Mtl w - beam gd fen (low fill culvert) unit price, Texas

Low bidders on TxDOT contracts carried a median of $75.00 per LF for item 5406020001, mtl w - beam gd fen (low fill culvert), from 06 FEB 2020 to 02 AUG 2024, across 169 low bids. Half of all 757 bids fell between $61.42 and $100.00.

Owner
Texas DOT
Item
5406020001
Unit
LF
Latest letting
02 AUG 2024
$75.00Low bidder's median, per LF
$78.05Median of all bids, per LF
169Contracts in the window
$70.00Engineer's estimate, median per LF

By year of letting

Mtl w - beam gd fen (low fill culvert), TxDOT: unit prices by year
YearContractsLow bidsLow-bid medianAll bidsMedian, all bids
20204141$60.00215$64.66
20213838$64.43191$65.00
20223333$90.00138$94.58
20233131$89.00106$92.00
20242626$97.80107$100.00
Mtl w - beam gd fen (low fill culvert), TxDOT: unit prices by year

Bid prices as published, not adjusted for inflation.

By district

Mtl w - beam gd fen (low fill culvert), TxDOT: unit prices by district, all lettings
DistrictLow bidsLow-bid medianAll bidsMedian, all bids
Yoakum District20$84.8799$90.72
San Angelo District16$71.0075$71.64
Tyler District11$73.5067$77.00
Brownwood District12$62.5055$70.00
Austin District10$73.9547$82.02
Wichita Falls District11$73.0047$73.00
Abilene District10$86.0038$85.00
Corpus Christi District6$85.9336$85.48
Paris District8$76.5035$65.00
Houston District9$75.0033$77.25
Bryan District6$94.5030$68.75
Dallas District6$71.3829$53.00
Mtl w - beam gd fen (low fill culvert), TxDOT: unit prices by district, all lettings

Districts with at least three low bids, over all lettings.

By quantity

Mtl w - beam gd fen (low fill culvert), TxDOT: low bidder's median by quantity band
Quantity (LF)Low bidsLow-bid median
1 to 6742$95.00
70 to 11342$79.35
125 to 222.5042$67.54
225 to 1,75543$66.00
Mtl w - beam gd fen (low fill culvert), TxDOT: low bidder's median by quantity band

The low bids split into four bands of equal count by the quantity on the contract. Larger quantities usually carry lower unit prices.

Latest contracts with this item

Latest TxDOT contracts carrying Mtl w - beam gd fen (low fill culvert)
LetContractDistrictQuantityLow bidder's priceMedianEstimateBidsLow bidderSource
02 AUG 202408243203San Angelo District619$99.00$108.88$85.005RK HALL, LLCTxDOT
10 JUL 202407243209Wichita Falls District125$85.50$89.50$60.005OVERLAND CORPORATIONTxDOT
06 JUN 202406243203Houston District50$95.00$95.00$18.402JAMES CONSTRUCTION GROUP, LLCTxDOT
06 JUN 202406243210Abilene District33$93.50$88.00$85.003RK HALL, LLCTxDOT
05 JUN 202406243006Brownwood District125$84.96$127.50$90.004ALLEN KELLER COMPANYTxDOT
05 JUN 202406243048Atlanta District100$105.00$117.50$115.008THK CONSTRUCTION LLCTxDOT
05 APR 202404243209Yoakum District160.32$100.00$100.80$90.0011BIG CREEK CONSTRUCTION, LTD.TxDOT
05 APR 202404243222Brownwood District340$85.00$110.00$100.003HJC FARMS, INC.TxDOT
04 APR 202404243018Laredo District450$100.00$95.69$90.004LUCANIA CONTRACTORS LLCTxDOT
06 MAR 202403243201Odessa District175$105.00$99.00$70.003SUNDT CONSTRUCTION, INC.TxDOT
06 MAR 202403243202Laredo District75$110.00$108.40$85.002ANDERSON COLUMBIA CO., INC.TxDOT
06 MAR 202403243208Fort Worth District40$110.00$85.00$80.882NORTHEASTERN PAVERS, LLCTxDOT
06 MAR 202403243228Yoakum District25$140.00$119.35$75.006R CONSTRUCTION CIVIL, LLCTxDOT
05 MAR 202403243008Yoakum District60$104.75$120.00$100.003HUNTER INDUSTRIES, LTD.TxDOT
05 MAR 202403243019Fort Worth District75$81.20$80.61$100.004PEACHTREE CONSTRUCTION, LTD.TxDOT
Latest TxDOT contracts carrying Mtl w - beam gd fen (low fill culvert)

Filter this item by your own quantity, district and period, or check your price against it, in the TxDOT explorer.

How these prices were read

TxDOT Bid Tabulations open-data export (data.texas.gov) from September 2024, read 21 November 2026, and TxDOT's legacy Tabulation of Bids pages for January 2020 to August 2024. The legacy pages are a large sample, not every contract: their file names were reused from year to year. Their district is the one TxDOT gives the county. Bids that did not match their published total are left out.

  • Statistics leave out bids over three times the low bid, zero or negative prices and token prices under 5% of the median.
  • Item codes and units are TxDOT's own: this item is compared with TxDOT contracts only.
  • Prices are bid prices, not paid prices, and are not adjusted for inflation. Use them as a reference range, never as a quote.

Your own bid history, read the same way

Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.