Prefab pm ty c (w)(18")(yld tri) unit price, Texas

Low bidders on TxDOT contracts carried a median of $30.00 per EACH for item 668-7110, prefab pm ty c (w)(18")(yld tri), over the 24 months to 19 NOV 2026, across 47 low bids. Half of all 231 bids fell between $25.00 and $55.00.

Owner
Texas DOT
Item
668-7110
Unit
EACH
Latest letting
04 NOV 2026
$30.00Low bidder's median, per EACH
$37.50Median of all bids, per EACH
47Contracts in the window
$36.00Engineer's estimate, median per EACH

By year of letting

Prefab pm ty c (w)(18")(yld tri), TxDOT: unit prices by year
YearContractsLow bidsLow-bid medianAll bidsMedian, all bids
202433$30.0014$63.75
20252323$30.00114$35.00
20262222$31.00105$38.00
Prefab pm ty c (w)(18")(yld tri), TxDOT: unit prices by year

Bid prices as published, not adjusted for inflation.

By district

Prefab pm ty c (w)(18")(yld tri), TxDOT: unit prices by district, last 24 months
DistrictLow bidsLow-bid medianAll bidsMedian, all bids
Yoakum District8$45.7544$39.27
Corpus Christi District8$16.2535$25.00
Waco District4$62.5026$34.50
Dallas District4$26.7523$40.70
Odessa District3$19.8019$30.00
Bryan District3$32.0017$32.00
Houston District4$53.0014$50.00
Tyler District4$30.0013$30.00
Prefab pm ty c (w)(18")(yld tri), TxDOT: unit prices by district, last 24 months

Districts with at least three low bids, over the last 24 months.

By quantity

Prefab pm ty c (w)(18")(yld tri), TxDOT: low bidder's median by quantity band
Quantity (EACH)Low bidsLow-bid median
3 to 811$35.00
10 to 2212$40.00
24 to 5812$36.00
81 to 1,01312$23.50
Prefab pm ty c (w)(18")(yld tri), TxDOT: low bidder's median by quantity band

The low bids split into four bands of equal count by the quantity on the contract. Larger quantities usually carry lower unit prices.

Latest contracts with this item

Latest TxDOT contracts carrying Prefab pm ty c (w)(18")(yld tri)
LetContractDistrictQuantityLow bidder's priceMedianEstimateBidsLow bidderSource
04 NOV 2026A00208598Yoakum District587$9.00$22.50n/a4RONALD R. WAGNER & CO., LPTxDOT
07 OCT 2026A00196467Bryan District34$30.00$30.00n/a4CLARK CONSTRUCTION OF TEXAS, INC.TxDOT
06 OCT 2026A00219476Tyler District15$35.00$42.50$32.002STRIPING TECHNOLOGY, L.P.TxDOT
03 SEP 2026A00198323Dallas District50$9.00$52.50$55.008AMERICAN LIGHTING AND SIGNALIZATION, LLCTxDOT
03 SEP 2026A00207181Yoakum District27$45.50$40.00$70.0073LW CIVIL LLCTxDOT
18 AUG 2026A00221093Yoakum District165$15.00$18.00$30.003PAVEMENT MARKINGS INC.TxDOT
05 AUG 2026A00188161Corpus Christi District3$8.00$35.50$8.506TRP INFRASTRUCTURE SERVICES, LLCTxDOT
05 AUG 2026A00214465Beaumont District13$115.00$55.80$35.008DECO CONTRACTORS, INC.TxDOT
05 AUG 2026A00222959Corpus Christi District20$10.00$32.00$10.003TRP INFRASTRUCTURE SERVICES, LLCTxDOT
01 JUL 2026A00187817Odessa District314$5.00$35.00$30.008VIZCAINO, L.P.TxDOT
03 JUN 2026A00132662Abilene District26$42.00$42.00$15.001FNF CONSTRUCTION, INC.TxDOT
02 JUN 2026A00221074Wichita Falls District25$50.00$35.00$30.002TRP INFRASTRUCTURE SERVICES, LLCTxDOT
07 MAY 2026A00031457San Antonio District81$35.00$35.00$18.003WEBBER, LLCTxDOT
06 MAY 2026A00196395Waco District5$100.00$57.50$100.004BIG CREEK CONSTRUCTION, LTD.TxDOT
06 MAY 2026A00219886Waco District110$25.00$25.00$32.005FC TRAFFIC CONTROL, LLCTxDOT
Latest TxDOT contracts carrying Prefab pm ty c (w)(18")(yld tri)

Filter this item by your own quantity, district and period, or check your price against it, in the TxDOT explorer.

How these prices were read

TxDOT Bid Tabulations open-data export (data.texas.gov) from September 2024, read 21 November 2026, and TxDOT's legacy Tabulation of Bids pages for January 2020 to August 2024. The legacy pages are a large sample, not every contract: their file names were reused from year to year. Their district is the one TxDOT gives the county. Bids that did not match their published total are left out.

  • Statistics leave out bids over three times the low bid, zero or negative prices and token prices under 5% of the median.
  • Item codes and units are TxDOT's own: this item is compared with TxDOT contracts only.
  • Prices are bid prices, not paid prices, and are not adjusted for inflation. Use them as a reference range, never as a quote.

Your own bid history, read the same way

Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.

We use your email to reply to you and, now and then, to tell you about Mirage. You can opt out at any time. Privacy policy