In sm rd sn sup&am TYS80(1)sa(t-2EXT) unit price, Texas
Low bidders on TxDOT contracts carried a median of $1,030.53 per EACH for item 6446031, in sm rd sn sup&am tys80(1)sa(t-2ext), from 07 FEB 2020 to 10 JUL 2024, across 56 low bids. Half of all 246 bids fell between $885.05 and $1,257.50.
- Owner
- Texas DOT
- Item
- 6446031
- Unit
- EACH
- Latest letting
- 10 JUL 2024
By year of letting
| Year | Contracts | Low bids | Low-bid median | All bids | Median, all bids |
|---|---|---|---|---|---|
| 2020 | 10 | 10 | $828.52 | 60 | $885.00 |
| 2021 | 14 | 14 | $948.46 | 69 | $960.00 |
| 2022 | 13 | 13 | $1,430.00 | 52 | $1,295.00 |
| 2023 | 14 | 14 | $1,090.00 | 42 | $1,087.50 |
| 2024 | 5 | 5 | $1,000.00 | 23 | $1,059.05 |
Bid prices as published, not adjusted for inflation.
By district
| District | Low bids | Low-bid median | All bids | Median, all bids |
|---|---|---|---|---|
| San Antonio District | 9 | $1,058.32 | 60 | $1,052.00 |
| Corpus Christi District | 10 | $955.96 | 46 | $950.00 |
| Tyler District | 5 | $775.00 | 23 | $1,000.00 |
| Houston District | 5 | $890.00 | 20 | $890.00 |
| Odessa District | 3 | $1,620.00 | 13 | $1,320.00 |
| Fort Worth District | 3 | $1,400.00 | 13 | $1,092.33 |
| Laredo District | 3 | $1,200.00 | 4 | $1,210.74 |
Districts with at least three low bids, over all lettings.
By quantity
| Quantity (EACH) | Low bids | Low-bid median |
|---|---|---|
| 1 to 1 | 14 | $1,307.92 |
| 1 to 2 | 14 | $973.50 |
| 2 to 3 | 14 | $1,164.83 |
| 3 to 9 | 14 | $895.00 |
The low bids split into four bands of equal count by the quantity on the contract. Larger quantities usually carry lower unit prices.
Latest contracts with this item
| Let | Contract | District | Quantity | Low bidder's price | Median | Estimate | Bids | Low bidder | Source |
|---|---|---|---|---|---|---|---|---|---|
| 10 JUL 2024 | 07243208 | San Antonio District | 3 | $1,460.00 | $1,267.50 | $980.55 | 8 | ACME BRIDGE COMPANY, INC. | TxDOT |
| 06 JUN 2024 | 06243203 | Houston District | 4 | $755.00 | $755.00 | $1,400.00 | 2 | JAMES CONSTRUCTION GROUP, LLC | TxDOT |
| 05 APR 2024 | 04243215 | Corpus Christi District | 9 | $850.00 | $940.00 | $1,000.00 | 5 | HIGHWAY BARRICADES AND SERVICES, LLC | TxDOT |
| 06 MAR 2024 | 03243219 | Houston District | 2 | $1,000.00 | $1,000.00 | $1,300.00 | 5 | DURWOOD GREENE CONSTRUCTION CO. | TxDOT |
| 05 MAR 2024 | 03243021 | Abilene District | 1 | $1,100.00 | $1,200.00 | $1,200.00 | 3 | GILVIN-TERRILL, LTD. | TxDOT |
| 02 NOV 2023 | 11233220 | Laredo District | 1 | $2,275.00 | $2,275.00 | $1,049.00 | 1 | E-Z BEL CONSTRUCTION, LLC | TxDOT |
| 07 SEP 2023 | 09233210 | San Angelo District | 1 | $687.50 | $687.50 | $1,100.00 | 3 | RK HALL, LLC | TxDOT |
| 03 AUG 2023 | 08233204 | Yoakum District | 2 | $1,031.07 | $1,031.07 | $1,300.00 | 1 | HUNTER INDUSTRIES, LTD. | TxDOT |
| 03 AUG 2023 | 08233212 | Bryan District | 1 | $1,100.00 | $1,059.00 | $1,100.00 | 3 | BIG CREEK CONSTRUCTION, LTD. | TxDOT |
| 03 AUG 2023 | 08233238 | Corpus Christi District | 1 | $1,125.00 | $1,007.00 | $1,150.00 | 4 | CK NEWBERRY, LLC | TxDOT |
| 02 AUG 2023 | 08233057 | Laredo District | 2 | $1,200.00 | $1,210.74 | $1,065.00 | 2 | ANDERSON COLUMBIA CO., INC. | TxDOT |
| 28 JUN 2023 | 06233612 | San Antonio District | 3 | $1,080.00 | $1,080.00 | $1,430.00 | 5 | ACME BRIDGE COMPANY, INC. | TxDOT |
| 27 JUN 2023 | 06233419 | San Antonio District | 1 | $1,150.00 | $1,150.00 | $1,700.00 | 5 | HUNTER INDUSTRIES, LTD. | TxDOT |
| 02 JUN 2023 | 06233206 | Austin District | 4 | $1,188.03 | $1,189.01 | $1,200.00 | 4 | HUNTER INDUSTRIES, LTD. | TxDOT |
| 02 JUN 2023 | 06233218 | El Paso District | 2 | $1,195.00 | $1,697.50 | $2,200.00 | 2 | DAN WILLIAMS COMPANY | TxDOT |
Filter this item by your own quantity, district and period, or check your price against it, in the TxDOT explorer.
How these prices were read
TxDOT Bid Tabulations open-data export (data.texas.gov) from September 2024, read 21 November 2026, and TxDOT's legacy Tabulation of Bids pages for January 2020 to August 2024. The legacy pages are a large sample, not every contract: their file names were reused from year to year. Their district is the one TxDOT gives the county. Bids that did not match their published total are left out.
- Statistics leave out bids over three times the low bid, zero or negative prices and token prices under 5% of the median.
- Item codes and units are TxDOT's own: this item is compared with TxDOT contracts only.
- Prices are bid prices, not paid prices, and are not adjusted for inflation. Use them as a reference range, never as a quote.
Your own bid history, read the same way