Low bidders on TxDOT contracts carried a median of $84.37 per LF for item 4506023001, rail (ty sstr), from 04 FEB 2022 to 02 AUG 2024, across 119 low bids. Half of all 442 bids fell between $61.11 and $154.00.
- Owner
- Texas DOT
- Item
- 4506023001
- Unit
- LF
- Latest letting
- 02 AUG 2024
By year of letting
| Year | Contracts | Low bids | Low-bid median | All bids | Median, all bids |
|---|---|---|---|---|---|
| 2022 | 33 | 33 | $75.00 | 144 | $75.00 |
| 2023 | 41 | 41 | $112.22 | 139 | $98.61 |
| 2024 | 45 | 45 | $101.51 | 159 | $109.79 |
Bid prices as published, not adjusted for inflation.
By district
| District | Low bids | Low-bid median | All bids | Median, all bids |
|---|---|---|---|---|
| Houston District | 15 | $54.91 | 90 | $63.27 |
| Dallas District | 10 | $65.41 | 35 | $70.00 |
| Yoakum District | 11 | $77.00 | 33 | $110.00 |
| Corpus Christi District | 9 | $180.00 | 32 | $114.59 |
| Childress District | 7 | $140.00 | 28 | $152.31 |
| Abilene District | 9 | $163.00 | 25 | $175.00 |
| San Angelo District | 6 | $193.09 | 23 | $220.00 |
| Pharr District | 6 | $85.50 | 23 | $120.00 |
| Fort Worth District | 6 | $67.58 | 22 | $85.32 |
| San Antonio District | 4 | $69.44 | 19 | $81.90 |
| Austin District | 4 | $109.47 | 17 | $103.95 |
| Amarillo District | 5 | $117.00 | 14 | $132.31 |
Districts with at least three low bids, over all lettings.
By quantity
| Quantity (LF) | Low bids | Low-bid median |
|---|---|---|
| 20 to 422 | 29 | $158.97 |
| 436 to 1,860 | 30 | $125.00 |
| 2,075 to 9,188 | 30 | $69.18 |
| 9,269 to 152,098.10 | 30 | $57.40 |
The low bids split into four bands of equal count by the quantity on the contract. Larger quantities usually carry lower unit prices.
Latest contracts with this item
| Let | Contract | District | Quantity | Low bidder's price | Median | Estimate | Bids | Low bidder | Source |
|---|---|---|---|---|---|---|---|---|---|
| 02 AUG 2024 | 08243201 | Pharr District | 12,400.20 | $45.00 | $64.00 | $65.00 | 3 | FOREMOST PAVING, INC. | TxDOT |
| 02 AUG 2024 | 08243202 | Houston District | 8,279.60 | $51.20 | $57.11 | $60.00 | 4 | JAMES CONSTRUCTION GROUP, LLC | TxDOT |
| 02 AUG 2024 | 08243203 | San Angelo District | 2,685.90 | $203.50 | $209.26 | $150.00 | 5 | RK HALL, LLC | TxDOT |
| 01 AUG 2024 | 08243001 | Houston District | 33,658.20 | $50.84 | $52.92 | $55.00 | 2 | WEBBER, LLC | TxDOT |
| 10 JUL 2024 | 07243201 | Dallas District | 64,708 | $69.11 | $65.56 | $45.00 | 2 | AUSTIN BRIDGE & ROAD SERVICES, LP | TxDOT |
| 10 JUL 2024 | 07243204 | Yoakum District | 143 | $269.10 | $247.05 | $200.00 | 6 | HUNTER INDUSTRIES, LTD. | TxDOT |
| 10 JUL 2024 | 07243211 | Childress District | 1,588 | $140.32 | $160.00 | $150.00 | 5 | C. E. BARKER, LTD. | TxDOT |
| 10 JUL 2024 | 07243224 | Childress District | 640 | $150.00 | $191.62 | $210.00 | 6 | SKYLINE BRIDGE LLC | TxDOT |
| 09 JUL 2024 | 07243001 | Fort Worth District | 49,596 | $55.00 | $53.38 | $77.00 | 2 | ZACHRY CONSTRUCTION CORPORATION | TxDOT |
| 09 JUL 2024 | 07243002 | El Paso District | 43,440 | $80.00 | $94.90 | $75.00 | 2 | SUNDT CONSTRUCTION, INC. | TxDOT |
| 09 JUL 2024 | 07243005 | Abilene District | 2,926 | $105.00 | $105.00 | $100.00 | 3 | FNF CONSTRUCTION, INC. | TxDOT |
| 06 JUN 2024 | 06243201 | San Antonio District | 30,791.40 | $63.68 | $63.68 | $66.00 | 5 | WEBBER, LLC | TxDOT |
| 06 JUN 2024 | 06243203 | Houston District | 8,425 | $51.68 | $55.59 | $43.00 | 2 | JAMES CONSTRUCTION GROUP, LLC | TxDOT |
| 06 JUN 2024 | 06243206 | Childress District | 2,869.20 | $125.00 | $125.00 | $130.00 | 4 | MORTMARA CONSTRUCTION, INC. | TxDOT |
| 06 JUN 2024 | 06243237 | Abilene District | 468 | $168.73 | $175.00 | $900.00 | 5 | TALBERT COMPANIES LLC | TxDOT |
Filter this item by your own quantity, district and period, or check your price against it, in the TxDOT explorer.
How these prices were read
TxDOT Bid Tabulations open-data export (data.texas.gov) from September 2024, read 21 November 2026, and TxDOT's legacy Tabulation of Bids pages for January 2020 to August 2024. The legacy pages are a large sample, not every contract: their file names were reused from year to year. Their district is the one TxDOT gives the county. Bids that did not match their published total are left out.
- Statistics leave out bids over three times the low bid, zero or negative prices and token prices under 5% of the median.
- Item codes and units are TxDOT's own: this item is compared with TxDOT contracts only.
- Prices are bid prices, not paid prices, and are not adjusted for inflation. Use them as a reference range, never as a quote.
Your own bid history, read the same way
Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.