4,683 | 71 | $24.50 |
| 4,745 to 548,634 | 72 | $12.22 |
The low bids split into four bands of equal count by the quantity on the contract. Larger quantities usually carry lower unit prices.
Latest contracts with this item
| Let | Contract | District | Quantity | Low bidder's price | Median | Estimate | Bids | Low bidder | Source |
|---|---|---|---|---|---|---|---|---|---|
| 02 AUG 2024 | 08243203 | San Angelo District | 699 | $197.91 | $100.00 | $60.00 | 5 | RK HALL, LLC | TxDOT |
| 10 JUL 2024 | 07243219 | Austin District | 70 | $115.00 | $182.50 | $30.00 | 2 | SCR CIVIL CONSTRUCTION, LLC | TxDOT |
| 10 JUL 2024 | 07243224 | Childress District | 3,423 | $35.00 | $42.05 | $20.00 | 6 | SKYLINE BRIDGE LLC | TxDOT |
| 10 JUL 2024 | 07243226 | Austin District | 20 | $200.00 | $100.00 | $30.00 | 3 | TAYLOR CONTRACTING LLC | TxDOT |
| 10 JUL 2024 | 07243228 | Paris District | 1,922 | $10.00 | $44.19 | $30.00 | 6 | L & N BRIDGE, LLC | TxDOT |
| 09 JUL 2024 | 07243025 | Childress District | 750 | $35.00 | $57.50 | $60.00 | 6 | SKYLINE BRIDGE LLC | TxDOT |
| 06 JUN 2024 | 06243204 | Abilene District | 71,842 | $15.00 | $22.50 | $35.00 | 2 | WEBBER, LLC | TxDOT |
| 06 JUN 2024 | 06243205 | Wichita Falls District | 132,466 | $7.50 | $8.00 | $10.00 | 3 | A. L. HELMCAMP, INC. | TxDOT |
| 06 JUN 2024 | 06243225 | San Angelo District | 15 | $50.00 | $100.00 | $30.00 | 3 | RELMCO, INC. | TxDOT |
| 06 JUN 2024 | 06243249 | Lufkin District | 280 | $15.00 | $36.00 | $60.00 | 6 | THK CONSTRUCTION LLC | TxDOT |
| 05 JUN 2024 | 06243008 | Wichita Falls District | 31,189 | $29.00 | $31.84 | $20.00 | 4 | A. L. HELMCAMP, INC. | TxDOT |
| 05 JUN 2024 | 06243011 | Paris District | 277 | $100.00 | $100.00 | $20.00 | 3 | A. K. GILLIS & SONS, LLC | TxDOT |
| 05 JUN 2024 | 06243012 | Amarillo District | 457 | $189.00 | $81.95 | $80.00 | 4 | KIEWIT INFRASTRUCTURE SOUTH CO. | TxDOT |
| 05 JUN 2024 | 06243051 | Childress District | 1,500 | $20.00 | $45.00 | $60.00 | 6 | THK CONSTRUCTION LLC | TxDOT |
| 03 MAY 2024 | 05243211 | Fort Worth District | 103 | $125.00 | $145.00 | $75.00 | 4 | RAGLE CONSTRUCTION, INC. | TxDOT |
Filter this item by your own quantity, district and period, or check your price against it, in the TxDOT explorer.
How these prices were read
TxDOT Bid Tabulations open-data export (data.texas.gov) from September 2024, read 21 November 2026, and TxDOT's legacy Tabulation of Bids pages for January 2020 to August 2024. The legacy pages are a large sample, not every contract: their file names were reused from year to year. Their district is the one TxDOT gives the county. Bids that did not match their published total are left out.
- Statistics leave out bids over three times the low bid, zero or negative prices and token prices under 5% of the median.
- Item codes and units are TxDOT's own: this item is compared with TxDOT contracts only.
- Prices are bid prices, not paid prices, and are not adjusted for inflation. Use them as a reference range, never as a quote.
Your own bid history, read the same way