Instl om assm (om-2Z)(flx)gnd unit price, Texas
Low bidders on TxDOT contracts carried a median of $70.00 per EACH for item 6586048, instl om assm (om-2z)(flx)gnd, from 09 JAN 2020 to 10 JUL 2024, across 93 low bids. Half of all 569 bids fell between $53.00 and $100.00.
- Owner
- Texas DOT
- Item
- 6586048
- Unit
- EACH
- Latest letting
- 10 JUL 2024
By year of letting
| Year | Contracts | Low bids | Low-bid median | All bids | Median, all bids |
|---|---|---|---|---|---|
| 2020 | 71 | 71 | $75.00 | 419 | $75.00 |
| 2021 | 20 | 20 | $54.50 | 140 | $60.00 |
| 2023 | 1 | 1 | $92.00 | 6 | $78.50 |
| 2024 | 1 | 1 | $40.00 | 4 | $43.38 |
Bid prices as published, not adjusted for inflation.
By district
| District | Low bids | Low-bid median | All bids | Median, all bids |
|---|---|---|---|---|
| Dallas District | 11 | $45.50 | 88 | $53.23 |
| Fort Worth District | 10 | $54.50 | 80 | $65.00 |
| Corpus Christi District | 11 | $75.00 | 64 | $75.50 |
| Odessa District | 10 | $99.50 | 58 | $101.15 |
| Amarillo District | 8 | $141.00 | 35 | $127.20 |
| Paris District | 5 | $50.00 | 32 | $65.00 |
| San Angelo District | 4 | $82.50 | 27 | $90.00 |
| Atlanta District | 3 | $70.00 | 21 | $75.00 |
| San Antonio District | 3 | $52.50 | 21 | $53.00 |
| Tyler District | 4 | $39.25 | 21 | $44.00 |
| Beaumont District | 4 | $53.35 | 20 | $55.50 |
| Lubbock District | 3 | $117.00 | 15 | $100.00 |
Districts with at least three low bids, over all lettings.
By quantity
| Quantity (EACH) | Low bids | Low-bid median |
|---|---|---|
| 1 to 6 | 23 | $60.50 |
| 8 to 16 | 23 | $60.00 |
| 16 to 39 | 23 | $70.00 |
| 43 to 218 | 24 | $88.22 |
The low bids split into four bands of equal count by the quantity on the contract. Larger quantities usually carry lower unit prices.
Latest contracts with this item
| Let | Contract | District | Quantity | Low bidder's price | Median | Estimate | Bids | Low bidder | Source |
|---|---|---|---|---|---|---|---|---|---|
| 10 JUL 2024 | 07243203 | Pharr District | 36 | $40.00 | $43.38 | $92.00 | 4 | FOREMOST PAVING, INC. | TxDOT |
| 02 AUG 2023 | 08233010 | Fort Worth District | 14 | $92.00 | $78.50 | $60.00 | 6 | JAGOE-PUBLIC COMPANY | TxDOT |
| 05 MAR 2021 | 03213201 | San Antonio District | 39 | $52.50 | $52.50 | $75.00 | 5 | WILLIAMS BROTHERS CONSTRUCTION CO., INC. | TxDOT |
| 05 MAR 2021 | 03213204 | Dallas District | 104 | $62.00 | $45.00 | $50.00 | 9 | KNIFE RIVER CORPORATION - SOUTH | TxDOT |
| 05 MAR 2021 | 03213211 | Bryan District | 88 | $192.00 | $80.00 | $74.00 | 7 | BLACKSMITH VENTURES LLC | TxDOT |
| 05 MAR 2021 | 03213218 | Fort Worth District | 2 | $54.00 | $53.25 | $57.00 | 12 | SEMA CONSTRUCTION, INC. | TxDOT |
| 05 MAR 2021 | 03213220 | Dallas District | 24 | $45.50 | $42.96 | $93.00 | 6 | EUROVIA ATLANTIC COAST LLC | TxDOT |
| 04 MAR 2021 | 03213006 | Atlanta District | 8 | $85.00 | $92.50 | $60.00 | 6 | EAST TEXAS BRIDGE, INC. | TxDOT |
| 04 MAR 2021 | 03213007 | Beaumont District | 4 | $50.00 | $55.00 | $65.00 | 3 | ANGEL BROTHERS HOLDINGS CORP. | TxDOT |
| 04 MAR 2021 | 03213013 | Beaumont District | 10 | $22.00 | $49.75 | $65.00 | 6 | TREVWAY, INC. | TxDOT |
| 04 MAR 2021 | 03214019 | Tyler District | 25 | $10.00 | $15.00 | $10.00 | 3 | FIREMAN EXCAVATING, INC. | TxDOT |
| 05 FEB 2021 | 02213202 | Corpus Christi District | 4 | $105.00 | $105.45 | $74.00 | 7 | HUNTER INDUSTRIES, LTD. | TxDOT |
| 05 FEB 2021 | 02213203 | Pharr District | 16 | $45.00 | $55.00 | $286.67 | 5 | IOC COMPANY LLC | TxDOT |
| 05 FEB 2021 | 02213214 | Amarillo District | 135 | $160.00 | $137.50 | $135.00 | 3 | J. LEE MILLIGAN, INC. | TxDOT |
| 05 FEB 2021 | 02213223 | Dallas District | 34 | $40.00 | $50.72 | $50.00 | 10 | A. K. GILLIS & SONS, LLC | TxDOT |
Filter this item by your own quantity, district and period, or check your price against it, in the TxDOT explorer.
How these prices were read
TxDOT Bid Tabulations open-data export (data.texas.gov) from September 2024, read 21 November 2026, and TxDOT's legacy Tabulation of Bids pages for January 2020 to August 2024. The legacy pages are a large sample, not every contract: their file names were reused from year to year. Their district is the one TxDOT gives the county. Bids that did not match their published total are left out.
- Statistics leave out bids over three times the low bid, zero or negative prices and token prices under 5% of the median.
- Item codes and units are TxDOT's own: this item is compared with TxDOT contracts only.
- Prices are bid prices, not paid prices, and are not adjusted for inflation. Use them as a reference range, never as a quote.