Pavement sealer (med nose) unit price, Texas
Low bidders on TxDOT contracts carried a median of $120.00 per EACH for item 6666233007, pavement sealer (med nose), from 06 FEB 2020 to 06 JUN 2024, across 57 low bids. Half of all 252 bids fell between $60.00 and $194.25.
- Owner
- Texas DOT
- Item
- 6666233007
- Unit
- EACH
- Latest letting
- 06 JUN 2024
By year of letting
| Year | Contracts | Low bids | Low-bid median | All bids | Median, all bids |
|---|---|---|---|---|---|
| 2020 | 8 | 8 | $104.50 | 47 | $182.00 |
| 2021 | 20 | 19 | $150.00 | 97 | $115.00 |
| 2022 | 11 | 11 | $195.00 | 34 | $182.62 |
| 2023 | 12 | 11 | $95.00 | 38 | $97.00 |
| 2024 | 9 | 8 | $87.50 | 36 | $100.00 |
Bid prices as published, not adjusted for inflation.
By district
| District | Low bids | Low-bid median | All bids | Median, all bids |
|---|---|---|---|---|
| San Antonio District | 43 | $125.00 | 193 | $150.00 |
| Lubbock District | 3 | $225.00 | 7 | $225.00 |
Districts with at least three low bids, over all lettings.
By quantity
| Quantity (EACH) | Low bids | Low-bid median |
|---|---|---|
| 1 to 1 | 14 | $188.00 |
| 1 to 2 | 14 | $85.00 |
| 2 to 7 | 14 | $100.00 |
| 7 to 30 | 15 | $107.44 |
The low bids split into four bands of equal count by the quantity on the contract. Larger quantities usually carry lower unit prices.
Latest contracts with this item
| Let | Contract | District | Quantity | Low bidder's price | Median | Estimate | Bids | Low bidder | Source |
|---|---|---|---|---|---|---|---|---|---|
| 06 JUN 2024 | 06243202 | Houston District | 1 | n/a | $55.00 | $100.00 | 2 | HARPER BROTHERS CONSTRUCTION LLC | TxDOT |
| 02 MAY 2024 | 05243027 | San Antonio District | 30 | $125.00 | $60.00 | $130.00 | 3 | INTERSTATE BARRICADES & MARKINGS, INC. | TxDOT |
| 02 MAY 2024 | 05243032 | San Antonio District | 1 | $45.00 | $117.50 | $190.95 | 4 | E-Z BEL CONSTRUCTION, LLC | TxDOT |
| 05 APR 2024 | 04243208 | San Antonio District | 2 | $100.00 | $156.00 | $103.00 | 6 | ENCINO LANDSCAPE, INC. | TxDOT |
| 06 MAR 2024 | 03243201 | Odessa District | 12 | $75.00 | $60.12 | $100.00 | 3 | SUNDT CONSTRUCTION, INC. | TxDOT |
| 02 FEB 2024 | 02243205 | San Antonio District | 2 | $660.00 | $660.00 | $150.00 | 9 | DAN WILLIAMS COMPANY | TxDOT |
| 01 FEB 2024 | 02243031 | San Antonio District | 1 | $60.00 | $69.00 | $190.95 | 3 | E-Z BEL CONSTRUCTION, LLC | TxDOT |
| 05 JAN 2024 | 01243203 | San Antonio District | 4 | $35.00 | $35.00 | $193.00 | 3 | HUNTER INDUSTRIES, LTD. | TxDOT |
| 05 JAN 2024 | 01243231 | Odessa District | 2 | $169.58 | $225.00 | $100.00 | 3 | REECE ALBERT, INC. | TxDOT |
| 02 NOV 2023 | 11233213 | El Paso District | 10 | $125.00 | $125.00 | $50.00 | 1 | TRI STATE ELECTRIC, LTD. | TxDOT |
| 02 NOV 2023 | 11233214 | San Antonio District | 2 | $95.00 | $95.00 | $137.00 | 3 | E-Z BEL CONSTRUCTION, LLC | TxDOT |
| 01 NOV 2023 | 11233028 | San Antonio District | 22 | $107.44 | $107.00 | $125.00 | 3 | AUSTIN BRIDGE & ROAD SERVICES, LP | TxDOT |
| 02 AUG 2023 | 08233002 | San Antonio District | 7 | $36.00 | $117.00 | $200.00 | 2 | JORDAN FOSTER CONSTRUCTION, LLC | TxDOT |
| 02 AUG 2023 | 08233033 | San Antonio District | 1 | $350.00 | $215.50 | $180.00 | 4 | J3 COMPANY, LLC | TxDOT |
| 02 AUG 2023 | 08233039 | Bryan District | 1 | $16.50 | $18.00 | $500.00 | 3 | TI-ZACK CONCRETE, INC. | TxDOT |
Filter this item by your own quantity, district and period, or check your price against it, in the TxDOT explorer.
How these prices were read
TxDOT Bid Tabulations open-data export (data.texas.gov) from September 2024, read 21 November 2026, and TxDOT's legacy Tabulation of Bids pages for January 2020 to August 2024. The legacy pages are a large sample, not every contract: their file names were reused from year to year. Their district is the one TxDOT gives the county. Bids that did not match their published total are left out.
- Statistics leave out bids over three times the low bid, zero or negative prices and token prices under 5% of the median.
- Item codes and units are TxDOT's own: this item is compared with TxDOT contracts only.
- Prices are bid prices, not paid prices, and are not adjusted for inflation. Use them as a reference range, never as a quote.