Port ctb (remove)(low prof)(ty 1) unit price, Texas
Low bidders on TxDOT contracts carried a median of $10.81 per LF for item 5126057, port ctb (remove)(low prof)(ty 1), from 09 JAN 2020 to 02 AUG 2024, across 213 low bids. Half of all 1,012 bids fell between $8.34 and $18.00.
- Owner
- Texas DOT
- Item
- 5126057
- Unit
- LF
- Latest letting
- 02 AUG 2024
By year of letting
| Year | Contracts | Low bids | Low-bid median | All bids | Median, all bids |
|---|---|---|---|---|---|
| 2020 | 45 | 45 | $10.00 | 249 | $10.50 |
| 2021 | 50 | 50 | $10.00 | 309 | $10.50 |
| 2022 | 40 | 40 | $10.90 | 156 | $13.00 |
| 2023 | 37 | 37 | $13.00 | 131 | $13.50 |
| 2024 | 41 | 41 | $12.00 | 167 | $16.00 |
Bid prices as published, not adjusted for inflation.
By district
| District | Low bids | Low-bid median | All bids | Median, all bids |
|---|---|---|---|---|
| San Antonio District | 41 | $10.00 | 244 | $11.91 |
| Dallas District | 24 | $9.91 | 125 | $10.50 |
| Austin District | 18 | $11.52 | 94 | $11.01 |
| Fort Worth District | 17 | $12.52 | 77 | $13.00 |
| Yoakum District | 15 | $15.00 | 70 | $15.00 |
| Houston District | 13 | $11.79 | 59 | $10.00 |
| Bryan District | 9 | $15.00 | 53 | $14.00 |
| Odessa District | 10 | $9.62 | 49 | $10.00 |
| Pharr District | 12 | $7.00 | 48 | $9.50 |
| Laredo District | 9 | $12.00 | 36 | $15.47 |
| Wichita Falls District | 8 | $11.87 | 34 | $15.00 |
| Corpus Christi District | 8 | $11.75 | 30 | $12.00 |
Districts with at least three low bids, over all lettings.
By quantity
| Quantity (LF) | Low bids | Low-bid median |
|---|---|---|
| 20 to 560 | 53 | $16.29 |
| 560 to 1,940 | 53 | $12.00 |
| 1,940 to 5,960 | 53 | $9.80 |
| 6,060 to 109,460 | 54 | $8.00 |
The low bids split into four bands of equal count by the quantity on the contract. Larger quantities usually carry lower unit prices.
Latest contracts with this item
| Let | Contract | District | Quantity | Low bidder's price | Median | Estimate | Bids | Low bidder | Source |
|---|---|---|---|---|---|---|---|---|---|
| 02 AUG 2024 | 08243202 | Houston District | 5,540 | $11.98 | $15.99 | $14.50 | 4 | JAMES CONSTRUCTION GROUP, LLC | TxDOT |
| 01 AUG 2024 | 08243001 | Houston District | 5,040 | $16.67 | $10.84 | $14.00 | 2 | WEBBER, LLC | TxDOT |
| 10 JUL 2024 | 07243201 | Dallas District | 16,060 | $9.82 | $13.26 | $6.00 | 2 | AUSTIN BRIDGE & ROAD SERVICES, LP | TxDOT |
| 10 JUL 2024 | 07243207 | Dallas District | 360 | $11.00 | $11.50 | $10.00 | 6 | HARPER BROTHERS CONSTRUCTION LLC | TxDOT |
| 10 JUL 2024 | 07243208 | San Antonio District | 40 | $49.30 | $75.15 | $20.92 | 8 | ACME BRIDGE COMPANY, INC. | TxDOT |
| 09 JUL 2024 | 07243001 | Fort Worth District | 19,400 | $7.49 | $10.14 | $16.00 | 2 | ZACHRY CONSTRUCTION CORPORATION | TxDOT |
| 06 JUN 2024 | 06243201 | San Antonio District | 20,060 | $9.70 | $11.50 | $12.00 | 5 | WEBBER, LLC | TxDOT |
| 06 JUN 2024 | 06243205 | Wichita Falls District | 300 | $75.00 | $75.00 | $7.00 | 3 | A. L. HELMCAMP, INC. | TxDOT |
| 06 JUN 2024 | 06243215 | San Antonio District | 1,520 | $2.90 | $19.37 | $15.00 | 8 | SALINAS CONSTRUCTION TECHNOLOGIES, LTD. | TxDOT |
| 06 JUN 2024 | 06243228 | Fort Worth District | 1,600 | $10.00 | $30.00 | $20.00 | 2 | RAGLE CONSTRUCTION, INC. | TxDOT |
| 06 JUN 2024 | 06243254 | Yoakum District | 200 | $12.00 | $20.00 | $30.00 | 5 | STX CIVIL | TxDOT |
| 05 JUN 2024 | 06243008 | Wichita Falls District | 500 | $36.00 | $34.50 | $74.00 | 4 | A. L. HELMCAMP, INC. | TxDOT |
| 05 JUN 2024 | 06243027 | Fort Worth District | 1,960 | $30.00 | $30.00 | $32.00 | 2 | FNH CONSTRUCTION, LLC | TxDOT |
| 05 JUN 2024 | 06243034 | Lufkin District | 20 | $495.37 | $495.37 | $20.00 | 1 | TEXAS MATERIALS GROUP, INC. | TxDOT |
| 05 JUN 2024 | 06243049 | Laredo District | 2,180 | $9.39 | $16.00 | $25.00 | 6 | J. CARROLL WEAVER, INC. | TxDOT |
Filter this item by your own quantity, district and period, or check your price against it, in the TxDOT explorer.
How these prices were read
TxDOT Bid Tabulations open-data export (data.texas.gov) from September 2024, read 21 November 2026, and TxDOT's legacy Tabulation of Bids pages for January 2020 to August 2024. The legacy pages are a large sample, not every contract: their file names were reused from year to year. Their district is the one TxDOT gives the county. Bids that did not match their published total are left out.
- Statistics leave out bids over three times the low bid, zero or negative prices and token prices under 5% of the median.
- Item codes and units are TxDOT's own: this item is compared with TxDOT contracts only.
- Prices are bid prices, not paid prices, and are not adjusted for inflation. Use them as a reference range, never as a quote.