Prestr conc girder (TX46) unit price, Texas
Low bidders on TxDOT contracts carried a median of $150.00 per LF for item 4256038, prestr conc girder (tx46), from 10 JAN 2020 to 03 AUG 2023, across 43 low bids. Half of all 238 bids fell between $136.25 and $190.00.
- Owner
- Texas DOT
- Item
- 4256038
- Unit
- LF
- Latest letting
- 03 AUG 2023
By year of letting
| Year | Contracts | Low bids | Low-bid median | All bids | Median, all bids |
|---|---|---|---|---|---|
| 2020 | 15 | 15 | $140.00 | 101 | $142.00 |
| 2021 | 19 | 19 | $150.00 | 101 | $152.70 |
| 2022 | 7 | 7 | $229.65 | 32 | $231.32 |
| 2023 | 2 | 2 | $349.10 | 4 | $282.50 |
Bid prices as published, not adjusted for inflation.
By district
| District | Low bids | Low-bid median | All bids | Median, all bids |
|---|---|---|---|---|
| Dallas District | 5 | $140.00 | 47 | $144.00 |
| San Antonio District | 5 | $125.00 | 35 | $132.00 |
| Yoakum District | 6 | $184.24 | 29 | $151.62 |
| Brownwood District | 3 | $264.00 | 14 | $259.50 |
| Houston District | 4 | $127.50 | 13 | $152.00 |
Districts with at least three low bids, over all lettings.
By quantity
| Quantity (LF) | Low bids | Low-bid median |
|---|---|---|
| 398 to 1,942.30 | 10 | $162.50 |
| 1,970.88 to 2,881.17 | 11 | $176.00 |
| 3,340.34 to 5,600 | 11 | $150.00 |
| 7,275.93 to 27,753.99 | 11 | $132.57 |
The low bids split into four bands of equal count by the quantity on the contract. Larger quantities usually carry lower unit prices.
Latest contracts with this item
| Let | Contract | District | Quantity | Low bidder's price | Median | Estimate | Bids | Low bidder | Source |
|---|---|---|---|---|---|---|---|---|---|
| 03 AUG 2023 | 08233209 | Lubbock District | 3,340.34 | $508.20 | $436.60 | $250.00 | 2 | WEBBER, LLC | TxDOT |
| 28 JUN 2023 | 06233602 | Yoakum District | 19,328.86 | $190.00 | $195.00 | $200.00 | 2 | WEBBER, LLC | TxDOT |
| 30 JUN 2022 | 06223601 | Dallas District | 1,193.79 | $185.00 | $199.19 | $127.00 | 5 | WEBBER, LLC | TxDOT |
| 30 JUN 2022 | 06223612 | Amarillo District | 2,089.50 | $275.00 | $275.00 | $220.00 | 3 | J. LEE MILLIGAN, INC. | TxDOT |
| 30 JUN 2022 | 06223617 | Yoakum District | 2,388 | $188.48 | $195.00 | $150.00 | 6 | SB CONTRACTORS LLC | TxDOT |
| 02 JUN 2022 | 06223201 | Lufkin District | 13,020.04 | $229.65 | $215.00 | $160.00 | 5 | LONGVIEW BRIDGE AND ROAD, LTD. | TxDOT |
| 04 MAR 2022 | 03223213 | Brownwood District | 714 | $264.00 | $325.00 | $230.00 | 5 | ACME BRIDGE COMPANY, INC. | TxDOT |
| 03 MAR 2022 | 03223001 | Beaumont District | 1,075.99 | $125.00 | $168.00 | $140.00 | 3 | WILLIAMS BROTHERS CONSTRUCTION CO., INC. | TxDOT |
| 07 JAN 2022 | 01223216 | Brownwood District | 478 | $310.00 | $265.00 | $230.00 | 5 | KNIFE RIVER CORPORATION - SOUTH | TxDOT |
| 04 NOV 2021 | 11213219 | Yoakum District | 1,970.88 | $180.00 | $175.00 | $160.00 | 2 | RAGLE CONSTRUCTION, INC. | TxDOT |
| 05 AUG 2021 | 08213201 | Houston District | 11,402.95 | $110.00 | $105.00 | $133.79 | 2 | WILLIAMS BROTHERS CONSTRUCTION CO., INC. | TxDOT |
| 05 AUG 2021 | 08213204 | Houston District | 4,299 | $156.43 | $154.22 | $143.25 | 2 | JAMES CONSTRUCTION GROUP, LLC | TxDOT |
| 05 AUG 2021 | 08213209 | Lubbock District | 2,794.40 | $176.00 | $195.00 | $150.00 | 5 | ALLEN BUTLER CONSTRUCTION, INC. | TxDOT |
| 05 AUG 2021 | 08213233 | Austin District | 3,366.49 | $165.00 | $200.00 | $170.00 | 3 | RELMCO, INC. | TxDOT |
| 05 AUG 2021 | 08213257 | Tyler District | 398 | $130.00 | $214.11 | $145.00 | 8 | ENCINO LANDSCAPE, INC. | TxDOT |
Filter this item by your own quantity, district and period, or check your price against it, in the TxDOT explorer.
How these prices were read
TxDOT Bid Tabulations open-data export (data.texas.gov) from September 2024, read 21 November 2026, and TxDOT's legacy Tabulation of Bids pages for January 2020 to August 2024. The legacy pages are a large sample, not every contract: their file names were reused from year to year. Their district is the one TxDOT gives the county. Bids that did not match their published total are left out.
- Statistics leave out bids over three times the low bid, zero or negative prices and token prices under 5% of the median.
- Item codes and units are TxDOT's own: this item is compared with TxDOT contracts only.
- Prices are bid prices, not paid prices, and are not adjusted for inflation. Use them as a reference range, never as a quote.
Your own bid history, read the same way
Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.