Inlet (compl)(psl)(fg)(3FTX3FT-3FTX3FT) unit price, Texas
Low bidders on TxDOT contracts carried a median of $6,400.00 per EACH for item 465-7126, inlet (compl)(psl)(fg)(3ftx3ft-3ftx3ft), over the 24 months to 19 NOV 2026, across 51 low bids. Half of all 286 bids fell between $5,814.77 and $8,596.32.
- Owner
- Texas DOT
- Item
- 465-7126
- Unit
- EACH
- Latest letting
- 04 NOV 2026
By year of letting
| Year | Contracts | Low bids | Low-bid median | All bids | Median, all bids |
|---|---|---|---|---|---|
| 2024 | 1 | 1 | $5,660.00 | 4 | $7,371.50 |
| 2025 | 26 | 26 | $6,700.00 | 134 | $7,450.00 |
| 2026 | 24 | 24 | $5,989.79 | 148 | $6,850.84 |
Bid prices as published, not adjusted for inflation.
By district
| District | Low bids | Low-bid median | All bids | Median, all bids |
|---|---|---|---|---|
| Dallas District | 10 | $7,050.00 | 64 | $7,683.26 |
| Pharr District | 7 | $5,000.00 | 37 | $6,500.00 |
| Tyler District | 5 | $6,800.00 | 32 | $7,200.00 |
| San Antonio District | 4 | $5,861.85 | 23 | $6,960.14 |
| Waco District | 3 | $5,908.90 | 21 | $6,825.00 |
| Amarillo District | 4 | $7,762.50 | 12 | $8,000.00 |
Districts with at least three low bids, over the last 24 months.
By quantity
| Quantity (EACH) | Low bids | Low-bid median |
|---|---|---|
| 1 to 1 | 12 | $6,069.24 |
| 1 to 2 | 13 | $6,400.00 |
| 3 to 8 | 13 | $5,500.00 |
| 12 to 51 | 13 | $7,023.81 |
The low bids split into four bands of equal count by the quantity on the contract. Larger quantities usually carry lower unit prices.
Latest contracts with this item
| Let | Contract | District | Quantity | Low bidder's price | Median | Estimate | Bids | Low bidder | Source |
|---|---|---|---|---|---|---|---|---|---|
| 04 NOV 2026 | A00129572 | Dallas District | 34 | $7,600.00 | $7,800.00 | $6,560.00 | 4 | MARIO SINACOLA & SONS EXCAVATING, INC. | TxDOT |
| 03 NOV 2026 | A00184974 | Austin District | 21 | $7,023.81 | $9,528.01 | $8,000.00 | 6 | AUSTIN BRIDGE & ROAD SERVICES, LP | TxDOT |
| 07 OCT 2026 | A00064192 | San Antonio District | 12 | $5,494.12 | $6,480.07 | $6,600.00 | 8 | HUNTER INDUSTRIES, LTD. | TxDOT |
| 06 AUG 2026 | A00049653 | Tyler District | 2 | $5,430.00 | $6,800.00 | $8,250.00 | 5 | LONGVIEW BRIDGE AND ROAD, LTD. | TxDOT |
| 06 AUG 2026 | A00193006 | Amarillo District | 2 | $6,400.00 | $6,400.00 | n/a | 3 | J. LEE MILLIGAN, INC. | TxDOT |
| 05 AUG 2026 | A00128458 | Amarillo District | 25 | $6,525.00 | $7,262.50 | $10,000 | 4 | J. LEE MILLIGAN, INC. | TxDOT |
| 05 AUG 2026 | A00068611 | Houston District | 5 | $4,292.10 | $6,622.61 | $6,800.00 | 7 | SER CONSTRUCTION PARTNERS, LLC | TxDOT |
| 02 JUL 2026 | A00124174 | Lubbock District | 51 | $10,690 | $11,962 | $7,000.00 | 4 | WILLIAMS BROTHERS CONSTRUCTION CO., INC. | TxDOT |
| 03 JUN 2026 | A00132662 | Abilene District | 5 | $3,000.00 | $3,000.00 | $6,500.00 | 1 | FNF CONSTRUCTION, INC. | TxDOT |
| 03 JUN 2026 | A00063871 | El Paso District | 50 | $8,500.00 | $7,050.00 | $15,000 | 4 | JORDAN FOSTER CONSTRUCTION, LLC | TxDOT |
| 02 JUN 2026 | A00065051 | San Antonio District | 1 | $6,229.58 | $7,000.00 | $5,413.00 | 7 | HUNTER INDUSTRIES, LTD. | TxDOT |
| 07 MAY 2026 | A00109269 | Pharr District | 1 | $3,730.00 | $5,188.39 | $7,000.00 | 6 | TEXAS CORDIA CONSTRUCTION, LLC | TxDOT |
| 07 MAY 2026 | A00031457 | San Antonio District | 5 | $8,043.85 | $8,043.85 | $6,000.00 | 3 | WEBBER, LLC | TxDOT |
| 06 MAY 2026 | A00121011 | Pharr District | 8 | $4,400.00 | $5,457.22 | $7,000.00 | 6 | IOC COMPANY LLC | TxDOT |
| 06 MAY 2026 | A00014162 | Dallas District | 22 | $5,380.00 | $6,000.00 | $5,500.00 | 9 | WEBBER, LLC | TxDOT |
Filter this item by your own quantity, district and period, or check your price against it, in the TxDOT explorer.
How these prices were read
TxDOT Bid Tabulations open-data export (data.texas.gov) from September 2024, read 21 November 2026, and TxDOT's legacy Tabulation of Bids pages for January 2020 to August 2024. The legacy pages are a large sample, not every contract: their file names were reused from year to year. Their district is the one TxDOT gives the county. Bids that did not match their published total are left out.
- Statistics leave out bids over three times the low bid, zero or negative prices and token prices under 5% of the median.
- Item codes and units are TxDOT's own: this item is compared with TxDOT contracts only.
- Prices are bid prices, not paid prices, and are not adjusted for inflation. Use them as a reference range, never as a quote.
Your own bid history, read the same way
Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.