In rd il (u/p) (ty 1) (150W eq) led unit price, Texas

Low bidders on TxDOT contracts carried a median of $1,700.00 per EACH for item 610-7014, in rd il (u/p) (ty 1) (150w eq) led, over the 24 months to 19 NOV 2026, across 39 low bids. Half of all 216 bids fell between $1,446.70 and $2,126.90.

Owner
Texas DOT
Item
610-7014
Unit
EACH
Latest letting
04 NOV 2026
$1,700.00Low bidder's median, per EACH
$1,800.00Median of all bids, per EACH
39Contracts in the window
$1,800.00Engineer's estimate, median per EACH

By year of letting

In rd il (u/p) (ty 1) (150W eq) led, TxDOT: unit prices by year
YearContractsLow bidsLow-bid medianAll bidsMedian, all bids
202411$1,490.307$1,420.00
20252020$1,732.50102$1,877.75
20261919$1,700.00114$1,699.00
In rd il (u/p) (ty 1) (150W eq) led, TxDOT: unit prices by year

Bid prices as published, not adjusted for inflation.

By district

In rd il (u/p) (ty 1) (150W eq) led, TxDOT: unit prices by district, last 24 months
DistrictLow bidsLow-bid medianAll bidsMedian, all bids
Dallas District8$1,975.4850$1,827.00
San Antonio District9$900.0043$1,800.00
Houston District4$1,597.4229$1,737.60
Austin District3$1,665.0019$1,798.52
In rd il (u/p) (ty 1) (150W eq) led, TxDOT: unit prices by district, last 24 months

Districts with at least three low bids, over the last 24 months.

By quantity

In rd il (u/p) (ty 1) (150W eq) led, TxDOT: low bidder's median by quantity band
Quantity (EACH)Low bidsLow-bid median
1 to 29$900.00
3 to 810$1,755.01
8 to 1410$1,815.00
16 to 31710$1,800.00
In rd il (u/p) (ty 1) (150W eq) led, TxDOT: low bidder's median by quantity band

The low bids split into four bands of equal count by the quantity on the contract. Larger quantities usually carry lower unit prices.

Latest contracts with this item

Latest TxDOT contracts carrying In rd il (u/p) (ty 1) (150W eq) led
LetContractDistrictQuantityLow bidder's priceMedianEstimateBidsLow bidderSource
04 NOV 2026A00212892Dallas District12$1,900.00$1,827.00$2,100.006INDUS ROAD & BRIDGE, INC.TxDOT
06 AUG 2026A00191470Houston District2$1,694.85$1,704.05n/a9JAMES CONSTRUCTION GROUP, LLCTxDOT
06 AUG 2026A00119935Laredo District6$1,577.14$1,320.99$2,044.504PULICE CONSTRUCTION, INC.TxDOT
06 AUG 2026A00206666Dallas District4$1,590.02$1,566.01$2,050.0010ALBATROSS CONSTRUCTION LLCTxDOT
05 AUG 2026A00128458Amarillo District8$2,120.00$1,612.50$1,000.004J. LEE MILLIGAN, INC.TxDOT
05 AUG 2026A00007222Fort Worth District14$1,700.00$1,675.00n/a11INDUS ROAD & BRIDGE, INC.TxDOT
02 JUL 2026A00124174Lubbock District18$1,600.00$1,768.97$2,800.004WILLIAMS BROTHERS CONSTRUCTION CO., INC.TxDOT
01 JUL 2026A00080576Odessa District8$2,795.00$800.00$1,900.005JONES BROS. DIRT & PAVING CONTRACTORS, INC.TxDOT
03 JUN 2026A00132662Abilene District12$1,750.00$1,750.00$1,800.001FNF CONSTRUCTION, INC.TxDOT
02 JUN 2026A00216194Houston District2$1,304.71$1,304.71$2,000.007JFO SERVICES, LLCTxDOT
07 MAY 2026A00183308Pharr District8$1,047.50$1,444.30$1,800.005IOC COMPANY LLCTxDOT
07 MAY 2026A00031457San Antonio District112$1,800.00$1,800.00$1,770.003WEBBER, LLCTxDOT
06 MAY 2026A00059994San Antonio District6$1,540.00$1,900.00$1,900.005HUNTER INDUSTRIES, LTD.TxDOT
06 MAY 2026A00196412San Antonio District1$900.00$1,404.00$1,700.003E-Z BEL CONSTRUCTION, LLCTxDOT
07 APR 2026A00084334Laredo District3$2,100.00$2,100.00$1,700.007HUNTER INDUSTRIES, LTD.TxDOT
Latest TxDOT contracts carrying In rd il (u/p) (ty 1) (150W eq) led

Filter this item by your own quantity, district and period, or check your price against it, in the TxDOT explorer.

How these prices were read

TxDOT Bid Tabulations open-data export (data.texas.gov) from September 2024, read 21 November 2026, and TxDOT's legacy Tabulation of Bids pages for January 2020 to August 2024. The legacy pages are a large sample, not every contract: their file names were reused from year to year. Their district is the one TxDOT gives the county. Bids that did not match their published total are left out.

  • Statistics leave out bids over three times the low bid, zero or negative prices and token prices under 5% of the median.
  • Item codes and units are TxDOT's own: this item is compared with TxDOT contracts only.
  • Prices are bid prices, not paid prices, and are not adjusted for inflation. Use them as a reference range, never as a quote.

Your own bid history, read the same way

Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.

We use your email to reply to you and, now and then, to tell you about Mirage. You can opt out at any time. Privacy policy