Instl del assm (d-sw)sz 1(brf)GF2 unit price, Texas
Low bidders on TxDOT contracts carried a median of $32.62 per EACH for item 658-7018, instl del assm (d-sw)sz 1(brf)gf2, over the 24 months to 19 NOV 2026, across 178 low bids. Half of all 936 bids fell between $27.00 and $50.00.
- Owner
- Texas DOT
- Item
- 658-7018
- Unit
- EACH
- Latest letting
- 03 NOV 2026
By year of letting
| Year | Contracts | Low bids | Low-bid median | All bids | Median, all bids |
|---|---|---|---|---|---|
| 2024 | 5 | 4 | $36.00 | 28 | $30.00 |
| 2025 | 100 | 90 | $32.00 | 463 | $35.00 |
| 2026 | 92 | 85 | $33.20 | 447 | $35.00 |
Bid prices as published, not adjusted for inflation.
By district
| District | Low bids | Low-bid median | All bids | Median, all bids |
|---|---|---|---|---|
| Houston District | 23 | $33.20 | 123 | $32.00 |
| Dallas District | 23 | $30.00 | 121 | $35.00 |
| Austin District | 17 | $40.00 | 105 | $37.45 |
| Tyler District | 9 | $28.00 | 58 | $28.00 |
| San Antonio District | 10 | $32.50 | 52 | $32.71 |
| Waco District | 7 | $45.00 | 46 | $44.16 |
| Paris District | 7 | $40.00 | 46 | $33.56 |
| Pharr District | 10 | $30.50 | 46 | $32.24 |
| Atlanta District | 10 | $22.50 | 37 | $38.50 |
| Laredo District | 8 | $44.41 | 31 | $48.00 |
| Abilene District | 7 | $50.00 | 31 | $46.05 |
| Amarillo District | 5 | $35.89 | 28 | $50.00 |
Districts with at least three low bids, over the last 24 months.
By quantity
| Quantity (EACH) | Low bids | Low-bid median |
|---|---|---|
| 2 to 10 | 44 | $35.00 |
| 10 to 27 | 45 | $32.86 |
| 28 to 55 | 44 | $33.10 |
| 55 to 500 | 45 | $30.00 |
The low bids split into four bands of equal count by the quantity on the contract. Larger quantities usually carry lower unit prices.
Latest contracts with this item
| Let | Contract | District | Quantity | Low bidder's price | Median | Estimate | Bids | Low bidder | Source |
|---|---|---|---|---|---|---|---|---|---|
| 03 NOV 2026 | A00184974 | Austin District | 54 | $22.00 | $23.14 | $65.00 | 6 | AUSTIN BRIDGE & ROAD SERVICES, LP | TxDOT |
| 07 OCT 2026 | A00132124 | Lufkin District | 65 | $50.00 | $38.50 | $44.00 | 7 | LONGVIEW BRIDGE AND ROAD, LTD. | TxDOT |
| 07 OCT 2026 | A00192619 | Dallas District | 90 | $29.18 | $30.87 | $35.00 | 6 | SICE, INC. | TxDOT |
| 07 OCT 2026 | A00222519 | Waco District | 55 | $10.00 | $20.00 | $33.69 | 4 | T&L CLEANING SERVICES LLC | TxDOT |
| 06 OCT 2026 | A00222925 | Waco District | 25 | $25.00 | $25.00 | $33.69 | 3 | ROSS SA ENTERPRISE LLC | TxDOT |
| 06 OCT 2026 | A00222422 | Dallas District | 20 | $50.00 | $47.50 | $15.00 | 4 | SYNERGY SIGNS & SERVICES LLC | TxDOT |
| 17 SEP 2026 | A00222375 | Paris District | 30 | $50.00 | $50.00 | $30.00 | 3 | MARCOM'S MOWING SERVICE, LLC | TxDOT |
| 03 SEP 2026 | A00184830 | Amarillo District | 12 | $45.00 | $54.00 | $45.00 | 7 | GILVIN-TERRILL, LTD. | TxDOT |
| 03 SEP 2026 | A00208481 | Dallas District | 3 | $46.18 | $46.18 | $38.00 | 7 | SICE, INC. | TxDOT |
| 03 SEP 2026 | A00220795 | Dallas District | 3 | $68.45 | $38.06 | $77.00 | 5 | HIGHWAY INTELLIGENT TRAFFIC SOLUTIONS, LLC | TxDOT |
| 12 AUG 2026 | A00222622 | Dallas District | 100 | n/a | $110.00 | $65.00 | 2 | MARCOM'S MOWING SERVICE, LLC | TxDOT |
| 06 AUG 2026 | A00193144 | Austin District | 16 | $17.00 | $37.45 | $40.00 | 7 | HUNTER INDUSTRIES, LTD. | TxDOT |
| 06 AUG 2026 | A00189724 | Laredo District | 30 | $80.00 | $80.00 | $23.59 | 3 | ANDERSON COLUMBIA CO., INC. | TxDOT |
| 06 AUG 2026 | A00193006 | Amarillo District | 162 | $48.00 | $45.00 | $45.00 | 3 | J. LEE MILLIGAN, INC. | TxDOT |
| 06 AUG 2026 | A00119935 | Laredo District | 18 | $48.82 | $46.23 | $35.00 | 4 | PULICE CONSTRUCTION, INC. | TxDOT |
Filter this item by your own quantity, district and period, or check your price against it, in the TxDOT explorer.
How these prices were read
TxDOT Bid Tabulations open-data export (data.texas.gov) from September 2024, read 21 November 2026, and TxDOT's legacy Tabulation of Bids pages for January 2020 to August 2024. The legacy pages are a large sample, not every contract: their file names were reused from year to year. Their district is the one TxDOT gives the county. Bids that did not match their published total are left out.
- Statistics leave out bids over three times the low bid, zero or negative prices and token prices under 5% of the median.
- Item codes and units are TxDOT's own: this item is compared with TxDOT contracts only.
- Prices are bid prices, not paid prices, and are not adjusted for inflation. Use them as a reference range, never as a quote.