Prep row (tree)(greater than 24" dia) unit price, Texas

Low bidders on TxDOT contracts carried a median of $1,813.15 per EACH for item 1006007, prep row (tree)(greater than 24" dia), from 06 FEB 2020 to 10 JUL 2024, across 46 low bids. Half of all 255 bids fell between $1,185.88 and $2,959.20.

Owner
Texas DOT
Item
1006007
Unit
EACH
Latest letting
10 JUL 2024
$1,813.15Low bidder's median, per EACH
$1,995.96Median of all bids, per EACH
46Contracts in the window
$2,000.00Engineer's estimate, median per EACH

By year of letting

Prep row (tree)(greater than 24" dia), TxDOT: unit prices by year
YearContractsLow bidsLow-bid medianAll bidsMedian, all bids
20201313$1,100.0091$1,500.00
20211313$2,000.0081$1,800.00
202255$1,600.0019$2,000.00
202355$2,000.0015$2,000.00
20241010$2,000.0049$2,880.00
Prep row (tree)(greater than 24" dia), TxDOT: unit prices by year

Bid prices as published, not adjusted for inflation.

By district

Prep row (tree)(greater than 24" dia), TxDOT: unit prices by district, all lettings
DistrictLow bidsLow-bid medianAll bidsMedian, all bids
Corpus Christi District6$1,120.0043$1,500.00
Houston District5$1,926.3031$2,174.44
Austin District5$2,000.0023$2,000.00
Amarillo District4$977.5019$1,500.00
Fort Worth District3$900.0018$837.50
Yoakum District3$2,100.0015$2,500.00
Prep row (tree)(greater than 24" dia), TxDOT: unit prices by district, all lettings

Districts with at least three low bids, over all lettings.

By quantity

Prep row (tree)(greater than 24" dia), TxDOT: low bidder's median by quantity band
Quantity (EACH)Low bidsLow-bid median
1 to 211$2,539.57
2 to 512$1,750.00
5 to 1211$1,926.30
16 to 19212$1,017.89
Prep row (tree)(greater than 24" dia), TxDOT: low bidder's median by quantity band

The low bids split into four bands of equal count by the quantity on the contract. Larger quantities usually carry lower unit prices.

Latest contracts with this item

Latest TxDOT contracts carrying Prep row (tree)(greater than 24" dia)
LetContractDistrictQuantityLow bidder's priceMedianEstimateBidsLow bidderSource
10 JUL 202407243219Austin District10$2,290.00$3,395.00$3,100.002SCR CIVIL CONSTRUCTION, LLCTxDOT
10 JUL 202407243226Austin District10$725.00$2,300.00$3,100.003TAYLOR CONTRACTING LLCTxDOT
09 JUL 202407243009Houston District3$3,500.00$2,940.00$1,250.008BRICE CONSTRUCTION AND DESIGN LLCTxDOT
09 JUL 202407243017Austin District10$2,000.00$2,200.00$3,100.006GARRET SHIELDS INFRASTRUCTURETxDOT
06 JUN 202406243225San Angelo District2$3,500.00$4,375.00$1,800.003RELMCO, INC.TxDOT
06 JUN 202406243231Houston District10$1,926.30$2,250.00$3,150.006SER CONSTRUCTION PARTNERS, LLCTxDOT
05 JUN 202406243003Pharr District11$200.00$1,350.00$2,400.002IOC COMPANY LLCTxDOT
03 MAY 202405243235Paris District2$1,500.00$3,785.00$3,100.007ENCINO LANDSCAPE, INC.TxDOT
02 MAY 202405243018Corpus Christi District20$2,000.00$1,695.00$1,889.008CK NEWBERRY, LLCTxDOT
05 JAN 202401243227Abilene District1$4,200.00$4,100.00$2,500.004A GREATER AUSTIN DEVELOPMENT COMPANY, LLCTxDOT
27 JUN 202306233407El Paso District190$720.00$472.50$900.002JORDAN FOSTER CONSTRUCTION, LLCTxDOT
27 JUN 202306233457Lubbock District6$3,000.00$2,500.00$2,000.002WEBBER, LLCTxDOT
05 MAY 202305233206Brownwood District24$1,200.00$1,975.00$1,955.004JAY MILLS CONTRACTING, INCORPORATEDTxDOT
05 MAY 202305233224Yoakum District1$2,000.00$2,000.00$2,000.003ENCINO LANDSCAPE, INC.TxDOT
08 MAR 202303233216Fort Worth District25$3,600.00$1,800.00$900.004DUININCK, INC.TxDOT
Latest TxDOT contracts carrying Prep row (tree)(greater than 24" dia)

Filter this item by your own quantity, district and period, or check your price against it, in the TxDOT explorer.

How these prices were read

TxDOT Bid Tabulations open-data export (data.texas.gov) from September 2024, read 21 November 2026, and TxDOT's legacy Tabulation of Bids pages for January 2020 to August 2024. The legacy pages are a large sample, not every contract: their file names were reused from year to year. Their district is the one TxDOT gives the county. Bids that did not match their published total are left out.

  • Statistics leave out bids over three times the low bid, zero or negative prices and token prices under 5% of the median.
  • Item codes and units are TxDOT's own: this item is compared with TxDOT contracts only.
  • Prices are bid prices, not paid prices, and are not adjusted for inflation. Use them as a reference range, never as a quote.

Your own bid history, read the same way

Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.