Mailbox install-d (wc-post) ty 3 unit price, Texas
Low bidders on TxDOT contracts carried a median of $250.00 per EACH for item 5606008, mailbox install-d (wc-post) ty 3, from 08 APR 2020 to 10 JUL 2024, across 66 low bids. Half of all 261 bids fell between $190.00 and $300.00.
- Owner
- Texas DOT
- Item
- 5606008
- Unit
- EACH
- Latest letting
- 10 JUL 2024
By year of letting
| Year | Contracts | Low bids | Low-bid median | All bids | Median, all bids |
|---|---|---|---|---|---|
| 2020 | 11 | 11 | $200.00 | 66 | $216.15 |
| 2021 | 12 | 12 | $213.00 | 55 | $200.00 |
| 2022 | 10 | 10 | $280.75 | 32 | $270.00 |
| 2023 | 21 | 21 | $295.00 | 57 | $300.00 |
| 2024 | 12 | 12 | $205.00 | 51 | $215.00 |
Bid prices as published, not adjusted for inflation.
By district
| District | Low bids | Low-bid median | All bids | Median, all bids |
|---|---|---|---|---|
| Yoakum District | 19 | $184.00 | 89 | $210.00 |
| Lufkin District | 17 | $269.50 | 62 | $244.90 |
| Waco District | 8 | $262.50 | 27 | $250.00 |
| Paris District | 6 | $218.00 | 20 | $211.00 |
| Bryan District | 4 | $219.25 | 16 | $278.13 |
| Pharr District | 3 | $300.00 | 15 | $392.00 |
| Wichita Falls District | 4 | $265.00 | 15 | $210.00 |
Districts with at least three low bids, over all lettings.
By quantity
| Quantity (EACH) | Low bids | Low-bid median |
|---|---|---|
| 1 to 2 | 16 | $293.50 |
| 2 to 4 | 17 | $250.00 |
| 4 to 6 | 16 | $240.00 |
| 7 to 19 | 17 | $216.00 |
The low bids split into four bands of equal count by the quantity on the contract. Larger quantities usually carry lower unit prices.
Latest contracts with this item
| Let | Contract | District | Quantity | Low bidder's price | Median | Estimate | Bids | Low bidder | Source |
|---|---|---|---|---|---|---|---|---|---|
| 10 JUL 2024 | 07243204 | Yoakum District | 4 | $165.00 | $182.50 | $320.00 | 6 | HUNTER INDUSTRIES, LTD. | TxDOT |
| 10 JUL 2024 | 07243213 | Lufkin District | 2 | $323.40 | $661.70 | $300.00 | 2 | PINTO CONSTRUCTION CO., INC. | TxDOT |
| 05 JUN 2024 | 06243009 | Bryan District | 6 | $145.00 | $185.65 | $230.00 | 6 | KNIFE RIVER CORPORATION - SOUTH | TxDOT |
| 05 JUN 2024 | 06243011 | Paris District | 1 | $210.00 | $510.00 | $225.00 | 3 | A. K. GILLIS & SONS, LLC | TxDOT |
| 03 MAY 2024 | 05243201 | Yoakum District | 1 | $347.93 | $282.00 | $300.00 | 3 | PULICE CONSTRUCTION, INC. | TxDOT |
| 03 MAY 2024 | 05243209 | Lufkin District | 4 | $306.90 | $306.90 | $150.00 | 3 | PINTO CONSTRUCTION CO., INC. | TxDOT |
| 05 APR 2024 | 04243209 | Yoakum District | 6 | $200.00 | $225.00 | $250.00 | 11 | BIG CREEK CONSTRUCTION, LTD. | TxDOT |
| 05 MAR 2024 | 03243008 | Yoakum District | 3 | $145.00 | $145.00 | $250.00 | 3 | HUNTER INDUSTRIES, LTD. | TxDOT |
| 01 FEB 2024 | 02243008 | Yoakum District | 10 | $145.00 | $164.00 | $350.00 | 6 | CLARK CONSTRUCTION OF TEXAS, INC. | TxDOT |
| 05 JAN 2024 | 01243205 | Lufkin District | 7 | $250.00 | $250.00 | $300.00 | 3 | A. L. HELMCAMP, INC. | TxDOT |
| 04 JAN 2024 | 01243002 | Yoakum District | 7 | $150.00 | $175.00 | $320.00 | 4 | HUNTER INDUSTRIES, LTD. | TxDOT |
| 04 JAN 2024 | 01243019 | Abilene District | 1 | $500.00 | $500.00 | $300.00 | 1 | HODGES AND SON CONSTRUCTION COMPANY, INC. | TxDOT |
| 05 DEC 2023 | 12233003 | Yoakum District | 8 | $130.00 | $263.00 | $300.00 | 4 | HUNTER INDUSTRIES, LTD. | TxDOT |
| 01 NOV 2023 | 11233012 | Paris District | 9 | $600.00 | $600.00 | $225.00 | 1 | HIGHWAY 19 CONSTRUCTION LLC | TxDOT |
| 07 SEP 2023 | 09233208 | Waco District | 1 | $300.00 | $290.25 | $270.00 | 4 | BIG CREEK CONSTRUCTION, LTD. | TxDOT |
Filter this item by your own quantity, district and period, or check your price against it, in the TxDOT explorer.
How these prices were read
TxDOT Bid Tabulations open-data export (data.texas.gov) from September 2024, read 21 November 2026, and TxDOT's legacy Tabulation of Bids pages for January 2020 to August 2024. The legacy pages are a large sample, not every contract: their file names were reused from year to year. Their district is the one TxDOT gives the county. Bids that did not match their published total are left out.
- Statistics leave out bids over three times the low bid, zero or negative prices and token prices under 5% of the median.
- Item codes and units are TxDOT's own: this item is compared with TxDOT contracts only.
- Prices are bid prices, not paid prices, and are not adjusted for inflation. Use them as a reference range, never as a quote.
Your own bid history, read the same way
Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.