Furn & place topsoil (4") unit price, Texas
Low bidders on TxDOT contracts carried a median of $3.00 per SY for item 160-7002, furn & place topsoil (4"), over the 24 months to 19 NOV 2026, across 217 low bids. Half of all 1,454 bids fell between $2.00 and $6.00.
- Owner
- Texas DOT
- Item
- 160-7002
- Unit
- SY
- Latest letting
- 04 NOV 2026
By year of letting
| Year | Contracts | Low bids | Low-bid median | All bids | Median, all bids |
|---|---|---|---|---|---|
| 2024 | 4 | 4 | $3.75 | 25 | $3.50 |
| 2025 | 113 | 113 | $3.00 | 737 | $4.00 |
| 2026 | 103 | 103 | $3.20 | 709 | $3.50 |
Bid prices as published, not adjusted for inflation.
By district
| District | Low bids | Low-bid median | All bids | Median, all bids |
|---|---|---|---|---|
| Austin District | 42 | $2.04 | 290 | $3.00 |
| Bryan District | 37 | $2.00 | 269 | $3.00 |
| Tyler District | 25 | $2.60 | 173 | $3.00 |
| Waco District | 20 | $2.00 | 137 | $3.00 |
| San Antonio District | 17 | $2.07 | 102 | $4.50 |
| Corpus Christi District | 9 | $4.25 | 80 | $3.99 |
| Fort Worth District | 13 | $7.00 | 79 | $6.00 |
| Pharr District | 11 | $4.00 | 52 | $4.00 |
| Lufkin District | 6 | $4.00 | 44 | $3.79 |
| Atlanta District | 7 | $3.00 | 43 | $3.00 |
| Yoakum District | 3 | $2.00 | 34 | $5.25 |
| Houston District | 3 | $4.00 | 29 | $4.00 |
Districts with at least three low bids, over the last 24 months.
By quantity
| Quantity (SY) | Low bids | Low-bid median |
|---|---|---|
| 8 to 1,792 | 54 | $7.38 |
| 1,859 to 6,665 | 54 | $4.12 |
| 6,976 to 36,964 | 54 | $2.00 |
| 37,102 to 750,353 | 55 | $1.40 |
The low bids split into four bands of equal count by the quantity on the contract. Larger quantities usually carry lower unit prices.
Latest contracts with this item
| Let | Contract | District | Quantity | Low bidder's price | Median | Estimate | Bids | Low bidder | Source |
|---|---|---|---|---|---|---|---|---|---|
| 04 NOV 2026 | A00124162 | Bryan District | 166,415 | $1.95 | $1.02 | $1.00 | 12 | FLUOR ENTERPRISES, INC. | TxDOT |
| 04 NOV 2026 | A00206631 | Bryan District | 160,878 | $0.50 | $1.00 | $0.75 | 7 | BIG CREEK CONSTRUCTION, LTD. | TxDOT |
| 03 NOV 2026 | A00184974 | Austin District | 65,042 | $7.00 | $6.06 | $2.00 | 6 | AUSTIN BRIDGE & ROAD SERVICES, LP | TxDOT |
| 03 NOV 2026 | A00204003 | Bryan District | 1,504 | $4.00 | $4.00 | $4.00 | 15 | C & W SOUTHERN LLC | TxDOT |
| 06 OCT 2026 | A00186301 | Waco District | 53,147 | $1.00 | $1.61 | $1.50 | 6 | BIG CREEK CONSTRUCTION, LTD. | TxDOT |
| 06 OCT 2026 | A00206378 | Bryan District | 208 | $18.67 | $14.50 | $2.00 | 10 | YOKO EXCAVATING, LLC | TxDOT |
| 03 SEP 2026 | A00206794 | San Antonio District | 30,001 | $1.09 | $1.27 | $2.00 | 6 | HUNTER INDUSTRIES, LTD. | TxDOT |
| 03 SEP 2026 | A00191741 | Houston District | 1,777 | $4.00 | $4.49 | $5.00 | 7 | CASTILLO ARANDA LLC | TxDOT |
| 03 SEP 2026 | A00061184 | Austin District | 69,282 | $0.87 | $1.38 | $1.50 | 8 | HUNTER INDUSTRIES, LTD. | TxDOT |
| 03 SEP 2026 | A00189990 | Bryan District | 1,938 | $1.29 | $3.00 | $4.00 | 7 | FUQUA CONSTRUCTION CO., INC. | TxDOT |
| 02 SEP 2026 | A00206505 | Pharr District | 1,508 | $4.55 | $6.28 | $10.00 | 4 | THE LEVY COMPANY, LLC | TxDOT |
| 02 SEP 2026 | A00221866 | Pharr District | 20,670 | $2.00 | $3.00 | $0.70 | 2 | DIGG COMMERCIAL, LLC | TxDOT |
| 06 AUG 2026 | A00197439 | Austin District | 28,174 | $3.74 | $2.40 | $1.50 | 7 | STX CIVIL | TxDOT |
| 06 AUG 2026 | A00193144 | Austin District | 24,136 | $1.59 | $1.59 | $1.75 | 7 | HUNTER INDUSTRIES, LTD. | TxDOT |
| 06 AUG 2026 | A00192187 | Beaumont District | 980 | $10.00 | $9.00 | $2.00 | 6 | CASTILLO ARANDA LLC | TxDOT |
Filter this item by your own quantity, district and period, or check your price against it, in the TxDOT explorer.
How these prices were read
TxDOT Bid Tabulations open-data export (data.texas.gov) from September 2024, read 21 November 2026, and TxDOT's legacy Tabulation of Bids pages for January 2020 to August 2024. The legacy pages are a large sample, not every contract: their file names were reused from year to year. Their district is the one TxDOT gives the county. Bids that did not match their published total are left out.
- Statistics leave out bids over three times the low bid, zero or negative prices and token prices under 5% of the median.
- Item codes and units are TxDOT's own: this item is compared with TxDOT contracts only.
- Prices are bid prices, not paid prices, and are not adjusted for inflation. Use them as a reference range, never as a quote.