Instl om assm (om-2Z)(wflx)gnd unit price, Texas
Low bidders on TxDOT contracts carried a median of $89.25 per EACH for item 658-7058, instl om assm (om-2z)(wflx)gnd, over the 24 months to 19 NOV 2026, across 101 low bids. Half of all 561 bids fell between $66.83 and $117.00.
- Owner
- Texas DOT
- Item
- 658-7058
- Unit
- EACH
- Latest letting
- 04 NOV 2026
By year of letting
| Year | Contracts | Low bids | Low-bid median | All bids | Median, all bids |
|---|---|---|---|---|---|
| 2024 | 5 | 5 | $85.00 | 25 | $94.00 |
| 2025 | 49 | 49 | $82.50 | 260 | $95.00 |
| 2026 | 53 | 52 | $90.00 | 301 | $92.00 |
Bid prices as published, not adjusted for inflation.
By district
| District | Low bids | Low-bid median | All bids | Median, all bids |
|---|---|---|---|---|
| Dallas District | 11 | $65.00 | 68 | $66.50 |
| San Antonio District | 11 | $75.00 | 64 | $79.50 |
| Bryan District | 9 | $90.00 | 58 | $90.00 |
| Atlanta District | 7 | $126.00 | 46 | $126.00 |
| Tyler District | 6 | $81.03 | 44 | $75.53 |
| Lufkin District | 8 | $42.50 | 37 | $75.00 |
| Austin District | 5 | $98.50 | 35 | $115.52 |
| Beaumont District | 8 | $101.50 | 31 | $100.00 |
| Fort Worth District | 5 | $64.00 | 29 | $70.00 |
| Laredo District | 6 | $125.00 | 27 | $121.49 |
| Amarillo District | 5 | $132.00 | 25 | $132.00 |
| Waco District | 3 | $95.00 | 18 | $90.00 |
Districts with at least three low bids, over the last 24 months.
By quantity
| Quantity (EACH) | Low bids | Low-bid median |
|---|---|---|
| 1 to 4 | 25 | $90.00 |
| 4 to 10 | 25 | $69.00 |
| 11 to 33 | 25 | $90.00 |
| 37 to 312 | 26 | $100.00 |
The low bids split into four bands of equal count by the quantity on the contract. Larger quantities usually carry lower unit prices.
Latest contracts with this item
| Let | Contract | District | Quantity | Low bidder's price | Median | Estimate | Bids | Low bidder | Source |
|---|---|---|---|---|---|---|---|---|---|
| 04 NOV 2026 | A00206631 | Bryan District | 32 | $85.00 | $85.00 | $100.00 | 7 | BIG CREEK CONSTRUCTION, LTD. | TxDOT |
| 07 OCT 2026 | A00132124 | Lufkin District | 2 | $130.00 | $110.00 | $115.00 | 7 | LONGVIEW BRIDGE AND ROAD, LTD. | TxDOT |
| 07 OCT 2026 | A00064192 | San Antonio District | 231 | $65.00 | $65.00 | $76.00 | 8 | HUNTER INDUSTRIES, LTD. | TxDOT |
| 03 SEP 2026 | A00184830 | Amarillo District | 8 | $80.00 | $102.00 | $100.00 | 7 | GILVIN-TERRILL, LTD. | TxDOT |
| 03 SEP 2026 | A00196194 | Atlanta District | 2 | $110.00 | $99.00 | $130.00 | 4 | LONGVIEW BRIDGE AND ROAD, LTD. | TxDOT |
| 03 SEP 2026 | A00206794 | San Antonio District | 8 | $75.00 | $75.00 | $84.20 | 6 | HUNTER INDUSTRIES, LTD. | TxDOT |
| 06 AUG 2026 | A00197439 | Austin District | 24 | $74.14 | $115.00 | $105.00 | 7 | STX CIVIL | TxDOT |
| 06 AUG 2026 | A00189724 | Laredo District | 28 | $125.00 | $125.00 | $121.00 | 3 | ANDERSON COLUMBIA CO., INC. | TxDOT |
| 06 AUG 2026 | A00196275 | Atlanta District | 2 | $137.00 | $150.00 | $100.00 | 5 | MADDEN CONTRACTING COMPANY, LLC. | TxDOT |
| 06 AUG 2026 | A00187792 | Dallas District | 5 | $60.00 | $60.00 | n/a | 7 | D. L. LENNON INCORPORATED - CONTRACTOR | TxDOT |
| 06 AUG 2026 | A00119935 | Laredo District | 9 | $100.90 | $99.48 | $120.00 | 4 | PULICE CONSTRUCTION, INC. | TxDOT |
| 06 AUG 2026 | A00203348 | Atlanta District | 37 | $140.00 | $103.00 | $114.00 | 4 | EAST TEXAS BRIDGE, INC. | TxDOT |
| 05 AUG 2026 | A00128458 | Amarillo District | 41 | $165.00 | $117.85 | $150.00 | 4 | J. LEE MILLIGAN, INC. | TxDOT |
| 05 AUG 2026 | A00219820 | Beaumont District | 4 | $82.50 | $82.50 | n/a | 1 | TEXAS MATERIALS GROUP, INC. | TxDOT |
| 05 AUG 2026 | A00187841 | Odessa District | 103 | $105.00 | $105.00 | $101.08 | 1 | FNF CONSTRUCTION, INC. | TxDOT |
Filter this item by your own quantity, district and period, or check your price against it, in the TxDOT explorer.
How these prices were read
TxDOT Bid Tabulations open-data export (data.texas.gov) from September 2024, read 21 November 2026, and TxDOT's legacy Tabulation of Bids pages for January 2020 to August 2024. The legacy pages are a large sample, not every contract: their file names were reused from year to year. Their district is the one TxDOT gives the county. Bids that did not match their published total are left out.
- Statistics leave out bids over three times the low bid, zero or negative prices and token prices under 5% of the median.
- Item codes and units are TxDOT's own: this item is compared with TxDOT contracts only.
- Prices are bid prices, not paid prices, and are not adjusted for inflation. Use them as a reference range, never as a quote.