Pav surf prep for mrk (med nose) unit price, Texas
Low bidders on TxDOT contracts carried a median of $50.00 per EACH for item 6786024, pav surf prep for mrk (med nose), from 09 JAN 2020 to 06 JUN 2024, across 41 low bids. Half of all 149 bids fell between $15.00 and $100.00.
- Owner
- Texas DOT
- Item
- 6786024
- Unit
- EACH
- Latest letting
- 06 JUN 2024
By year of letting
| Year | Contracts | Low bids | Low-bid median | All bids | Median, all bids |
|---|---|---|---|---|---|
| 2020 | 7 | 7 | $28.75 | 41 | $35.00 |
| 2021 | 11 | 10 | $43.00 | 36 | $30.78 |
| 2022 | 8 | 8 | $50.00 | 21 | $55.00 |
| 2023 | 8 | 8 | $42.50 | 20 | $42.50 |
| 2024 | 9 | 8 | $77.50 | 31 | $55.00 |
Bid prices as published, not adjusted for inflation.
By district
| District | Low bids | Low-bid median | All bids | Median, all bids |
|---|---|---|---|---|
| Houston District | 9 | $10.00 | 49 | $10.81 |
| San Antonio District | 6 | $60.00 | 27 | $64.60 |
| Lubbock District | 7 | $120.00 | 20 | $75.00 |
| Austin District | 6 | $18.00 | 13 | $50.00 |
| El Paso District | 4 | $82.50 | 7 | $60.00 |
Districts with at least three low bids, over all lettings.
By quantity
| Quantity (EACH) | Low bids | Low-bid median |
|---|---|---|
| 1 to 2 | 10 | $24.50 |
| 2 to 4 | 10 | $76.00 |
| 4 to 7 | 10 | $30.88 |
| 7 to 31 | 11 | $100.00 |
The low bids split into four bands of equal count by the quantity on the contract. Larger quantities usually carry lower unit prices.
Latest contracts with this item
| Let | Contract | District | Quantity | Low bidder's price | Median | Estimate | Bids | Low bidder | Source |
|---|---|---|---|---|---|---|---|---|---|
| 06 JUN 2024 | 06243202 | Houston District | 1 | n/a | $55.00 | $10.60 | 2 | HARPER BROTHERS CONSTRUCTION LLC | TxDOT |
| 04 APR 2024 | 04243041 | Lubbock District | 2 | $55.00 | $63.45 | $80.00 | 4 | A. L. HELMCAMP, INC. | TxDOT |
| 06 MAR 2024 | 03243201 | Odessa District | 12 | $100.00 | $121.50 | $45.00 | 3 | SUNDT CONSTRUCTION, INC. | TxDOT |
| 06 MAR 2024 | 03243203 | Lubbock District | 10 | $120.00 | $76.00 | $150.00 | 2 | DUININCK, INC. | TxDOT |
| 01 FEB 2024 | 02243002 | Lubbock District | 1 | $34.00 | $34.00 | $75.00 | 2 | DUININCK, INC. | TxDOT |
| 01 FEB 2024 | 02243025 | Austin District | 2 | $25.00 | $25.00 | $34.00 | 3 | AUSTIN TRAFFIC SIGNAL CONSTRUCTION CO., INC. | TxDOT |
| 05 JAN 2024 | 01243228 | El Paso District | 31 | $105.00 | $113.29 | $75.00 | 2 | TRI STATE ELECTRIC, LTD. | TxDOT |
| 05 JAN 2024 | 01243231 | Odessa District | 2 | $113.05 | $150.00 | $50.00 | 3 | REECE ALBERT, INC. | TxDOT |
| 04 JAN 2024 | 01243005 | Houston District | 4 | $10.60 | $10.71 | $90.00 | 10 | SER CONSTRUCTION PARTNERS, LLC | TxDOT |
| 02 NOV 2023 | 11233213 | El Paso District | 10 | $135.00 | $135.00 | $40.00 | 1 | TRI STATE ELECTRIC, LTD. | TxDOT |
| 02 NOV 2023 | 11233214 | San Antonio District | 2 | $75.00 | $75.00 | $35.00 | 3 | E-Z BEL CONSTRUCTION, LLC | TxDOT |
| 07 SEP 2023 | 09233229 | Austin District | 6 | $300.00 | $210.00 | $46.51 | 2 | FNH CONSTRUCTION, LLC | TxDOT |
| 02 AUG 2023 | 08233039 | Bryan District | 1 | $5.50 | $6.00 | $300.00 | 3 | TI-ZACK CONCRETE, INC. | TxDOT |
| 02 AUG 2023 | 08233046 | Houston District | 21 | $10.00 | $17.50 | $5.00 | 2 | BATTERSON, LLP | TxDOT |
| 02 JUN 2023 | 06233227 | Austin District | 6 | $50.00 | $50.00 | $11.00 | 3 | E-Z BEL CONSTRUCTION, LLC | TxDOT |
Filter this item by your own quantity, district and period, or check your price against it, in the TxDOT explorer.
How these prices were read
TxDOT Bid Tabulations open-data export (data.texas.gov) from September 2024, read 21 November 2026, and TxDOT's legacy Tabulation of Bids pages for January 2020 to August 2024. The legacy pages are a large sample, not every contract: their file names were reused from year to year. Their district is the one TxDOT gives the county. Bids that did not match their published total are left out.
- Statistics leave out bids over three times the low bid, zero or negative prices and token prices under 5% of the median.
- Item codes and units are TxDOT's own: this item is compared with TxDOT contracts only.
- Prices are bid prices, not paid prices, and are not adjusted for inflation. Use them as a reference range, never as a quote.
Your own bid history, read the same way
Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.