Grate & frame unit price, Texas
Low bidders on TxDOT contracts carried a median of $2,073.00 per EACH for item 4716003, grate & frame, from 10 JAN 2020 to 06 JUN 2024, across 42 low bids. Half of all 209 bids fell between $1,500.00 and $3,500.00.
- Owner
- Texas DOT
- Item
- 4716003
- Unit
- EACH
- Latest letting
- 06 JUN 2024
By year of letting
| Year | Contracts | Low bids | Low-bid median | All bids | Median, all bids |
|---|---|---|---|---|---|
| 2020 | 10 | 10 | $1,010.00 | 64 | $1,556.00 |
| 2021 | 6 | 6 | $1,465.97 | 28 | $1,423.53 |
| 2022 | 6 | 6 | $2,585.00 | 28 | $2,175.00 |
| 2023 | 13 | 13 | $2,972.38 | 53 | $2,972.38 |
| 2024 | 7 | 7 | $3,000.00 | 36 | $3,175.00 |
Bid prices as published, not adjusted for inflation.
By district
| District | Low bids | Low-bid median | All bids | Median, all bids |
|---|---|---|---|---|
| San Antonio District | 5 | $1,709.93 | 29 | $2,150.00 |
| Waco District | 4 | $1,410.00 | 27 | $2,510.00 |
| Bryan District | 5 | $2,972.38 | 24 | $2,000.00 |
| Corpus Christi District | 4 | $1,250.00 | 21 | $1,919.17 |
| Austin District | 3 | $1,860.00 | 19 | $2,200.00 |
| Beaumont District | 3 | $2,470.00 | 15 | $1,431.95 |
| Houston District | 3 | $1,000.00 | 14 | $1,751.49 |
| Amarillo District | 4 | $2,250.00 | 13 | $3,165.00 |
| Paris District | 3 | $4,125.00 | 12 | $4,000.00 |
Districts with at least three low bids, over all lettings.
By quantity
| Quantity (EACH) | Low bids | Low-bid median |
|---|---|---|
| 1 to 3 | 10 | $2,323.00 |
| 4 to 12 | 11 | $2,896.00 |
| 12 to 29 | 10 | $2,175.00 |
| 30 to 261 | 11 | $1,000.00 |
The low bids split into four bands of equal count by the quantity on the contract. Larger quantities usually carry lower unit prices.
Latest contracts with this item
| Let | Contract | District | Quantity | Low bidder's price | Median | Estimate | Bids | Low bidder | Source |
|---|---|---|---|---|---|---|---|---|---|
| 06 JUN 2024 | 06243231 | Houston District | 74 | $1,140.70 | $2,269.32 | $2,500.00 | 6 | SER CONSTRUCTION PARTNERS, LLC | TxDOT |
| 03 MAY 2024 | 05243235 | Paris District | 10 | $3,000.00 | $3,000.00 | $1,800.00 | 7 | ENCINO LANDSCAPE, INC. | TxDOT |
| 03 MAY 2024 | 05243237 | Pharr District | 19 | $3,307.00 | $3,029.06 | $1,800.00 | 6 | TEXAS CORDIA CONSTRUCTION, LLC | TxDOT |
| 05 APR 2024 | 04243208 | San Antonio District | 1 | $2,500.00 | $3,841.50 | $2,500.00 | 6 | ENCINO LANDSCAPE, INC. | TxDOT |
| 04 APR 2024 | 04243024 | Waco District | 42 | $1,864.34 | $3,225.00 | $1,800.00 | 6 | TI-ZACK CONCRETE, LLC | TxDOT |
| 05 MAR 2024 | 03243018 | Wichita Falls District | 3 | $3,200.00 | $4,700.00 | $1,800.00 | 2 | A. L. HELMCAMP, INC. | TxDOT |
| 05 MAR 2024 | 03243028 | Paris District | 5 | $4,125.00 | $4,125.00 | $2,500.00 | 3 | SAMMY GIST ENTERPRISES, INC. | TxDOT |
| 06 DEC 2023 | 12233201 | Yoakum District | 10 | $6,000.00 | $5,000.00 | $1,600.00 | 3 | WILLIAMS BROTHERS CONSTRUCTION CO., INC. | TxDOT |
| 06 DEC 2023 | 12233207 | Amarillo District | 8 | $3,000.00 | $3,500.00 | $2,600.00 | 5 | TI-ZACK CONCRETE, INC. | TxDOT |
| 05 DEC 2023 | 12233012 | Amarillo District | 18 | $3,593.33 | $4,661.66 | $2,600.00 | 4 | TI-ZACK CONCRETE, INC. | TxDOT |
| 06 SEP 2023 | 09233025 | Austin District | 6 | $1,500.00 | $3,500.00 | $2,500.00 | 9 | D&S CONCRETE CONTRACTORS LLC | TxDOT |
| 03 AUG 2023 | 08233228 | Bryan District | 4 | $4,000.00 | $2,174.00 | $2,500.00 | 3 | TEXAS MATERIALS GROUP, INC. | TxDOT |
| 03 AUG 2023 | 08233252 | Fort Worth District | 1 | $5,000.00 | $5,000.00 | $2,500.00 | 3 | FNH CONSTRUCTION, LLC | TxDOT |
| 02 AUG 2023 | 08233015 | Austin District | 250 | $1,860.00 | $1,150.00 | $1,250.00 | 7 | 3LW CIVIL LLC | TxDOT |
| 02 AUG 2023 | 08233039 | Bryan District | 30 | $2,972.38 | $2,600.00 | $2,000.00 | 3 | TI-ZACK CONCRETE, INC. | TxDOT |
Filter this item by your own quantity, district and period, or check your price against it, in the TxDOT explorer.
How these prices were read
TxDOT Bid Tabulations open-data export (data.texas.gov) from September 2024, read 21 November 2026, and TxDOT's legacy Tabulation of Bids pages for January 2020 to August 2024. The legacy pages are a large sample, not every contract: their file names were reused from year to year. Their district is the one TxDOT gives the county. Bids that did not match their published total are left out.
- Statistics leave out bids over three times the low bid, zero or negative prices and token prices under 5% of the median.
- Item codes and units are TxDOT's own: this item is compared with TxDOT contracts only.
- Prices are bid prices, not paid prices, and are not adjusted for inflation. Use them as a reference range, never as a quote.
Your own bid history, read the same way