Fl bs (cmp in plc)(tyd GR1-2)(fnal pos) unit price, Texas
Low bidders on TxDOT contracts carried a median of $55.00 per CY for item 2476053003, fl bs (cmp in plc)(tyd gr1-2)(fnal pos), from 07 FEB 2020 to 04 JAN 2024, across 68 low bids. Half of all 268 bids fell between $47.90 and $83.25.
- Owner
- Texas DOT
- Item
- 2476053003
- Unit
- CY
- Latest letting
- 04 JAN 2024
By year of letting
| Year | Contracts | Low bids | Low-bid median | All bids | Median, all bids |
|---|---|---|---|---|---|
| 2020 | 10 | 10 | $45.00 | 56 | $48.00 |
| 2021 | 18 | 18 | $48.00 | 81 | $55.00 |
| 2022 | 18 | 18 | $55.00 | 63 | $65.71 |
| 2023 | 21 | 21 | $70.00 | 66 | $80.00 |
| 2024 | 1 | 1 | $70.00 | 2 | $79.00 |
Bid prices as published, not adjusted for inflation.
By district
| District | Low bids | Low-bid median | All bids | Median, all bids |
|---|---|---|---|---|
| Waco District | 27 | $54.10 | 116 | $60.00 |
| Brownwood District | 18 | $50.00 | 56 | $57.50 |
| San Antonio District | 6 | $58.21 | 31 | $58.00 |
| Dallas District | 6 | $76.75 | 22 | $88.50 |
| Abilene District | 5 | $58.09 | 20 | $65.86 |
Districts with at least three low bids, over all lettings.
By quantity
| Quantity (CY) | Low bids | Low-bid median |
|---|---|---|
| 151 to 1,420 | 17 | $92.00 |
| 1,545 to 6,426 | 17 | $50.00 |
| 7,100 to 19,646 | 17 | $50.00 |
| 19,957 to 72,638 | 17 | $45.65 |
The low bids split into four bands of equal count by the quantity on the contract. Larger quantities usually carry lower unit prices.
Latest contracts with this item
| Let | Contract | District | Quantity | Low bidder's price | Median | Estimate | Bids | Low bidder | Source |
|---|---|---|---|---|---|---|---|---|---|
| 04 JAN 2024 | 01243008 | Waco District | 1,545 | $70.00 | $79.00 | $48.00 | 2 | BIG CREEK CONSTRUCTION, LTD. | TxDOT |
| 02 NOV 2023 | 11233211 | Dallas District | 1,390 | $92.00 | $95.00 | $88.00 | 5 | TEXAS-REYES GROUP LTD. | TxDOT |
| 07 SEP 2023 | 09233208 | Waco District | 18,619 | $70.00 | $74.38 | $50.00 | 4 | BIG CREEK CONSTRUCTION, LTD. | TxDOT |
| 06 SEP 2023 | 09233027 | Brownwood District | 2,192 | $80.00 | $95.00 | $75.00 | 2 | JAY MILLS CONTRACTING, INCORPORATED | TxDOT |
| 03 AUG 2023 | 08233201 | Paris District | 72,638 | $30.17 | $53.12 | $55.00 | 4 | SEMA CONSTRUCTION, INC. | TxDOT |
| 03 AUG 2023 | 08233206 | Tyler District | 19,957 | $100.00 | $90.00 | $60.00 | 2 | INDUS ROAD & BRIDGE, INC. | TxDOT |
| 03 AUG 2023 | 08233222 | Brownwood District | 39,266 | $57.00 | $73.00 | $48.00 | 3 | JAY MILLS CONTRACTING, INCORPORATED | TxDOT |
| 02 AUG 2023 | 08233006 | Brownwood District | 1,854 | $108.00 | $114.79 | $60.00 | 2 | STERLING DELAWARE HOLDING COMPANY | TxDOT |
| 02 AUG 2023 | 08233036 | Waco District | 7,110 | $55.00 | $66.20 | $55.00 | 3 | KNIFE RIVER CORPORATION - SOUTH | TxDOT |
| 02 AUG 2023 | 08233040 | Waco District | 3,476 | $65.00 | $75.00 | $48.00 | 2 | TEXAS MATERIALS GROUP, INC. | TxDOT |
| 28 JUN 2023 | 06233622 | Waco District | 1,776 | $75.00 | $84.46 | $67.00 | 2 | KNIFE RIVER CORPORATION - SOUTH | TxDOT |
| 27 JUN 2023 | 06233403 | Houston District | 644 | $130.00 | $130.00 | $48.00 | 5 | MAIN LANE INDUSTRIES LTD. | TxDOT |
| 27 JUN 2023 | 06233405 | Dallas District | 19,646 | $52.00 | $73.50 | $80.00 | 2 | GRANITE CONSTRUCTION COMPANY | TxDOT |
| 02 JUN 2023 | 06233209 | Waco District | 34,423 | $70.00 | $63.70 | $56.00 | 3 | BIG CREEK CONSTRUCTION, LTD. | TxDOT |
| 02 JUN 2023 | 06233224 | Abilene District | 356 | $113.00 | $113.00 | $70.00 | 3 | PROJECT ALLIED RESOURCES, LLC | TxDOT |
Filter this item by your own quantity, district and period, or check your price against it, in the TxDOT explorer.
How these prices were read
TxDOT Bid Tabulations open-data export (data.texas.gov) from September 2024, read 21 November 2026, and TxDOT's legacy Tabulation of Bids pages for January 2020 to August 2024. The legacy pages are a large sample, not every contract: their file names were reused from year to year. Their district is the one TxDOT gives the county. Bids that did not match their published total are left out.
- Statistics leave out bids over three times the low bid, zero or negative prices and token prices under 5% of the median.
- Item codes and units are TxDOT's own: this item is compared with TxDOT contracts only.
- Prices are bid prices, not paid prices, and are not adjusted for inflation. Use them as a reference range, never as a quote.