Full - width mowing unit price, Texas
Low bidders on TxDOT contracts carried a median of $2,800.00 per CYC for item 7306107003, full - width mowing, from 07 FEB 2020 to 10 JUL 2024, across 71 low bids. Half of all 390 bids fell between $1,619.41 and $5,000.00.
- Owner
- Texas DOT
- Item
- 7306107003
- Unit
- CYC
- Latest letting
- 10 JUL 2024
By year of letting
| Year | Contracts | Low bids | Low-bid median | All bids | Median, all bids |
|---|---|---|---|---|---|
| 2020 | 19 | 19 | $3,153.75 | 135 | $3,316.38 |
| 2021 | 19 | 19 | $2,500.00 | 116 | $2,485.57 |
| 2022 | 14 | 14 | $2,614.50 | 57 | $3,707.00 |
| 2023 | 14 | 13 | $3,075.00 | 60 | $3,401.28 |
| 2024 | 6 | 6 | $4,750.00 | 22 | $4,250.00 |
Bid prices as published, not adjusted for inflation.
By district
| District | Low bids | Low-bid median | All bids | Median, all bids |
|---|---|---|---|---|
| Dallas District | 18 | $3,287.50 | 126 | $3,702.09 |
| San Antonio District | 16 | $2,826.88 | 104 | $2,500.00 |
| Houston District | 18 | $2,500.00 | 90 | $2,496.94 |
| Lubbock District | 14 | $3,757.75 | 50 | $5,011.90 |
Districts with at least three low bids, over all lettings.
By quantity
| Quantity (CYC) | Low bids | Low-bid median |
|---|---|---|
| 1 to 3 | 17 | $2,400.00 |
| 3 to 6 | 18 | $3,582.75 |
| 6 to 10 | 18 | $2,764.50 |
| 10 to 36 | 18 | $3,500.00 |
The low bids split into four bands of equal count by the quantity on the contract. Larger quantities usually carry lower unit prices.
Latest contracts with this item
| Let | Contract | District | Quantity | Low bidder's price | Median | Estimate | Bids | Low bidder | Source |
|---|---|---|---|---|---|---|---|---|---|
| 10 JUL 2024 | 07243207 | Dallas District | 12 | $3,000.00 | $3,429.37 | $110.00 | 6 | HARPER BROTHERS CONSTRUCTION LLC | TxDOT |
| 05 JUN 2024 | 06243007 | Dallas District | 3 | $4,000.00 | $4,000.00 | $5,300.00 | 3 | KNIFE RIVER CORPORATION - SOUTH | TxDOT |
| 04 APR 2024 | 04243005 | Lubbock District | 14 | $5,500.00 | $6,750.00 | $6,000.00 | 4 | GRATIOT CONSTRUCTION, LTD. | TxDOT |
| 06 MAR 2024 | 03243203 | Lubbock District | 2 | $2,400.00 | $8,700.00 | $5,500.00 | 2 | DUININCK, INC. | TxDOT |
| 05 MAR 2024 | 03243002 | Houston District | 6 | $7,875.00 | $5,471.31 | $3,000.00 | 4 | SER CONSTRUCTION PARTNERS, LLC | TxDOT |
| 05 JAN 2024 | 01243203 | San Antonio District | 14 | $9,000.00 | $7,000.00 | $2,100.00 | 3 | HUNTER INDUSTRIES, LTD. | TxDOT |
| 06 DEC 2023 | 12233212 | Houston District | 6 | $250.00 | $1,625.00 | $2,683.00 | 6 | RAGLE CONSTRUCTION, INC. | TxDOT |
| 06 DEC 2023 | 12233226 | Lubbock District | 2 | $4,200.00 | $7,100.00 | $4,500.00 | 4 | JAMES HAMILTON CONSTRUCTION CO. | TxDOT |
| 03 AUG 2023 | 08233202 | Houston District | 6 | $2,119.58 | $3,302.57 | $2,200.00 | 5 | ZACHRY CONSTRUCTION CORPORATION | TxDOT |
| 03 AUG 2023 | 08233257 | Dallas District | 2 | $1,000.00 | $5,000.00 | $2,000.00 | 7 | BUILT RIGHT CONSTRUCTION OF OKLAHOMA, LLC | TxDOT |
| 28 JUN 2023 | 06233601 | Dallas District | 12 | $4,100.00 | $5,000.00 | $5,000.00 | 5 | WILLIAMS BROTHERS CONSTRUCTION CO., INC. | TxDOT |
| 28 JUN 2023 | 06233604 | Dallas District | 6 | $3,075.00 | $3,937.50 | $8,000.00 | 2 | TEXAS MATERIALS GROUP, INC. | TxDOT |
| 27 JUN 2023 | 06233404 | Houston District | 12 | $2,500.00 | $1,099.40 | $4,000.00 | 5 | BALFOUR BEATTY INFRASTRUCTURE, INC. | TxDOT |
| 27 JUN 2023 | 06233411 | Houston District | 8 | $2,800.00 | $2,800.00 | $2,800.00 | 1 | TEXAS MATERIALS GROUP, INC. | TxDOT |
| 27 JUN 2023 | 06233457 | Lubbock District | 7 | $4,050.00 | $3,150.00 | $6,500.00 | 2 | WEBBER, LLC | TxDOT |
Filter this item by your own quantity, district and period, or check your price against it, in the TxDOT explorer.
How these prices were read
TxDOT Bid Tabulations open-data export (data.texas.gov) from September 2024, read 21 November 2026, and TxDOT's legacy Tabulation of Bids pages for January 2020 to August 2024. The legacy pages are a large sample, not every contract: their file names were reused from year to year. Their district is the one TxDOT gives the county. Bids that did not match their published total are left out.
- Statistics leave out bids over three times the low bid, zero or negative prices and token prices under 5% of the median.
- Item codes and units are TxDOT's own: this item is compared with TxDOT contracts only.
- Prices are bid prices, not paid prices, and are not adjusted for inflation. Use them as a reference range, never as a quote.