Mtl w - beam gd fen (low fill culvert) unit price, Texas
Low bidders on TxDOT contracts carried a median of $75.00 per LF for item 5406020001, mtl w - beam gd fen (low fill culvert), from 06 FEB 2020 to 02 AUG 2024, across 169 low bids. Half of all 757 bids fell between $61.42 and $100.00.
- Owner
- Texas DOT
- Item
- 5406020001
- Unit
- LF
- Latest letting
- 02 AUG 2024
By year of letting
| Year | Contracts | Low bids | Low-bid median | All bids | Median, all bids |
|---|---|---|---|---|---|
| 2020 | 41 | 41 | $60.00 | 215 | $64.66 |
| 2021 | 38 | 38 | $64.43 | 191 | $65.00 |
| 2022 | 33 | 33 | $90.00 | 138 | $94.58 |
| 2023 | 31 | 31 | $89.00 | 106 | $92.00 |
| 2024 | 26 | 26 | $97.80 | 107 | $100.00 |
Bid prices as published, not adjusted for inflation.
By district
| District | Low bids | Low-bid median | All bids | Median, all bids |
|---|---|---|---|---|
| Yoakum District | 20 | $84.87 | 99 | $90.72 |
| San Angelo District | 16 | $71.00 | 75 | $71.64 |
| Tyler District | 11 | $73.50 | 67 | $77.00 |
| Brownwood District | 12 | $62.50 | 55 | $70.00 |
| Austin District | 10 | $73.95 | 47 | $82.02 |
| Wichita Falls District | 11 | $73.00 | 47 | $73.00 |
| Abilene District | 10 | $86.00 | 38 | $85.00 |
| Corpus Christi District | 6 | $85.93 | 36 | $85.48 |
| Paris District | 8 | $76.50 | 35 | $65.00 |
| Houston District | 9 | $75.00 | 33 | $77.25 |
| Bryan District | 6 | $94.50 | 30 | $68.75 |
| Dallas District | 6 | $71.38 | 29 | $53.00 |
Districts with at least three low bids, over all lettings.
By quantity
| Quantity (LF) | Low bids | Low-bid median |
|---|---|---|
| 1 to 67 | 42 | $95.00 |
| 70 to 113 | 42 | $79.35 |
| 125 to 222.50 | 42 | $67.54 |
| 225 to 1,755 | 43 | $66.00 |
The low bids split into four bands of equal count by the quantity on the contract. Larger quantities usually carry lower unit prices.
Latest contracts with this item
| Let | Contract | District | Quantity | Low bidder's price | Median | Estimate | Bids | Low bidder | Source |
|---|---|---|---|---|---|---|---|---|---|
| 02 AUG 2024 | 08243203 | San Angelo District | 619 | $99.00 | $108.88 | $85.00 | 5 | RK HALL, LLC | TxDOT |
| 10 JUL 2024 | 07243209 | Wichita Falls District | 125 | $85.50 | $89.50 | $60.00 | 5 | OVERLAND CORPORATION | TxDOT |
| 06 JUN 2024 | 06243203 | Houston District | 50 | $95.00 | $95.00 | $18.40 | 2 | JAMES CONSTRUCTION GROUP, LLC | TxDOT |
| 06 JUN 2024 | 06243210 | Abilene District | 33 | $93.50 | $88.00 | $85.00 | 3 | RK HALL, LLC | TxDOT |
| 05 JUN 2024 | 06243006 | Brownwood District | 125 | $84.96 | $127.50 | $90.00 | 4 | ALLEN KELLER COMPANY | TxDOT |
| 05 JUN 2024 | 06243048 | Atlanta District | 100 | $105.00 | $117.50 | $115.00 | 8 | THK CONSTRUCTION LLC | TxDOT |
| 05 APR 2024 | 04243209 | Yoakum District | 160.32 | $100.00 | $100.80 | $90.00 | 11 | BIG CREEK CONSTRUCTION, LTD. | TxDOT |
| 05 APR 2024 | 04243222 | Brownwood District | 340 | $85.00 | $110.00 | $100.00 | 3 | HJC FARMS, INC. | TxDOT |
| 04 APR 2024 | 04243018 | Laredo District | 450 | $100.00 | $95.69 | $90.00 | 4 | LUCANIA CONTRACTORS LLC | TxDOT |
| 06 MAR 2024 | 03243201 | Odessa District | 175 | $105.00 | $99.00 | $70.00 | 3 | SUNDT CONSTRUCTION, INC. | TxDOT |
| 06 MAR 2024 | 03243202 | Laredo District | 75 | $110.00 | $108.40 | $85.00 | 2 | ANDERSON COLUMBIA CO., INC. | TxDOT |
| 06 MAR 2024 | 03243208 | Fort Worth District | 40 | $110.00 | $85.00 | $80.88 | 2 | NORTHEASTERN PAVERS, LLC | TxDOT |
| 06 MAR 2024 | 03243228 | Yoakum District | 25 | $140.00 | $119.35 | $75.00 | 6 | R CONSTRUCTION CIVIL, LLC | TxDOT |
| 05 MAR 2024 | 03243008 | Yoakum District | 60 | $104.75 | $120.00 | $100.00 | 3 | HUNTER INDUSTRIES, LTD. | TxDOT |
| 05 MAR 2024 | 03243019 | Fort Worth District | 75 | $81.20 | $80.61 | $100.00 | 4 | PEACHTREE CONSTRUCTION, LTD. | TxDOT |
Filter this item by your own quantity, district and period, or check your price against it, in the TxDOT explorer.
How these prices were read
TxDOT Bid Tabulations open-data export (data.texas.gov) from September 2024, read 21 November 2026, and TxDOT's legacy Tabulation of Bids pages for January 2020 to August 2024. The legacy pages are a large sample, not every contract: their file names were reused from year to year. Their district is the one TxDOT gives the county. Bids that did not match their published total are left out.
- Statistics leave out bids over three times the low bid, zero or negative prices and token prices under 5% of the median.
- Item codes and units are TxDOT's own: this item is compared with TxDOT contracts only.
- Prices are bid prices, not paid prices, and are not adjusted for inflation. Use them as a reference range, never as a quote.
Your own bid history, read the same way
Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.