Re pm w/ret req ty i (y)4"(brk)(100MIL) unit price, Texas
Low bidders on TxDOT contracts carried a median of $0.47 per LF for item 6666312007, re pm w/ret req ty i (y)4"(brk)(100mil), from 09 JAN 2020 to 03 MAY 2024, across 504 low bids. Half of all 2,388 bids fell between $0.36 and $0.66.
- Owner
- Texas DOT
- Item
- 6666312007
- Unit
- LF
- Latest letting
- 03 MAY 2024
By year of letting
| Year | Contracts | Low bids | Low-bid median | All bids | Median, all bids |
|---|---|---|---|---|---|
| 2020 | 160 | 160 | $0.45 | 823 | $0.45 |
| 2021 | 171 | 170 | $0.42 | 916 | $0.42 |
| 2022 | 133 | 133 | $0.52 | 506 | $0.53 |
| 2023 | 36 | 36 | $0.69 | 126 | $0.74 |
| 2024 | 5 | 5 | $2.36 | 17 | $2.36 |
Bid prices as published, not adjusted for inflation.
By district
| District | Low bids | Low-bid median | All bids | Median, all bids |
|---|---|---|---|---|
| Austin District | 48 | $0.40 | 254 | $0.40 |
| Dallas District | 39 | $0.50 | 223 | $0.50 |
| San Antonio District | 46 | $0.57 | 216 | $0.50 |
| Fort Worth District | 32 | $0.48 | 165 | $0.48 |
| Tyler District | 38 | $0.51 | 165 | $0.54 |
| Abilene District | 29 | $0.50 | 147 | $0.48 |
| Waco District | 35 | $0.60 | 141 | $0.60 |
| Wichita Falls District | 29 | $0.46 | 137 | $0.44 |
| Odessa District | 27 | $0.51 | 125 | $0.48 |
| Pharr District | 28 | $0.50 | 108 | $0.50 |
| Laredo District | 23 | $0.45 | 90 | $0.50 |
| Childress District | 16 | $0.42 | 84 | $0.45 |
Districts with at least three low bids, over all lettings.
By quantity
| Quantity (LF) | Low bids | Low-bid median |
|---|---|---|
| 20 to 1,016 | 126 | $1.00 |
| 1,020 to 4,000 | 126 | $0.54 |
| 4,033 to 9,730 | 126 | $0.47 |
| 9,920 to 1,439,180 | 126 | $0.33 |
The low bids split into four bands of equal count by the quantity on the contract. Larger quantities usually carry lower unit prices.
Latest contracts with this item
| Let | Contract | District | Quantity | Low bidder's price | Median | Estimate | Bids | Low bidder | Source |
|---|---|---|---|---|---|---|---|---|---|
| 03 MAY 2024 | 05243239 | San Antonio District | 40 | $2.36 | $2.25 | $1.19 | 4 | RELMCO, INC. | TxDOT |
| 02 MAY 2024 | 05243032 | San Antonio District | 120 | $3.00 | $3.40 | $1.85 | 4 | E-Z BEL CONSTRUCTION, LLC | TxDOT |
| 02 FEB 2024 | 02243239 | Lubbock District | 1,847 | $1.20 | $1.20 | $0.75 | 3 | LONE STAR DIRT & PAVING, LTD. | TxDOT |
| 01 FEB 2024 | 02243025 | Austin District | 800 | $3.00 | $3.00 | $1.17 | 3 | AUSTIN TRAFFIC SIGNAL CONSTRUCTION CO., INC. | TxDOT |
| 01 FEB 2024 | 02243031 | San Antonio District | 120 | $1.20 | $1.80 | $1.85 | 3 | E-Z BEL CONSTRUCTION, LLC | TxDOT |
| 02 NOV 2023 | 11233214 | San Antonio District | 160 | $1.11 | $1.11 | $0.31 | 3 | E-Z BEL CONSTRUCTION, LLC | TxDOT |
| 06 SEP 2023 | 09233017 | Dallas District | 50 | $1.00 | $1.20 | $1.00 | 2 | DURABLE SPECIALTIES, INC. | TxDOT |
| 03 AUG 2023 | 08233205 | Fort Worth District | 4,302 | $0.69 | $0.60 | $1.10 | 4 | SEMA CONSTRUCTION, INC. | TxDOT |
| 28 JUN 2023 | 06233607 | Abilene District | 3,142 | $1.00 | $1.20 | $1.00 | 2 | BONTKE BROTHERS CONSTRUCTION COMPANY | TxDOT |
| 28 JUN 2023 | 06233633 | Houston District | 100 | $1.67 | $1.69 | $0.60 | 4 | TRAF-TEX, INC. | TxDOT |
| 27 JUN 2023 | 06233407 | El Paso District | 6,752 | $1.30 | $1.30 | $1.13 | 2 | JORDAN FOSTER CONSTRUCTION, LLC | TxDOT |
| 27 JUN 2023 | 06233457 | Lubbock District | 5,080 | $0.95 | $0.85 | $0.75 | 2 | WEBBER, LLC | TxDOT |
| 02 JUN 2023 | 06233227 | Austin District | 2,835 | $0.90 | $1.10 | $0.76 | 3 | E-Z BEL CONSTRUCTION, LLC | TxDOT |
| 01 JUN 2023 | 06233026 | Pharr District | 280 | $1.00 | $1.00 | $0.48 | 3 | FOREMOST PAVING, INC. | TxDOT |
| 01 JUN 2023 | 06233028 | Childress District | 200 | $2.00 | $4.00 | $0.32 | 2 | HODGES AND SON CONSTRUCTION COMPANY, INC. | TxDOT |
Filter this item by your own quantity, district and period, or check your price against it, in the TxDOT explorer.
How these prices were read
TxDOT Bid Tabulations open-data export (data.texas.gov) from September 2024, read 21 November 2026, and TxDOT's legacy Tabulation of Bids pages for January 2020 to August 2024. The legacy pages are a large sample, not every contract: their file names were reused from year to year. Their district is the one TxDOT gives the county. Bids that did not match their published total are left out.
- Statistics leave out bids over three times the low bid, zero or negative prices and token prices under 5% of the median.
- Item codes and units are TxDOT's own: this item is compared with TxDOT contracts only.
- Prices are bid prices, not paid prices, and are not adjusted for inflation. Use them as a reference range, never as a quote.
Your own bid history, read the same way
Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.